Letting of 3/29/2006 LA DOTD Headquarters


 
go back
Go Back
 
Lead Project: 829-12-0026
Parish: LAFOURCHE
Routes: LA 653
Description: LA 653 (CSLM 3.19 - CSLM 5.74)
Type Const: grading, cold planing asphaltic concrete, in-place stablilized base course, superpave
asphaltic concrete overlay and related work.
Estimated Construction Cost: $753,642.81
 
RankLicenseBidderConstruction Bid
1 06276 BARRIERE CONSTRUCTION CO., LLC $802,727.24
2 06487 HUEY STOCKSTILL, INC. $810,037.20
 
Item Number Item Description Quantity Unit of Measure - 1 -
BARRIERE CONSTRUCTION CO., LLC
- 2 -
HUEY STOCKSTILL, INC.

 

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
203-08 borrow (vehicular measurement) 300      CUYD 8.00 2,400.00 15.00 4,500.00        
203-08-A borrow (vehicular measurement)(selected soils) 100      CUYD 8.00 800.00 15.00 1,500.00        
204-02 temporary hay or straw bales 50      EACH 5.00 250.00 5.00 250.00        
401-02 aggregate surface course (adjusted vehicular
measurement)
100      CUYD 30.00 3,000.00 45.00 4,500.00        
502-01 superpave asphaltic concrete 5,914.5    TON 60.00 354,870.00 66.00 390,357.00        
502-01-A superpave asphaltic concrete, drives, turnouts and
miscellaneous
470.0    TON 60.00 28,200.00 100.00 47,000.00        
509-01 cold planing asphaltic pavement 24,781      SQYD 2.00 49,562.00 1.50 37,171.50        
509-02 contractor retained reclaimed asphaltic pavement - 752      CUYD 10.00 - 7,520.00 FREE FREE        
713-01 temporary signs and barricades lump      LUMP 5,000.00 5,000.00 6,000.00 6,000.00        
713-04-A temporary pavement markings (broken line)(4" width)(4'
length)
5.100  MILE 135.00 688.50 170.00 867.00        
713-04-B temporary pavement markings (broken line)(4" width)
(10' length)
3.620  MILE 2.00 7.24 10.00 36.20        
713-05-A temporary pavement markings (solid line)(4" width) 13.500  MILE 3.00 40.50 10.00 135.00        
727-01 mobilization lump      LUMP 58,000.00 58,000.00 60,000.00 60,000.00        
731-02 reflectorized raised pavement markers 350      EACH 5.50 1,925.00 6.20 2,170.00        
732-02-A plastic pavement striping (solid line) (4" width) 6.750  MILE 2,400.00 16,200.00 3,500.00 23,625.00        
732-03-A plastic pavement striping (broken line)(4" width) 1.810  MILE 800.00 1,448.00 1,200.00 2,172.00        
735-01 mailboxes 21      EACH 1.00 21.00 5.00 105.00        
735-02 mailbox supports (single) 21      EACH 120.00 2,520.00 200.00 4,200.00        
740-01 construction layout lump      LUMP 5,000.00 5,000.00 2,000.00 2,000.00        
744-01 traffic control management lump      LUMP 1,000.00 1,000.00 3,100.00 3,100.00        
S-001 cement treated base course (12 in depth) 31,035      SQYD 9.00 279,315.00 7.10 220,348.50        
                       
 CONTRACTOR TOTAL       802,727.24   810,037.20