Bid Tabulations
Letting of
08/25/2010
LA DOTD Headquarters
| Lead Project: 006-03-0058 | |
| Parish: Orleans | |
| Routes: US 90 | |
| Description: JCT. S. CARR. AVE. TO W. END OF US 90 BUS.AND I-10 INTER. | |
| Type Const: COLD PLANING ASPHALTIC CONCRETE, PAVEMENT PATCHING, SUPERPAVE ASPHALTIC CONCRETE OVERLAY, AND RELATED WORK | |
| Estimated Construction Cost: $3,492,194.81 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 02179 | Boh Bros. Construction Co., LLC. | $4,920,183.46 |
| 2 | 06276 | Barriere Construction Co., LLC | $4,977,393.10 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Boh Bros. Construction Co., LLC. |
- 2 - Barriere Construction Co., LLC |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 1,500 | LNFT | 16.00 | 24,000.00 | 16.00 | 24,000.00 |
| 0002 | 202-02-06100 | Removal of Concrete Walks and Drives | 1,345 | SQYD | 30.00 | 40,350.00 | 15.00 | 20,175.00 |
| 0003 | 203-07-00100 | Borrow (Vehicular Measurement) | 10,000 | CUYD | 18.00 | 180,000.00 | 13.00 | 130,000.00 |
| 0004 | 502-01-00100 | Superpave Asphaltic Concrete | 16,607.7 | TON | 95.00 | 1,577,731.50 | 85.00 | 1,411,654.50 |
| 0005 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 1,917 | TON | 95.00 | 182,115.00 | 85.00 | 162,945.00 |
| 0006 | 509-01-00100 | Cold Planing Asphaltic Pavement | 153,411 | SQYD | 2.60 | 398,868.60 | 2.50 | 383,527.50 |
| 0007 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -8,523 | CUYD | 10.00 | -85,230.00 | -10.00 | 85,230.00 |
| 0008 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 3,000 | SQYD | 130.00 | 390,000.00 | 80.00 | 240,000.00 |
| 0009 | 702-04-00150 | Adjusting Manholes w/Manhole Adjustment Rings | 50 | EACH | 300.00 | 15,000.00 | 150.00 | 7,500.00 |
| 0010 | 706-01-00100 | Concrete Walk (4" Thick) | 1,000 | SQYD | 61.00 | 61,000.00 | 50.00 | 50,000.00 |
| 0011 | 706-01-00300 | Concrete Walk (6" Thick) | 2,500 | SQYD | 67.00 | 167,500.00 | 55.00 | 137,500.00 |
| 0012 | 706-04-00100 | Handicapped Curb Ramps | 411 | EACH | 1,300.00 | 534,300.00 | 2,100.00 | 863,100.00 |
| 0013 | 707-01-00100 | Concrete Curb | 10,000 | LNFT | 19.00 | 190,000.00 | 28.00 | 280,000.00 |
| 0014 | 707-03-00100 | Combination Concrete Curb and Gutter | 5,000 | LNFT | 28.00 | 140,000.00 | 33.50 | 167,500.00 |
| 0015 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 325,000.00 | 325,000.00 | 400,000.00 | 400,000.00 |
| 0016 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 4,576 | LNFT | 0.30 | 1,372.80 | 0.15 | 686.40 |
| 0017 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 1,936 | LNFT | 0.90 | 1,742.40 | 0.60 | 1,161.60 |
| 0018 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 22.16 | MILE | 771.00 | 17,085.36 | 175.00 | 3,878.00 |
| 0019 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 22.16 | MILE | 535.00 | 11,855.60 | 175.00 | 3,878.00 |
| 0020 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 22.16 | MILE | 620.00 | 13,739.20 | 200.00 | 4,432.00 |
| 0021 | 727-01-00100 | Mobilization | 1 | LUMP | 450,000.00 | 450,000.00 | 490,000.00 | 490,000.00 |
| 0022 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,463 | EACH | 5.00 | 7,315.00 | 5.10 | 7,461.30 |
| 0023 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 2,288 | LNFT | 1.50 | 3,432.00 | 1.10 | 2,516.80 |
| 0024 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 1,936 | LNFT | 5.00 | 9,680.00 | 3.00 | 5,808.00 |
| 0025 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 11.08 | MILE | 2,800.00 | 31,024.00 | 2,400.00 | 26,592.00 |
| 0026 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 11.08 | MILE | 950.00 | 10,526.00 | 950.00 | 10,526.00 |
| 0027 | 732-04-01040 | Plastic Pavement Legends and Symbols (Arrow - Double) | 3 | EACH | 250.00 | 750.00 | 200.00 | 600.00 |
| 0028 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 3 | EACH | 240.00 | 720.00 | 175.00 | 525.00 |
| 0029 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 3 | EACH | 250.00 | 750.00 | 190.00 | 570.00 |
| 0030 | 732-04-19020 | Plastic Pavement Legends and Symbols (SCHOOL ZONE) | 2 | EACH | 450.00 | 900.00 | 425.00 | 850.00 |
| 0031 | 740-01-00100 | Construction Layout | 1 | LUMP | 160,000.00 | 160,000.00 | 20,000.00 | 20,000.00 |
| 0032 | NS-500-00360 | Saw Cutting Asphaltic Concrete Pavement Over Portland Cement Concrete Composite Pavement | 48,960 | INLF | 1.10 | 53,856.00 | 0.60 | 29,376.00 |
| 0034 | NS-MSC-00002 | Reset Street Names (Tile) | 3 | EACH | 1,600.00 | 4,800.00 | 1,800.00 | 5,400.00 |
| CONTRACTOR TOTAL | 4,920,183.46 | 4,977,393.10 | ||||||