Letting of 3/29/2006 LA DOTD Headquarters


 
go back
Go Back
DBE GOAL FED
Lead Project: 029-02-0030
Parish: VERNON
Routes: LA 8
Description: TEXAS STATE LINE - JCT. LA 464
Type Const: grading, lime treatment, cement treated base course, drainage structures, superpave
asphaltic concrete pavement, concrete slab span bridge, and related work.
Estimated Construction Cost: $4,417,214.28
 
RankLicenseBidderConstruction Bid
1 08815 W. E. MCDONALD & SON, LLC. $4,829,059.50
2 12312 GILCHRIST CONSTRUCTION CO. LLC $4,840,147.55
 
Item Number Item Description Quantity Unit of Measure - 1 -
W. E. MCDONALD & SON, LLC.
- 2 -
GILCHRIST CONSTRUCTION CO. LLC

 

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
201-01 clearing & grubbing lump      LUMP 200,000.00 200,000.00 100,000.00 100,000.00        
202-01 removal of structures & obstructions lump      LUMP 10,000.00 10,000.00 2,000.00 2,000.00        
202-02-A removal of bridge (station 445+14.45 to sta.
445+71.75 19.5' x 57' timber bridge)
1      EACH 10,000.00 10,000.00 8,000.00 8,000.00        
202-02-H removal of guard rail 771      LNFT 0.01 7.71 6.00 4,626.00        
203-02 drainage excavation 1,940      CUYD 5.00 9,700.00 5.50 10,670.00        
203-06 excavation & embankment lump      LUMP 90,000.00 90,000.00 65,000.00 65,000.00        
203-08-A borrow (vehicular meas.)(selected soils) 2,581      CUYD 8.00 20,648.00 12.00 30,972.00        
204-05-A temporary sediment check dams (hay) 8      EACH 200.00 1,600.00 160.00 1,280.00        
204-05-B temporary sediment check dams (stone) 4      EACH 500.00 2,000.00 900.00 3,600.00        
204-06 temporary silt fencing 2,645      LNFT 2.50 6,612.50 2.00 5,290.00        
303-02 removal of existing patches 350      SQYD 0.01 3.50 5.00 1,750.00        
304-01 lime 614.28   TON 135.00 82,927.80 135.00 82,927.80        
304-03-D lime treatment (type c) (12" thick) 26,001      SQYD 0.50 13,000.50 1.50 39,001.50        
304-04-D lime treatment (type d) (12" thick) 26,001      SQYD 2.00 52,002.00 1.50 39,001.50        
401-02 aggregate surface course (adjusted vehicular
measurement)
4,953      CUYD 1.00 4,953.00 20.00 99,060.00        
402-01 traffic maintenance aggregate (vehicular measurement) 30.0    CUYD 100.00 3,000.00 100.00 3,000.00        
502-01 superpave asphaltic concrete 29,890.5    TON 61.00 1,823,320.50 62.00 1,853,211.00        
502-01-A superpave asphaltic concrete, drives, turnouts and
miscellaneous
1,679.8    TON 126.00 211,654.80 100.00 167,980.00        
509-01 cold planing asphaltic pavement 107,346      SQYD 1.60 171,753.60 2.00 214,692.00        
509-02 contractor retained reclaimed asphaltic pavement - 5,964      CUYD 0.01 - 59.64 0.01 - 59.64        
701-05-G side drain pipe (18") 60      LNFT 45.00 2,700.00 66.00 3,960.00        
701-10-I reinforced concrete pipe (extension)(24") 12      LNFT 100.00 1,200.00 150.00 1,800.00        
701-10-M reinforced concrete pipe (extension)(36") 24      LNFT 125.00 3,000.00 180.00 4,320.00        
701-14 cleaning existing pipes 80      LNFT 20.00 1,600.00 19.00 1,520.00        
701-15 concrete collar 3      EACH 1,400.00 4,200.00 900.00 2,700.00        
704-01-B guard rail (single thrie beam)(6'-3" post spacing) 338.0    LNFT 27.00 9,126.00 30.00 10,140.00        
704-03 blocked out guard rail 368.8    LNFT 15.75 5,808.60 18.00 6,638.40        
704-07-A guard rail bridge attachments (single thrie beam) 50.0    LNFT 30.00 1,500.00 33.00 1,650.00        
704-08-B guard rail transitions (double thrie beam) 250.0    LNFT 45.00 11,250.00 51.00 12,750.00        
704-11-A guard rail end treatment (flared) 10      EACH 1,800.00 18,000.00 2,000.00 20,000.00        
