Letting of 3/29/2006 LA DOTD Headquarters


 
go back
Go Back
 
Lead Project: 451-08-0069
Parish: MADISON
Routes: I-20
Description: DELTA PIT SCALE MAINLINE SORTING SYSTEM
Type Const: grading, pavement patching, superpave asphaltic concrete pavement, mainline sorting
system, extended maintenance, and related work.
Estimated Construction Cost: $1,951,079.34
 
RankLicenseBidderConstruction Bid
1 01692 TOOMER ELECTRICAL CO., INC. $2,110,817.87
2 05789 D & J CONSTRUCTION CO., INC. $2,576,663.00
 
Item Number Item Description Quantity Unit of Measure - 1 -
TOOMER ELECTRICAL CO., INC.
- 2 -
D & J CONSTRUCTION CO., INC.

 

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
202-01 removal of structures & obstructions lump      LUMP 24,000.00 24,000.00 25,000.00 25,000.00        
203-06 excavation & embankment lump      LUMP 24,000.00 24,000.00 50,000.00 50,000.00        
203-09 geotextile fabric 45      SQYD 4.80 216.00 10.00 450.00        
204-02 temporary hay or straw bales 40      EACH 10.60 424.00 15.00 600.00        
204-06 temporary silt fencing 1,000      LNFT 3.70 3,700.00 3.00 3,000.00        
302-01 class ii base course 20.0    CUYD 180.00 3,600.00 125.00 2,500.00        
502-01 superpave asphaltic concrete 572.5    TON 180.00 103,050.00 200.00 114,500.00        
602-05-Q-03 full depth patching of jointed conc pvmt (13" thick)
(48.1 sq yds & over)
55.7    SQYD 480.00 26,736.00 400.00 22,280.00        
602-07 patching continuously reinforced concrete pavement 800.0    SQYD 120.00 96,000.00 325.00 260,000.00        
602-08 grinding concrete pavement 522.2    SQYD 21.60 11,279.52 40.00 20,888.00        
713-01 temporary signs & barricades lump      LUMP 43,830.00 43,830.00 250,000.00 250,000.00        
713-05-A temporary pavement markings (solid line)(4" width) 1.553  MILE 1,176.00 1,826.33 3,000.00 4,659.00        
713-09 temporary precast concrete barrier (department
furnished)
50      EACH 310.00 15,500.00 750.00 37,500.00        
727-01 mobilization lump      LUMP 226,992.00 226,992.00 255,000.00 255,000.00        
729-04 sign (type d) 1,212.0    SQFT 30.90 37,450.80 30.00 36,360.00        
729-08-F mounting (w6 x 12) 12      EACH 960.00 11,520.00 1,250.00 15,000.00        
729-08-G mounting (w8 x 18) 12      EACH 1,560.00 18,720.00 1,550.00 18,600.00        
729-13 mounting (bridge fascia mounted) 4      EACH 6,600.00 26,400.00 9,000.00 36,000.00        
731-02 reflectorized raised pavement markers 110      EACH 6.30 693.00 20.00 2,200.00        
732-02-A plastic pavement striping (solid line) (4" width) 3.121  MILE 2,820.00 8,801.22 6,000.00 18,726.00        
740-01 construction layout lump      LUMP 8,448.00 8,448.00 50,000.00 50,000.00        
744-01 traffic control management lump      LUMP 45,792.00 45,792.00 60,000.00 60,000.00        
S-001 mainline sorting system lump      LUMP 1,288,836.00 1,288,836.00 1,000,000.00 1,000,000.00        
S-002 extended maintenance lump      LUMP 22,163.00 22,163.00 240,000.00 240,000.00        
S-003 sawcut p. c. c. pavement (full depth) 180      LNFT 18.00 3,240.00 30.00 5,400.00        
S-004 rumble strips (ground-in) 0.4    MILE 24,000.00 9,600.00 20,000.00 8,000.00        
S-005 dynamic message sign unit 4      EACH 12,000.00 48,000.00 10,000.00 40,000.00        
                       
 CONTRACTOR TOTAL       2,110,817.87   2,576,663.00