Letting of 3/29/2006 LA DOTD Headquarters


REBID
go back
Go Back
DBE GOAL FED
Lead Project: 250-01-0040
Parish: E BATON ROUGE
Routes: LA 19
Description: LAVEY LANE-TWIN OAKS
Type Const: grading, drainage structures, cold planing asphaltic concrete, class ii base course,
superpave asphaltic concrete overlay and related work.
Estimated Construction Cost: $4,543,570.85
Maximum Number of Days Allowed for Construction: 350
Calculated Daily User Cost: $3,000.00
 
RankLicenseBidderConstruction Bid Bidder's Proposed
Contract Time
Total Bid
1 00046 BARBER BROS. CONTRACTING CO., L.L.C $6,248,070.35 350 $7,298,070.35
2 00481 COASTAL BRIDGE CO., L.L.C. $6,675,973.80 250 $7,425,973.80
 
Item Number Item Description Quantity Unit of Measure - 1 -
BARBER BROS. CONTRACTING CO., L.L.C
- 2 -
COASTAL BRIDGE CO., L.L.C.

 

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
201-01 clearing & grubbing lump      LUMP 40,000.00 40,000.00 100,000.00 100,000.00        
202-01 removal of structures & obstructions lump      LUMP 150,000.00 150,000.00 25,000.00 25,000.00        
202-02-C removal of portland cement concrete pavement 4,504      SQYD 12.50 56,300.00 65.00 292,760.00        
202-02-D removal of concrete walks & drives 4,538      SQYD 12.50 56,725.00 30.00 136,140.00        
203-01 general excavation 6,069      CUYD 20.00 121,380.00 12.00 72,828.00        
203-04 embankment 1,665      CUYD 25.00 41,625.00 20.00 33,300.00        
204-02 temporary hay or straw bales 50      EACH 21.00 1,050.00 15.00 750.00        
204-06 temporary silt fencing 200      LNFT 5.00 1,000.00 2.00 400.00        
302-01 class ii base course 5,029.5    CUYD 85.00 427,507.50 105.00 528,097.50        
304-01 lime 300.00   TON 140.00 42,000.00 130.00 39,000.00        
304-04-D lime treatment (type d) (12" thick) 19,110      SQYD 4.00 76,440.00 2.50 47,775.00        
402-01 traffic maintenance aggregate (vehicular measurement) 50.0    CUYD 250.00 12,500.00 500.00 25,000.00        
502-01 superpave asphaltic concrete 29,591.2    TON 65.00 1,923,428.00 65.00 1,923,428.00        
502-01-A superpave asphaltic concrete, drives, turnouts &
miscellaneous
681.3    TON 110.00 74,943.00 90.00 61,317.00        
509-01 cold planing asphaltic pavement 27,527      SQYD 3.00 82,581.00 2.50 68,817.50        
602-02-A cleaning and resealing existing longitudinal pavement
joints
20,000      LNFT 1.60 32,000.00 1.60 32,000.00        
602-02-B cleaning and resealing existing transverse pavement
joints
15,000      LNFT 2.00 30,000.00 1.30 19,500.00        
602-03 cleaning and sealing random cracks 1,500      LNFT 4.00 6,000.00 2.35 3,525.00        
701-03-F storm drain pipe (15" rcp/pcp) 384      LNFT 90.00 34,560.00 75.00 28,800.00        
701-03-G storm drain pipe (18" rcp/pcp) 24      LNFT 100.00 2,400.00 85.00 2,040.00        
701-03-I storm drain pipe (24" rcp/pcp) 24      LNFT 155.00 3,720.00 135.00 3,240.00        
701-03-K storm drain pipe (30" rcp/pcp) 24      LNFT 240.00 5,760.00 205.00 4,920.00        
701-03-M storm drain pipe (36" rcp/pcp) 24      LNFT 250.00 6,000.00 219.00 5,256.00        
701-03-N storm drain pipe (42" rcp/pcp) 24      LNFT 315.00 7,560.00 275.00 6,600.00        
701-03-O storm drain pipe (48" rcp/pcp) 24      LNFT 320.00 7,680.00 300.00 7,200.00        
702-03-A catch basins (cb-01) 2      EACH 3,500.00 7,000.00 2,300.00 4,600.00        
702-03-B catch basins (cb-02) 1      EACH 7,500.00 7,500.00 4,500.00 4,500.00        
702-03-D catch basins (cb-07) 57      EACH 5,500.00 313,500.00 5,000.00 285,000.00        
702-03-F catch basins (cb-08) 10      EACH 7,000.00 70,000.00 6,500.00 65,000.00        
702-04-A adjusting manholes 5      EACH 2,200.00 11,000.00 2,000.00 10,000.00        
702-04-B adjusting catch basins 66      EACH 2,500.00 165,000.00 2,000.00 132,000.00        
704-01-A guard rail (single thrie beam)(3'-1 1/2" post spacing) 162.0    LNFT 100.00 16,200.00 60.00 9,720.00        
