Letting of 3/29/2006 LA DOTD Headquarters


REBID
go back
Go Back
 
Lead Project: 720-01-0213
Parish: ORLEANS
Routes:
Description: REPAIRS AND MODIFICATIONS TO THE M/V NEVILLE LEVY
Type Const: towing and docking, replace sprinkler system, replace air conditioning/heating system,
replace fire suppression system, and related work
Estimated Construction Cost: $400,000.00
 
RankLicenseBidderConstruction Bid
1 43625 BUCK KREIHS MARINE REPAIR, LLC $464,885.00
2 40669 BOLLINGER QUICK REPAIR LLC $589,320.00
 
Item Number Item Description Quantity Unit of Measure - 1 -
BUCK KREIHS MARINE REPAIR, LLC
- 2 -
BOLLINGER QUICK REPAIR LLC

 

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
S-001 towing and docking lump      LUMP 4,800.00 4,800.00 8,840.00 8,840.00        
S-002 replace sprinkler system lump      LUMP 336,585.00 336,585.00 417,005.00 417,005.00        
S-003 replace air conditioning/heating system lump      LUMP 75,500.00 75,500.00 89,175.00 89,175.00        
S-004 replace fire suppression system lump      LUMP 48,000.00 48,000.00 74,300.00 74,300.00        
                       
 CONTRACTOR TOTAL       464,885.00   589,320.00