Bid Tabulations
Letting of
06/16/2010
LA DOTD Headquarters
| Lead Project: 001-07-0028 | |
| Parish: Lincoln | |
| Routes: US 80 | |
| Description: BIENVILLE PARISH LINE TO 0.1 MILES W OF SIMSBORO | |
| Type Const: GRADING, COLD PLANING ASPHALTIC PAVEMENT, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, ULTRATHIN HMAC WEARING COURSE SYSTEM AND RELATED WORK. | |
| Estimated Construction Cost: $710,443.73 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 08584 | Madden Contracting Co., Inc. | $622,689.07 |
| 2 | 12487 | Diamond B Construction Co., L.L.C. | $774,482.26 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Madden Contracting Co., Inc. |
- 2 - Diamond B Construction Co., L.L.C. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing Tree Trimming | 1 | LUMP | 10,000.00 | 10,000.00 | 15,000.00 | 15,000.00 |
| 0002 | 202-02-14500 | Removal of Guard Rail | 588 | LNFT | 5.25 | 3,087.00 | 2.50 | 1,470.00 |
| 0003 | 203-07-00100 | Borrow (Vehicular Measurement) | 36 | CUYD | 5.00 | 180.00 | 40.00 | 1,440.00 |
| 0004 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 591 | CUYD | 25.00 | 14,775.00 | 30.00 | 17,730.00 |
| 0005 | 502-01-00100 | Superpave Asphaltic Concrete | 249.5 | TON | 160.00 | 39,920.00 | 274.00 | 68,363.00 |
| 0006 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 89.9 | TON | 215.00 | 19,328.50 | 226.00 | 20,317.40 |
| 0007 | 509-01-00100 | Cold Planing Asphaltic Pavement | 2,301 | SQYD | 4.50 | 10,354.50 | 20.00 | 46,020.00 |
| 0008 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -192 | CUYD | 0.10 | -19.20 | 0.10 | -19.20 |
| 0009 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 186 | LNFT | 32.00 | 5,952.00 | 27.00 | 5,022.00 |
| 0010 | 704-03-00100 | Blocked Out Guard Rail | 125 | LNFT | 19.00 | 2,375.00 | 25.00 | 3,125.00 |
| 0011 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 54.00 | 5,400.00 | 73.00 | 7,300.00 |
| 0012 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,000.00 | 8,000.00 | 2,300.00 | 9,200.00 |
| 0013 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 21,500.00 | 21,500.00 | 10,000.00 | 10,000.00 |
| 0014 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 9.221 | MILE | 325.00 | 2,996.83 | 160.00 | 1,475.36 |
| 0015 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 3.88 | MILE | 1.00 | 3.88 | 410.00 | 1,590.80 |
| 0016 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 31.62 | MILE | 1.00 | 31.62 | 775.00 | 24,505.50 |
| 0017 | 716-01-00100 | Mulch (Vegetative) | 0.24 | TON | 1.00 | 0.24 | 6,000.00 | 1,440.00 |
| 0018 | 717-01-00100 | Seeding | 7 | LB | 1.00 | 7.00 | 24.00 | 168.00 |
| 0019 | 718-01-00100 | Fertilizer | 120 | LB | 0.10 | 12.00 | 6.00 | 720.00 |
| 0020 | 727-01-00100 | Mobilization | 1 | LUMP | 21,500.00 | 21,500.00 | 25,000.00 | 25,000.00 |
| 0021 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 70.00 | 280.00 | 130.00 | 520.00 |
| 0022 | 731-02-00100 | Reflectorized Raised Pavement Markers | 600 | EACH | 3.50 | 2,100.00 | 5.00 | 3,000.00 |
| 0023 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 15.81 | MILE | 2,000.00 | 31,620.00 | 3,000.00 | 47,430.00 |
| 0024 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.94 | MILE | 800.00 | 1,552.00 | 835.00 | 1,619.90 |
| 0025 | 740-01-00100 | Construction Layout | 1 | LUMP | 15,000.00 | 15,000.00 | 7,000.00 | 7,000.00 |
| 0026 | NS-500-00280 | Surface Preparation | 1 | LUMP | 30,000.00 | 30,000.00 | 40,000.00 | 40,000.00 |
| 0027 | NS-500-00320 | Ultrathin HMAC Wearing Course System (3/4 Inch Thick) | 63,853 | SQYD | 5.90 | 376,732.70 | 6.50 | 415,044.50 |
| CONTRACTOR TOTAL | 622,689.07 | 774,482.26 | ||||||