| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - SPECIALTY CONTRACTORS |
- 2 - STRANCO, INC. |
PHILLIPS & JORDAN, INC |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
400,000.00 |
400,000.00 |
575,000.00 |
575,000.00 |
268,750.00 |
268,750.00 |
|
|
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
5,000.00 |
5,000.00 |
30,000.00 |
30,000.00 |
64,375.00 |
64,375.00 |
|
|
| 202-02-01 |
removal of wood frame commercial building (lt. of
sta.332+75;60'x 60') |
1   |
EACH |
8,000.00 |
8,000.00 |
12,000.00 |
12,000.00 |
12,500.00 |
12,500.00 |
|
|
| 202-02-02 |
removal of pro lube shop building (rt. of sta.240+75;
50'x 50') |
1   |
EACH |
2,000.00 |
2,000.00 |
40,000.00 |
40,000.00 |
12,500.00 |
12,500.00 |
|
|
| 202-02-03 |
removal of brick veneer wall/sign (rt. of sta.271+75;
24'x 6') |
1   |
EACH |
500.00 |
500.00 |
2,000.00 |
2,000.00 |
1,250.00 |
1,250.00 |
|
|
| 202-02-04 |
removal of wood frame residence (rt. of sta.280+75;
25'x 40') |
1   |
EACH |
5,000.00 |
5,000.00 |
5,000.00 |
5,000.00 |
6,250.00 |
6,250.00 |
|
|
| 202-02-05 |
removal of metal canopy/gas station (lt. of sta.179+20;
25'x 30') |
1   |
EACH |
2,000.00 |
2,000.00 |
40,000.00 |
40,000.00 |
1,250.00 |
1,250.00 |
|
|
| 202-02-06 |
removal of wood frame gift shop (rt. of sta.289+20;
50'x 40') |
1   |
EACH |
4,000.00 |
4,000.00 |
12,000.00 |
12,000.00 |
7,500.00 |
7,500.00 |
|
|
| 202-02-07 |
removal of wood frame greenhouse (rt. of sta.289+80;
30'x 30') |
1   |
EACH |
500.00 |
500.00 |
3,000.00 |
3,000.00 |
6,250.00 |
6,250.00 |
|
|
| 202-02-08 |
removal of wood frame greenhouse (rt. of sta.290+20;
30'x 15') |
1   |
EACH |
500.00 |
500.00 |
3,000.00 |
3,000.00 |
2,500.00 |
2,500.00 |
|
|
| 204-05-A |
temporary sediment check dams (hay)
|
75   |
EACH |
85.00 |
6,375.00 |
100.00 |
7,500.00 |
112.50 |
8,437.50 |
|
|
| 204-06 |
temporary silt fencing
|
4,000   |
LNFT |
1.30 |
5,200.00 |
1.60 |
6,400.00 |
1.69 |
6,760.00 |
|
|
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
2,700.0 |
CUYD |
2.00 |
5,400.00 |
30.00 |
81,000.00 |
45.00 |
121,500.00 |
|
|
| 705-01 |
barbed wire fence
|
23,684   |
LNFT |
5.00 |
118,420.00 |
6.40 |
151,577.60 |
6.19 |
146,603.96 |
|
|
| 705-02 |
combination mesh & barbed wire fence
|
3,513   |
LNFT |
6.00 |
21,078.00 |
7.00 |
24,591.00 |
6.69 |
23,501.97 |
|
|
| 705-04 |
single swinging driveway gates
|
12   |
EACH |
400.00 |
4,800.00 |
500.00 |
6,000.00 |
500.00 |
6,000.00 |
|
|
| 705-05 |
double swinging driveway gates
|
3   |
DBGT |
600.00 |
1,800.00 |
600.00 |
1,800.00 |
900.00 |
2,700.00 |
|
|
| 705-09 |
rebuilt fence
|
265   |
LNFT |
15.00 |
3,975.00 |
100.00 |
26,500.00 |
25.00 |
6,625.00 |
|
|
| 709-01 |
steel cattle guard
|
1   |
EACH |
1,200.00 |
1,200.00 |
2,000.00 |
2,000.00 |
8,750.00 |
8,750.00 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
10,000.00 |
10,000.00 |
30,000.00 |
30,000.00 |
15,000.00 |
15,000.00 |
|
|
| 717-01 |
seeding
|
4,250   |
LB |
6.00 |
25,500.00 |
9.00 |
38,250.00 |
10.00 |
42,500.00 |
|
|
| 718-01 |
fertilizer
|
142,000   |
LB |
0.30 |
42,600.00 |
0.60 |
85,200.00 |
0.25 |
35,500.00 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
25,000.00 |
25,000.00 |
40,000.00 |
40,000.00 |
40,000.00 |
40,000.00 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
40,000.00 |
40,000.00 |
45,000.00 |
45,000.00 |
101,831.25 |
101,831.25 |
|
|
| 744-01 |
traffic control management
|
lump |
LUMP |
20,000.00 |
20,000.00 |
25,000.00 |
25,000.00 |
40,000.00 |
40,000.00 |
|
|
| S-001 |
tree trimming
|
lump |
LUMP |
7,500.00 |
7,500.00 |
20,000.00 |
20,000.00 |
90,000.00 |
90,000.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
766,348.00 |
|
1,312,818.60 |
|
IRREGULAR |
|
|
|