705-01 barbed wire fence 1,800      LNFT 6.00 10,800.00 6.80 12,240.00        
708-01 right-of-way monument 13      EACH 200.00 2,600.00 300.00 3,900.00        
708-02 right-of-way monument witness post 13      EACH 200.00 2,600.00 300.00 3,900.00        
711-01-C riprap (30 lb, 14" thick) 37      SQYD 54.00 1,998.00 60.00 2,220.00        
711-01-D riprap (55 lb, 18" thick) 916      SQYD 58.00 53,128.00 70.00 64,120.00        
711-04 geotextile fabric 953      SQYD 2.75 2,620.75 3.00 2,859.00        
712-02 sacked concrete revetment 10      SQYD 100.00 1,000.00 110.00 1,100.00        
712-04 flexible revetment 15      SQYD 54.00 810.00 34.00 510.00        
713-01 temporary signs & barricades lump      LUMP 120,000.00 120,000.00 20,000.00 20,000.00        
713-04-A temporary pavement markings (broken line)(4" width)(4'
length)
27.271  MILE 300.00 8,181.30 400.00 10,908.40        
713-04-B temporary pavement markings (broken line)(4" width)
(10' length)
8.675  MILE 200.00 1,735.00 300.00 2,602.50        
713-05-A temporary pavement markings (solid line)(4" width) 62.467  MILE 435.00 27,173.15 520.00 32,482.84        
716-01-A mulch (vegetative) 3.00   ACRE 750.00 2,250.00 850.00 2,550.00        
717-01 seeding 405      LB 7.00 2,835.00 8.00 3,240.00        
718-01 fertilizer 9,000      LB 0.35 3,150.00 0.40 3,600.00        
720-01-A erosion control system, slope protection (type a) 30      SQYD 2.50 75.00 10.00 300.00        
721-01 asphalt mulch 22,960      GAL 1.89 43,394.40 2.10 48,216.00        
722-01 project site laboratory 1      EACH 3,000.00 3,000.00 10,000.00 10,000.00        
725-01 temporary detour roads 1,536.6    LNFT 125.00 192,075.00 220.00 338,052.00        
725-03 temporary detour bridging 80.00   LNFT 700.00 56,000.00 880.00 70,400.00        
726-01 bedding material 15.6    CUYD 100.00 1,560.00 80.00 1,248.00        
727-01 mobilization lump      LUMP 200,000.00 200,000.00 200,000.00 200,000.00        
729-16-B object marker assembly (type 2) 5      EACH 50.00 250.00 51.00 255.00        
729-16-C object marker assembly (type 3) 10      EACH 66.00 660.00 75.00 750.00        
731-02 reflectorized raised pavement markers 1,214      EACH 5.00 6,070.00 5.00 6,070.00        
732-02-A plastic pavement striping (solid line) (4" width) 31.713  MILE 1,875.00 59,461.88 2,300.00 72,939.90        
732-03-A plastic pavement striping (broken line)(4" width) 4.238  MILE 650.00 2,754.70 750.00 3,178.50        
735-01 mailboxes 66      EACH 1.00 66.00 10.00 660.00        
735-02 mailbox supports (single) 58      EACH 125.00 7,250.00 150.00 8,700.00        
735-03 mailbox supports (double) 8      EACH 175.00 1,400.00 185.00 1,480.00        
740-01 construction layout lump      LUMP 12,500.00 12,500.00 40,000.00 40,000.00        
744-01 traffic control management lump      LUMP 6,000.00 6,000.00 35,000.00 35,000.00        
804-01-B precast concrete piles (14") 2,240      LNFT 38.00 85,120.00 42.00 94,080.00        
804-12 loading permanent piles 1      EACH 1.00 1.00 100.00 100.00        
805-01-F class a concrete (bents) 52.23   CUYD 450.00 23,503.50 780.00 40,739.40        
805-03 class aa concrete 215.16   CUYD 550.00 118,338.00 500.00 107,580.00        
806-01 deformed reinforcing steel 47,792      LB 0.60 28,675.20 0.70 33,454.40        
810-01 concrete railing (barrier) 240.00   LNFT 135.00 32,400.00 60.00 14,400.00        
813-01 concrete approach slabs 364.44   SQYD 150.00 54,666.00 170.00 61,954.80        
S-001 cement treated base course (12 in depth) 130,005      SQYD 6.75 877,533.75 5.25 682,526.25        
S-002 cleaning existing ditches 870      LNFT 4.50 3,915.00 5.00 4,350.00        
                       
 CONTRACTOR TOTAL       4,829,059.50   4,840,147.55