704-03 blocked out guard rail 206.3    LNFT 20.00 4,126.00 20.00 4,126.00        
704-06-A guard rail anchor sections (trailing end)(single thrie
beam)
12.5    LNFT 100.00 1,250.00 80.00 1,000.00        
704-11-A guard rail end treatment (flared) 2      EACH 2,500.00 5,000.00 2,500.00 5,000.00        
706-01-A concrete walk (4" thick) 4,368.2    SQYD 45.00 196,569.00 45.00 196,569.00        
706-02-C concrete drive (6" thick) 1,754.6    SQYD 70.00 122,822.00 75.00 131,595.00        
707-03 combination concrete curb & gutter 18,742.8    LNFT 25.00 468,570.00 30.00 562,284.00        
712-01-C concrete cast-in-place revetment (6" thick) 455      SQYD 75.00 34,125.00 65.00 29,575.00        
713-01 temporary signs & barricades lump      LUMP 150,000.00 150,000.00 275,000.00 275,000.00        
713-03-A temporary pavement markings (4" width) 21,144      LNFT 0.20 4,228.80 0.20 4,228.80        
713-04-A temporary pavement markings (broken line)(4" width)(4'
length)
4.000  MILE 350.00 1,400.00 300.00 1,200.00        
724-01-B pavement patching (12" minimum thickness) 4,251      SQYD 75.00 318,825.00 25.00 106,275.00        
726-01 bedding material 115.0    CUYD 60.00 6,900.00 65.00 7,475.00        
727-01 mobilization lump      LUMP 475,000.00 475,000.00 600,000.00 600,000.00        
729-16-C object marker assembly (type 3) 4      EACH 90.00 360.00 70.00 280.00        
731-02 reflectorized raised pavement markers 1,367      EACH 6.00 8,202.00 5.50 7,518.50        
732-01-C plastic pavement striping (8" width) 1,024      LNFT 1.25 1,280.00 1.00 1,024.00        
732-01-E plastic pavement striping (24" width) 312      LNFT 3.50 1,092.00 3.00 936.00        
732-02-A plastic pavement striping (solid line) (4" width) 8.237  MILE 2,500.00 20,592.50 2,500.00 20,592.50        
732-03-A plastic pavement striping (broken line)(4" width) 7.679  MILE 1,200.00 9,214.80 1,000.00 7,679.00        
732-04-A plastic pavement legends & symbols (arrow) 8      EACH 160.00 1,280.00 150.00 1,200.00        
732-04-B plastic pavement legends & symbols (double arrow) 17      EACH 250.00 4,250.00 220.00 3,740.00        
732-04-C plastic pavement legends & symbols (only) 8      EACH 175.00 1,400.00 150.00 1,200.00        
732-05 removal of existing markings 2.000  MILE 3,000.00 6,000.00 3,000.00 6,000.00        
739-01 hydro-seeding 1.00   ACRE 2,000.00 2,000.00 2,500.00 2,500.00        
740-01 construction layout lump      LUMP 60,000.00 60,000.00 225,000.00 225,000.00        
744-01 traffic control management lump      LUMP 80,000.00 80,000.00 80,000.00 80,000.00        
805-01-B class a concrete (box culvert headwalls) 5.49   CUYD 2,000.00 10,980.00 1,200.00 6,588.00        
805-12-E reinforced concrete box culverts (4'x 4') 8.0    LNFT 600.00 4,800.00 750.00 6,000.00        
806-01 deformed reinforcing steel 387      LB 1.25 483.75 2.00 774.00        
S-001 paved gutter drain 40      EACH 2,700.00 108,000.00 2,600.00 104,000.00        
S-002 headwall raising 112      LNFT 90.00 10,080.00 75.00 8,400.00        
S-003 cured in place pipe 782      LNFT 215.00 168,130.00 225.00 175,950.00        
S-004 sawing and sealing longitudinal joints in asphalt 20,000      LNFT 1.15 23,000.00 1.15 23,000.00        
S-005 sawing and sealing transverse joints in asphalt 15,000      LNFT 1.25 18,750.00 1.05 15,750.00        
S-006 sawing longitudinal joints in asphalt 20,000      LNFT 1.00 20,000.00 1.00 20,000.00        
S-007 sawing transverse joints in asphalt 15,000      LNFT 1.20 18,000.00 1.00 15,000.00        
S-008 dynamic message sign unit 2      EACH 24,000.00 48,000.00 20,000.00 40,000.00        
                       
 ITEM TOTAL (CONSTRUCTION BID)       6,248,070.35   6,675,973.80        
 Number of Days Bid at $3,000 per day.     350 1,050,000.00 250 750,000.00 0   0  
 TOTAL BID       7,298,070.35   7,425,973.80