Letting of 1/26/2005 LA DOTD Headquarters


 
go back
Go Back
DBE GOAL FED
Lead Project: 050-06-0066
Parish: IBERVILLE, W BATON ROUGE
Routes: LA 1
Description: BAYOU PLAQUEMINE BRIDGE - ADDIS
Type Const: grading, drainage structures, class ii base course, cold pla ning asphaltic pavement,
pavement patching, superpave asphaltic concrete pavement and related work.
 
RankLicenseBidderAmount
100046 BARBER BROS. CONTRACTING CO., L.L.C $3,276,828.88
200849 F.G. SULLIVAN, JR. CONTRACTOR LLC $3,393,792.16
312487 DIAMOND B CONSTRUCTION CO., L.L.C. $3,662,975.28
 
Item Number Item Description Quantity Unit of Measure - 1 -
BARBER BROS. CONTRACTING CO., L.L.C
- 2 -
F.G. SULLIVAN, JR. CONTRACTOR LLC
- 3 -
DIAMOND B CONSTRUCTION CO., L.L.C.

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
202-01 removal of signal pole foundation (lt. of sta.
121+28.00)
lump      LUMP 790.00 790.00 500.00 500.00 525.00 525.00    
202-02-C removal of portland cement concrete pavement 169      SQYD 21.00 3,549.00 15.00 2,535.00 22.00 3,718.00    
202-02-D removal of concrete walks & drives 83      SQYD 18.00 1,494.00 15.00 1,245.00 13.00 1,079.00    
202-02-E removal of concrete curbs 1,156.0    LNFT 5.50 6,358.00 5.00 5,780.00 8.00 9,248.00    
202-02-G removal of surfacing & stabilized base 1,858.9    SQYD 6.00 11,153.40 5.00 9,294.50 9.00 16,730.10    
202-02-H removal of guard rail 130      LNFT 8.00 1,040.00 5.00 650.00 6.00 780.00    
203-08 borrow (vehicular measurement) 4,707      CUYD 12.00 56,484.00 15.00 70,605.00 13.00 61,191.00    
302-02-D class ii base course (12" thick) (crushed stone or
recycled pccp only)
4,512.0    SQYD 18.20 82,118.40 25.00 112,800.00 20.00 90,240.00    
502-01 superpave asphaltic concrete 21,107.8    TON 46.00 970,958.80 45.00 949,851.00 60.42 1,275,333.27    
502-01-A superpave asphaltic concrete, paved drives and
turnouts
373.1    TON 91.00 33,952.10 80.00 29,848.00 120.00 44,772.00    
509-01-A cold planing asphaltic pavement (2" deep) 40,902      SQYD 1.80 73,623.60 1.00 40,902.00 1.50 61,353.00    
509-01-B cold planing asphaltic pavement (2" avg. depth) 35,935      SQYD 2.40 86,244.00 1.00 35,935.00 2.00 71,870.00    
509-01-C cold planing asphaltic pavement (3" avg depth) 2,238      SQYD 10.30 23,051.40 3.00 6,714.00 3.50 7,833.00    
509-01-D cold planing asphaltic pavement (1 1/2" avg depth) 38,278      SQYD 2.17 83,063.26 1.00 38,278.00 1.55 59,330.90    
509-02 contractor retained reclaimed asphaltic pavement - 2,722      CUYD FREE FREE 0.10 - 272.20 0.10 - 272.20    
602-02-A cleaning and resealing existing longitudinal pavement
joints
97,516      LNFT 0.55 53,633.80 0.50 48,758.00 0.50 48,758.00    
602-02-B cleaning and resealing existing transverse pavement
joints
23,774      LNFT 1.95 46,359.30 1.00 23,774.00 2.00 47,548.00    
602-03 cleaning and sealing random cracks 2,000      LNFT 3.50 7,000.00 2.00 4,000.00 3.25 6,500.00    
602-05-G-01 full depth patching of jointed conc pvmt (8" thick)
(16.0 sq yds & under)
1,844.0    SQYD 186.00 342,984.00 200.00 368,800.00 185.00 341,140.00    
602-05-G-02 full depth patching of jointed conc pvmt (8" thick)
(16.1-48.0 sq yds)
590.0    SQYD 177.00 104,430.00 180.00 106,200.00 175.00 103,250.00    
602-05-G-03 full depth patching of jointed conc pvmt (8" thick)
(48.1 sq yds & over)
57.0    SQYD 175.00 9,975.00 175.00 9,975.00 175.00 9,975.00    
