Bid Tabulations
Letting of
03/17/2010
LA DOTD Headquarters
| Lead Project: 003-08-0024 | |
| Parish: Jefferson Davis | |
| Routes: US 90 | |
| Description: EAST OF ST. LOUISE STREET TO MERMENTAU RIVER BRIDGE | |
| Type Const: COLD PLANING ASPHALTIC CONCRETE, SUPERPAVE ASPHALTIC CONCRETE OVERLAY, AND RELATED WORK. | |
| Estimated Construction Cost: $712,762.53 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 34356 | Prairie Contractors Inc. | $572,336.43 |
| 2 | 00183 | R. E. Heidt Construction Co., Inc. | $619,917.58 |
| 3 | 12312 | Gilchrist Construction Co. LLC | $697,884.96 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Prairie Contractors Inc. |
- 2 - R. E. Heidt Construction Co., Inc. |
- 3 - Gilchrist Construction Co. LLC |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 844 | CUYD | 35.00 | 29,540.00 | 77.00 | 64,988.00 | 40.00 | 33,760.00 |
| 0002 | 502-01-00100 | Superpave Asphaltic Concrete | 4,726.94 | TON | 78.00 | 368,701.32 | 99.00 | 467,967.06 | 96.50 | 456,149.71 |
| 0003 | 509-01-00100 | Cold Planing Asphaltic Pavement | 42,972 | SQYD | 1.75 | 75,201.00 | 0.53 | 22,775.16 | 1.30 | 55,863.60 |
| 0004 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -1,194 | CUYD | 0.01 | -11.94 | 13.00 | -15,522.00 | 0.50 | -597.00 |
| 0005 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 375 | SQYD | 88.00 | 33,000.00 | 84.00 | 31,500.00 | 125.00 | 46,875.00 |
| 0006 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 7,400.00 | 7,400.00 | 2,520.00 | 2,520.00 | 12,000.00 | 12,000.00 |
| 0007 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 6.49 | MILE | 400.00 | 2,596.00 | 280.00 | 1,817.20 | 300.00 | 1,947.00 |
| 0008 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 3.245 | MILE | 1.00 | 3.25 | 288.75 | 936.99 | 10.00 | 32.45 |
| 0009 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 8.045 | MILE | 1.00 | 8.05 | 624.75 | 5,026.11 | 10.00 | 80.45 |
| 0010 | 727-01-00100 | Mobilization | 1 | LUMP | 28,000.00 | 28,000.00 | 11,200.00 | 11,200.00 | 62,000.00 | 62,000.00 |
| 0011 | 731-02-00100 | Reflectorized Raised Pavement Markers | 405 | EACH | 6.00 | 2,430.00 | 4.99 | 2,020.95 | 5.50 | 2,227.50 |
| 0012 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 8.045 | MILE | 2,750.00 | 22,123.75 | 2,520.00 | 20,273.40 | 2,500.00 | 20,112.50 |
| 0013 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 3.245 | MILE | 1,000.00 | 3,245.00 | 682.50 | 2,214.71 | 750.00 | 2,433.75 |
| 0014 | 740-01-00100 | Construction Layout | 1 | LUMP | 100.00 | 100.00 | 2,200.00 | 2,200.00 | 5,000.00 | 5,000.00 |
| CONTRACTOR TOTAL | 572,336.43 | 619,917.58 | 697,884.96 | |||||||