Letting of 3/29/2006 LA DOTD Headquarters


 
go back
Go Back
 
Lead Project: 829-26-0013
Parish: LAFOURCHE
Routes:
Description: LA 3235 CROSS DRAINS (CM)
Type Const: nonplastic embankment, rip rap for erosion repair
Estimated Construction Cost: $188,025.00
 
RankLicenseBidderConstruction Bid
1 06276 BARRIERE CONSTRUCTION CO., LLC $287,300.00
2 00481 COASTAL BRIDGE CO., L.L.C. $302,275.00
 
Item Number Item Description Quantity Unit of Measure - 1 -
BARRIERE CONSTRUCTION CO., LLC
- 2 -
COASTAL BRIDGE CO., L.L.C.

 

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
203-05-A nonplastic embankment (stone) 2,150      CUYD 75.00 161,250.00 74.00 159,100.00        
203-08 borrow (vehicular measurement) 50      CUYD 10.00 500.00 50.00 2,500.00        
203-09 geotextile fabric 600      SQYD 3.00 1,800.00 3.00 1,800.00        
701-14 cleaning existing pipes 50      LNFT 10.00 500.00 20.00 1,000.00        
711-03-C riprap (30 lb) 1,275      TON 70.00 89,250.00 65.00 82,875.00        
713-01 temporary signs & barricades lump      LUMP 8,000.00 8,000.00 10,000.00 10,000.00        
727-01 mobilization lump      LUMP 26,000.00 26,000.00 45,000.00 45,000.00        
                       
 CONTRACTOR TOTAL       287,300.00   302,275.00