701-03-M storm drain pipe (36" rcp/pcp) 32      LNFT 140.00 4,480.00 140.00 4,480.00 110.00 3,520.00    
701-10-G reinforced concrete pipe (extension)(18") 48      LNFT 105.00 5,040.00 110.00 5,280.00 55.00 2,640.00    
701-10-I reinforced concrete pipe (extension)(24") 56      LNFT 114.00 6,384.00 115.00 6,440.00 66.00 3,696.00    
701-10-K reinforced concrete pipe (extension)(30") 80      LNFT 124.00 9,920.00 125.00 10,000.00 82.00 6,560.00    
701-10-M reinforced concrete pipe (extension)(36") 64      LNFT 139.00 8,896.00 140.00 8,960.00 93.00 5,952.00    
701-12-M corrugated metal pipe (extension)(36") 10      LNFT 124.00 1,240.00 125.00 1,250.00 132.00 1,320.00    
701-15 concrete collar 23      EACH 275.00 6,325.00 300.00 6,900.00 765.00 17,595.00    
702-03-A catch basins (cb-01) 10      EACH 3,850.00 38,500.00 4,000.00 40,000.00 4,000.00 40,000.00    
702-03-B catch basins (cb-02) 1      EACH 4,100.00 4,100.00 4,000.00 4,000.00 5,500.00 5,500.00    
702-03-C catch basins (cb-06) 1      EACH 3,000.00 3,000.00 3,000.00 3,000.00 5,500.00 5,500.00    
702-04-B adjusting catch basins 1      EACH 1,650.00 1,650.00 1,700.00 1,700.00 4,000.00 4,000.00    
702-07-A cross drain safety end (type 1) 1      EACH 1,650.00 1,650.00 1,700.00 1,700.00 1,700.00 1,700.00    
702-07-C cross drain safety end (type 3) 70      EACH 2,600.00 182,000.00 2,500.00 175,000.00 2,800.00 196,000.00    
702-07-D cross drain safety end (type 4) 1      EACH 4,300.00 4,300.00 4,000.00 4,000.00 8,500.00 8,500.00    
702-08-A side drain safety end (type 1) 8      EACH 1,700.00 13,600.00 1,700.00 13,600.00 1,500.00 12,000.00    
702-08-B side drain safety end (type 2) 7      EACH 3,900.00 27,300.00 4,000.00 28,000.00 5,000.00 35,000.00    
704-01-A guard rail (single thrie beam)(3'-1 1/2" post spacing) 519.4    LNFT 33.00 17,140.20 30.00 15,582.00 43.00 22,334.20    
704-03 blocked out guard rail 950.1    LNFT 17.50 16,626.75 16.00 15,201.60 20.00 19,002.00    
704-06-A guard rail anchor sections (trailing end)(single thrie
beam)
50.4    LNFT 100.00 5,040.00 87.00 4,384.80 77.00 3,880.80    
704-11-A guard rail end treatment (flared) 1      EACH 2,100.00 2,100.00 1,850.00 1,850.00 2,000.00 2,000.00    
704-11-B guard rail end treatment (tangent) 9      EACH 2,600.00 23,400.00 2,300.00 20,700.00 2,300.00 20,700.00    
707-01 concrete curb 1,156.0    LNFT 14.00 16,184.00 12.00 13,872.00 28.00 32,368.00    
713-01 temporary signs & barricades lump      LUMP 70,000.00 70,000.00 158,000.00 158,000.00 30,000.00 30,000.00    
713-03-C temporary pavement markings (8" width) 8,010      LNFT 0.35 2,803.50 0.15 1,201.50 0.33 2,643.30    
713-03-E temporary pavement markings (24" width) 768      LNFT 1.35 1,036.80 0.60 460.80 1.31 1,006.08    
713-04-A temporary pavement markings (broken line)(4" width)(4'
length)
13.356  MILE 372.00 4,968.43 600.00 8,013.60 145.00 1,936.62    
713-04-B temporary pavement markings (broken line)(4" width)
(10' length)
13.356  MILE 290.00 3,873.24 130.00 1,736.28 285.00 3,806.46    
713-05-A temporary pavement markings (solid line)(4" width) 22.556  MILE 550.00 12,405.80 130.00 2,932.28 500.00 11,278.00    
713-06-A temporary pavement legends and symbols (arrow) 112      EACH 60.00 6,720.00 25.00 2,800.00 60.00 6,720.00    
713-06-C temporary pavement legends and symbols (only) 56      EACH 60.00 3,360.00 25.00 1,400.00 60.00 3,360.00    
