Bid Tabulations
Letting of
05/25/2011
LA DOTD Headquarters
| Lead Project: 001-03-0088 | |
| Parish: Bossier | |
| Routes: US 80 | |
| Description: TURN LANE ADDITION AT LA 3 | |
| Type Const: GRADING, CLASS II BASE COURSE, PORTLAND CEMENT CONCRETE PAVEMENT AND RELATED WORK. | |
| Estimated Construction Cost: $92,622.93 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 48462 | Fessler And Bowman, Inc. | $63,163.99 |
| 2 | 28218 | F. J. Burnell, Inc. | $71,921.95 |
| 3 | 18546 | C W & W Contractors, Inc. | $97,499.85 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Fessler And Bowman, Inc. |
- 2 - F. J. Burnell, Inc. |
- 3 - C W & W Contractors, Inc. |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 1,809.05 | 1,809.05 | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 |
| 0002 | 202-02-06100 | Removal of Concrete Walks and Drives | 207.1 | SQYD | 10.50 | 2,174.55 | 10.00 | 2,071.00 | 10.00 | 2,071.00 |
| 0003 | 202-02-06140 | Removal of Curbs (Concrete) | 221 | LNFT | 5.67 | 1,253.07 | 5.00 | 1,105.00 | 3.00 | 663.00 |
| 0004 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 120.6 | SQYD | 11.24 | 1,355.54 | 12.00 | 1,447.20 | 10.00 | 1,206.00 |
| 0005 | 202-03-00010 | Relocation Relocate Guy Wire pole | 1 | EACH | 302.57 | 302.57 | 7,500.00 | 7,500.00 | 4,003.00 | 4,003.00 |
| 0006 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 5,021.79 | 5,021.79 | 2,500.00 | 2,500.00 | 4,000.00 | 4,000.00 |
| 0007 | 302-02-04000 | Class II Base Course (8 1/2" Thick) | 149.4 | SQYD | 50.03 | 7,474.48 | 25.00 | 3,735.00 | 24.00 | 3,585.60 |
| 0008 | 601-01-00300 | Portland Cement Concrete Pavement (9" Thick) | 122 | SQYD | 113.75 | 13,877.50 | 80.00 | 9,760.00 | 120.00 | 14,640.00 |
| 0009 | 702-04-00200 | Adjusting Catch Basins | 2 | EACH | 2,511.62 | 5,023.24 | 1,500.00 | 3,000.00 | 1,800.00 | 3,600.00 |
| 0010 | 706-01-00100 | Concrete Walk (4" Thick) | 6.3 | SQYD | 253.48 | 1,596.92 | 150.00 | 945.00 | 100.00 | 630.00 |
| 0011 | 706-02-00200 | Concrete Drive (6" Thick) | 134.9 | SQYD | 37.63 | 5,076.29 | 65.00 | 8,768.50 | 100.00 | 13,490.00 |
| 0012 | 706-04-00100 | Handicapped Curb Ramps | 1 | EACH | 907.72 | 907.72 | 1,000.00 | 1,000.00 | 1,000.00 | 1,000.00 |
| 0013 | 707-01-00200 | Concrete Curb (Barrier) | 166.7 | LNFT | 6.22 | 1,036.87 | 10.00 | 1,667.00 | 15.00 | 2,500.50 |
| 0014 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 3,479.59 | 3,479.59 | 4,000.00 | 4,000.00 | 8,000.00 | 8,000.00 |
| 0015 | 714-01-00100 | Slab Sodding (Bermuda Grass) | 40 | SQYD | 12.10 | 484.00 | 8.00 | 320.00 | 10.00 | 400.00 |
| 0016 | 727-01-00100 | Mobilization | 1 | LUMP | 3,243.59 | 3,243.59 | 6,000.00 | 6,000.00 | 10,000.00 | 10,000.00 |
| 0017 | 731-02-00100 | Reflectorized Raised Pavement Markers | 80 | EACH | 5.30 | 424.00 | 6.00 | 480.00 | 20.00 | 1,600.00 |
| 0018 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 333 | LNFT | 2.12 | 705.96 | 2.25 | 749.25 | 3.00 | 999.00 |
| 0019 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 118 | LNFT | 4.24 | 500.32 | 5.00 | 590.00 | 9.00 | 1,062.00 |
| 0020 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.275 | MILE | 3,177.02 | 873.68 | 3,500.00 | 962.50 | 7,000.00 | 1,925.00 |
| 0021 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 0.018 | MILE | 5,591.56 | 100.65 | 7,000.00 | 126.00 | 15,000.00 | 270.00 |
| 0022 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.23 | MILE | 1,270.81 | 292.29 | 1,500.00 | 345.00 | 5,000.00 | 1,150.00 |
| 0023 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 1 | EACH | 211.80 | 211.80 | 200.00 | 200.00 | 500.00 | 500.00 |
| 0024 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 1 | EACH | 211.80 | 211.80 | 200.00 | 200.00 | 500.00 | 500.00 |
| 0025 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 1 | EACH | 211.80 | 211.80 | 200.00 | 200.00 | 500.00 | 500.00 |
| 0026 | 732-05-00100 | Removal of Existing Markings | 0.122 | MILE | 6,354.04 | 775.19 | 7,500.00 | 915.00 | 40,000.00 | 4,880.00 |
| 0027 | 740-01-00100 | Construction Layout | 1 | LUMP | 2,420.59 | 2,420.59 | 2,200.00 | 2,200.00 | 3,500.00 | 3,500.00 |
| 0028 | 741-11-00100 | Adjusting Water Valve | 4 | EACH | 69.74 | 278.96 | 500.00 | 2,000.00 | 250.00 | 1,000.00 |
| 0029 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 2,757 | INLF | 0.74 | 2,040.18 | 1.50 | 4,135.50 | 1.75 | 4,824.75 |
| CONTRACTOR TOTAL | 63,163.99 | 71,921.95 | 97,499.85 | |||||||