Letting of 3/03/2004 LA DOTD Headquarters


 
go back
Go Back
DBE GOAL FED
Lead Project: 070-01-0029
Parish: CLAIBORNE
Routes: LA 2
Description: JUNCTION LA 9 TO JUNCTION LA 518
Type Const: grading, cold planing asphaltic concrete, superpave asphaltic concrete pavement,
cement treated base course, pavement patching and related work.
 
RankLicenseBidderAmount
108584 MADDEN CONTRACTING CO., INC. $2,339,800.81
 
Item Number Item Description Quantity Unit of Measure - 1 -
MADDEN CONTRACTING CO., INC.

 

 

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
202-02-H removal of guard rail 416      LNFT 4.00 1,664.00            
203-08 borrow (vehicular measurement) 6,000      CUYD 8.00 48,000.00            
401-02 aggregate surface course (adjusted vehicular
measurement)
400      CUYD 10.00 4,000.00            
502-01-A superpave asphaltic concrete (level 1) 28,061.9    TON 49.00 1,375,033.10            
502-01-D superpave asphaltic concrete, incidental paving (level
a)
1,000.0    TON 20.00 20,000.00            
509-01 cold planing asphaltic pavement 97,912      SQYD 1.46 142,951.52            
509-02 contractor retained reclaimed asphaltic pavement - 2,040      CUYD 0.01 - 20.40            
701-08 relaying pipe 6      LNFT 150.00 900.00            
701-15 concrete collar 1      EACH 500.00 500.00            
704-03 blocked out guard rail 62.5    LNFT 14.00 875.00            
704-07-A guard rail bridge attachments (single thrie beam) 50.0    LNFT 27.00 1,350.00            
704-08-B guard rail transitions (double thrie beam) 100.0    LNFT 32.00 3,200.00            
704-11-B guard rail end treatment (tangent) 4      EACH 1,800.00 7,200.00            
707-04 asphaltic curb 190.0    LNFT 1.00 190.00            
713-01 temporary signs & barricades lump      LUMP 74,500.00 74,500.00            
713-04-A temporary pavement markings (broken line)(4" width)(4'
length)
19.367  MILE 1.00 19.36            
713-04-B temporary pavement markings (broken line)(4" width)
(10' length)
8.341  MILE 1.00 8.34            
713-05-A temporary pavement markings (solid line)(4" width) 65.577  MILE 1.00 65.57            
716-01-B mulch (fiber) 13.83   ACRE 550.00 7,606.50            
722-02 project site laboratory (equipped) 1      EACH 2,000.00 2,000.00            
724-01-A pavement patching (6" minimum thickness) 2,000      SQYD 20.00 40,000.00            
727-01 mobilization lump      LUMP 74,500.00 74,500.00            
729-16-B object marker assembly (type 2) 12      EACH 55.00 660.00            
729-16-C object marker assembly (type 3) 4      EACH 65.00 260.00            
731-02 reflectorized raised pavement markers 2,175      EACH 5.20 11,310.00            
732-01-E plastic pavement striping (24" width) 370      LNFT 2.94 1,087.80            
732-02-A plastic pavement striping (solid line) (4" width) 32.570  MILE 1,760.00 57,323.20            
732-03-A plastic pavement striping (broken line)(4" width) 4.828  MILE 592.00 2,858.17            
735-01 mailboxes 29      EACH 5.00 145.00            
735-02 mailbox supports (single) 21      EACH 125.00 2,625.00            
735-03 mailbox supports (double) 4      EACH 150.00 600.00            
739-01 hydro-seeding 13.83   ACRE 900.00 12,447.00            
740-01 construction layout lump      LUMP 35,000.00 35,000.00            
S-001 cement treated base course (12 in depth) 67,315      SQYD 5.91 397,831.65            
S-002 rumble strips (ground in) 19.0    MILE 690.00 13,110.00            
                       
 CONTRACTOR TOTAL       2,339,800.81