| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - BARRIERE CONSTRUCTION CO., LLC |
- 2 - BOH BROS. CONSTRUCTION CO., LLC. |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-D |
removal of concrete walks & drives
|
912   |
SQYD |
16.25 |
14,820.00 |
20.00 |
18,240.00 |
|
|
|
|
| 202-02-F |
removal of concrete combination curb & gutter
|
182.0 |
LNFT |
22.25 |
4,049.50 |
18.00 |
3,276.00 |
|
|
|
|
| 203-03 |
embankment
|
850   |
CUYD |
70.00 |
59,500.00 |
35.00 |
29,750.00 |
|
|
|
|
| 204-02 |
temporary hay or straw bales
|
50   |
EACH |
15.00 |
750.00 |
15.00 |
750.00 |
|
|
|
|
| 204-06 |
temporary silt fencing
|
300   |
LNFT |
3.00 |
900.00 |
3.00 |
900.00 |
|
|
|
|
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
600.0 |
CUYD |
10.00 |
6,000.00 |
25.00 |
15,000.00 |
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
3,343.6 |
TON |
90.00 |
300,924.00 |
200.00 |
668,720.00 |
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
236.0 |
TON |
130.00 |
30,680.00 |
200.00 |
47,200.00 |
|
|
|
|
| 509-01 |
cold planing asphaltic pavement
|
13,552   |
SQYD |
4.00 |
54,208.00 |
5.00 |
67,760.00 |
|
|
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 559   |
CUYD |
1.00 |
- 559.00 |
10.00 |
- 5,590.00 |
|
|
|
|
| 510-01-B |
pavement patching (12" minimum thickness)
|
1,355   |
SQYD |
80.00 |
108,400.00 |
175.00 |
237,125.00 |
|
|
|
|
| 701-03-F |
storm drain pipe (15" rcp/pcp)
|
100   |
LNFT |
300.00 |
30,000.00 |
75.00 |
7,500.00 |
|
|
|
|
| 701-14 |
cleaning existing pipes
|
3,519   |
LNFT |
4.50 |
15,835.50 |
10.00 |
35,190.00 |
|
|
|
|
| 702-03-A |
catch basins (cb-01)
|
1   |
EACH |
5,000.00 |
5,000.00 |
4,000.00 |
4,000.00 |
|
|
|
|
| 702-03-C |
catch basins (cb-06)
|
1   |
EACH |
5,000.00 |
5,000.00 |
5,000.00 |
5,000.00 |
|
|
|
|
| 702-04-A |
adjusting manholes
|
5   |
EACH |
1,300.00 |
6,500.00 |
2,000.00 |
10,000.00 |
|
|
|
|
| 702-04-B |
adjusting catch basins
|
19   |
EACH |
2,500.00 |
47,500.00 |
4,000.00 |
76,000.00 |
|
|
|
|
| 706-01-A |
concrete walk (4" thick)
|
151.6 |
SQYD |
84.00 |
12,734.40 |
80.00 |
12,128.00 |
|
|
|
|
| 706-02-C |
concrete drive (6" thick)
|
43.3 |
SQYD |
85.00 |
3,680.50 |
100.00 |
4,330.00 |
|
|
|
|
| 706-02-D |
concrete drive (8" thick)
|
717.3 |
SQYD |
95.00 |
68,143.50 |
120.00 |
86,076.00 |
|
|
|
|
| 707-01 |
concrete curb
|
348.0 |
LNFT |
30.25 |
10,527.00 |
17.00 |
5,916.00 |
|
|
|
|
| 707-01-A |
concrete curb (doweled barrier curb extension)
|
5,914.1 |
LNFT |
26.50 |
156,723.65 |
17.00 |
100,539.70 |
|
|
|
|
| 707-03 |
combination concrete curb & gutter
|
166.0 |
LNFT |
60.00 |
9,960.00 |
100.00 |
16,600.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
135,000.00 |
135,000.00 |
300,000.00 |
300,000.00 |
|
|
|
|
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
2.580 |
MILE |
100.00 |
258.00 |
300.00 |
774.00 |
|
|
|
|
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
2.810 |
MILE |
200.00 |
562.00 |
400.00 |
1,124.00 |
|
|
|
|
| 713-05-A |
temporary pavement legends and symbols (arrow)
|
2   |
EACH |
50.00 |
100.00 |
60.00 |
120.00 |
|
|
|
|
| 713-05-C |
temporary pavement legends and symbols (only)
|
2   |
EACH |
50.00 |
100.00 |
60.00 |
120.00 |
|
|
|
|
| 717-01 |
seeding
|
5   |
LB |
80.00 |
400.00 |
100.00 |
500.00 |
|
|
|
|
| 718-01 |
fertilizer
|
20   |
LB |
15.00 |
300.00 |
20.00 |
400.00 |
|
|
|
|
| 726-01 |
bedding material
|
25.0 |
CUYD |
100.00 |
2,500.00 |
30.00 |
750.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
135,000.00 |
135,000.00 |
200,000.00 |
200,000.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
340   |
EACH |
5.10 |
1,734.00 |
6.00 |
2,040.00 |
|
|
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
300   |
LNFT |
0.80 |
240.00 |
1.00 |
300.00 |
|
|
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
84   |
LNFT |
3.25 |
273.00 |
4.00 |
336.00 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
1.400 |
MILE |
2,650.00 |
3,710.00 |
3,000.00 |
4,200.00 |
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
1.290 |
MILE |
690.00 |
890.10 |
800.00 |
1,032.00 |
|
|
|
|
| 732-03-C |
plastic pavement striping (broken line)(8" width)
|
0.060 |
MILE |
1,300.00 |
78.00 |
1,600.00 |
96.00 |
|
|
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
2   |
EACH |
195.00 |
390.00 |
250.00 |
500.00 |
|
|
|
|
| 732-04-C |
plastic pavement legends & symbols (only)
|
2   |
EACH |
225.00 |
450.00 |
250.00 |
500.00 |
|
|
|
|
| 736-09 |
loop detector
|
350   |
LNFT |
14.00 |
4,900.00 |
16.00 |
5,600.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
30,000.00 |
30,000.00 |
70,000.00 |
70,000.00 |
|
|
|
|
| 741-11 |
adjusting water valve and meter box
|
1   |
EACH |
1,800.00 |
1,800.00 |
2,000.00 |
2,000.00 |
|
|
|
|
| S-001 |
roadway reinforcing mesh (complete road system)
|
12,016   |
SQYD |
7.00 |
84,112.00 |
8.00 |
96,128.00 |
|
|
|
|
| S-002 |
cleaning and resealing random cracks in asphaltic
concrete pavement |
6,000   |
LNFT |
1.50 |
9,000.00 |
4.00 |
24,000.00 |
|
|
|
|
| S-003 |
saw cutting portland cement concrete pavement
|
3,000   |
INFT |
1.10 |
3,300.00 |
8.00 |
24,000.00 |
|
|
|
|
| S-004 |
saw cutting asphaltic concrete pavement
|
713   |
INFT |
1.00 |
713.00 |
8.00 |
5,704.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
1,367,087.15 |
|
2,186,634.70 |
|
|
|
|
|