713-06-D temporary pavement legends and symbols (rr crossing) 16      EACH 250.00 4,000.00 100.00 1,600.00 240.00 3,840.00    
724-01-A pavement patching (6" minimum thickness) 2,905      SQYD 27.50 79,887.50 30.00 87,150.00 65.00 188,825.00    
724-01-B pavement patching (12" minimum thickness) 847      SQYD 65.00 55,055.00 65.00 55,055.00 77.00 65,219.00    
726-01 bedding material 352.4    CUYD 27.50 9,691.00 20.00 7,048.00 55.00 19,382.00    
727-01 mobilization lump      LUMP 100,000.00 100,000.00 233,000.00 233,000.00 100,000.00 100,000.00    
729-16-B object marker assembly (type 2) 40      EACH 55.00 2,200.00 50.00 2,000.00 72.00 2,880.00    
729-16-C object marker assembly (type 3) 30      EACH 55.00 1,650.00 50.00 1,500.00 71.00 2,130.00    
731-02 reflectorized raised pavement markers 2,432      EACH 5.50 13,376.00 6.00 14,592.00 5.35 13,011.20    
732-01-C plastic pavement striping (8" width) 3,402      LNFT 1.00 3,402.00 1.25 4,252.50 1.00 3,402.00    
732-01-E plastic pavement striping (24" width) 612      LNFT 3.25 1,989.00 4.00 2,448.00 3.00 1,836.00    
732-02-A plastic pavement striping (solid line) (4" width) 18.400  MILE 2,200.00 40,480.00 2,200.00 40,480.00 2,200.00 40,480.00    
732-03-A plastic pavement striping (broken line)(4" width) 9.266  MILE 850.00 7,876.10 1,000.00 9,266.00 800.00 7,412.80    
732-04-A plastic pavement legends & symbols (arrow) 56      EACH 140.00 7,840.00 150.00 8,400.00 136.00 7,616.00    
732-04-C plastic pavement legends & symbols (only) 28      EACH 150.00 4,200.00 150.00 4,200.00 147.00 4,116.00    
732-04-D plastic pavement legends & symbols (rr crossing) 6      EACH 500.00 3,000.00 500.00 3,000.00 500.00 3,000.00    
735-01 mailboxes 12      EACH 2.00 24.00 1.00 12.00 15.00 180.00    
735-02 mailbox supports (single) 2      EACH 125.00 250.00 135.00 270.00 200.00 400.00    
735-03 mailbox supports (double) 2      EACH 200.00 400.00 175.00 350.00 300.00 600.00    
735-04 mailbox supports (multiple) 2      EACH 300.00 600.00 300.00 600.00 500.00 1,000.00    
736-09 loop detector 178      LNFT 12.50 2,225.00 10.00 1,780.00 16.00 2,848.00    
736-10 underground junction box 2      EACH 310.00 620.00 350.00 700.00 500.00 1,000.00    
739-01 hydro-seeding 10.00   ACRE 1,000.00 10,000.00 1,000.00 10,000.00 1,000.00 10,000.00    
740-01 construction layout lump      LUMP 20,000.00 20,000.00 80,000.00 80,000.00 38,000.00 38,000.00    
S-001 roadway reinforcing mesh (complete road system) 47,348      SQYD 6.15 291,190.20 6.50 307,762.00 6.00 284,088.00    
S-002 rumble strips (ground-in) 16.1    MILE 850.00 13,685.00 600.00 9,660.00 815.00 13,121.50    
S-003 variable message sign unit 6      EACH 13,000.00 78,000.00 10,000.00 60,000.00 6,000.00 36,000.00    
S-004 sawcuts in asphaltic concrete lifts 4,943      LNFT 1.20 5,931.60 1.00 4,943.00 1.00 4,943.00    
S-005 sawing and sealing longitudinal joints in asphaltic
concrete overlay
1,373      LNFT 1.70 2,334.10 1.50 2,059.50 1.75 2,402.75    
S-006 sawing and sealing transverse joints in asphaltic
concrete overlay
1,098      LNFT 1.70 1,866.60 1.50 1,647.00 1.75 1,921.50    
S-007 removal of concrete catch basins 7      EACH 250.00 1,750.00 200.00 1,400.00 1,700.00 11,900.00    
S-008 ditch relocation 2,000      LNFT 5.50 11,000.00 5.00 10,000.00 10.00 20,000.00    
                       
 CONTRACTOR TOTAL       3,276,828.88   3,393,792.16   3,662,975.28