| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - D & J CONSTRUCTION CO., INC. |
- 2 - DIAMOND B CONSTRUCTION CO., L.L.C. |
- 3 - GILCHRIST CONSTRUCTION CO. LLC |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-D |
removal of concrete walks & drives
|
344   |
SQYD |
7.00 |
2,408.00 |
3.00 |
1,032.00 |
10.00 |
3,440.00 |
|
|
| 202-02-H |
removal of guard rail
|
416   |
LNFT |
6.00 |
2,496.00 |
4.00 |
1,664.00 |
5.00 |
2,080.00 |
|
|
| 203-08 |
borrow (vehicular measurement)
|
150   |
CUYD |
40.00 |
6,000.00 |
20.00 |
3,000.00 |
20.00 |
3,000.00 |
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
3,269   |
CUYD |
5.00 |
16,345.00 |
13.00 |
42,497.00 |
27.50 |
89,897.50 |
|
|
| 502-01-A |
superpave asphaltic concrete (level 1)
|
11,572.5 |
TON |
42.00 |
486,045.00 |
43.21 |
500,047.72 |
40.00 |
462,900.00 |
|
|
| 502-01-D |
superpave asphaltic concrete, incidental paving (level
a) |
2,215.0 |
TON |
65.00 |
143,975.00 |
68.24 |
151,151.60 |
60.00 |
132,900.00 |
|
|
| 507-01-B |
asphaltic surface treatment (2 applications)
|
52,714   |
SQYD |
1.95 |
102,792.30 |
2.05 |
108,063.70 |
2.00 |
105,428.00 |
|
|
| 509-01 |
cold planing asphaltic pavement
|
52,714   |
SQYD |
0.90 |
47,442.60 |
0.76 |
40,062.64 |
1.00 |
52,714.00 |
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 2,759   |
CUYD |
0.01 |
- 27.59 |
0.15 |
- 413.85 |
1.00 |
- 2,759.00 |
|
|
| 704-03 |
blocked out guard rail
|
162.6 |
LNFT |
15.00 |
2,439.00 |
15.75 |
2,560.95 |
16.00 |
2,601.60 |
|
|
| 704-07-A |
guard rail bridge attachments (single thrie beam)
|
50.0 |
LNFT |
25.00 |
1,250.00 |
34.00 |
1,700.00 |
34.50 |
1,725.00 |
|
|
| 704-08-B |
guard rail transitions (double thrie beam)
|
100.0 |
LNFT |
40.00 |
4,000.00 |
34.00 |
3,400.00 |
35.00 |
3,500.00 |
|
|
| 704-11-A |
guard rail end treatment (flared)
|
4   |
EACH |
1,650.00 |
6,600.00 |
1,700.00 |
6,800.00 |
1,700.00 |
6,800.00 |
|
|
| 706-02-C |
concrete drive (6" thick)
|
344.4 |
SQYD |
40.00 |
13,776.00 |
42.00 |
14,464.80 |
45.00 |
15,498.00 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
9,000.00 |
9,000.00 |
4,400.00 |
4,400.00 |
10,000.00 |
10,000.00 |
|
|
| 713-03-E |
temporary pavement markings (24" width)
|
66   |
LNFT |
4.50 |
297.00 |
0.63 |
41.58 |
0.65 |
42.90 |
|
|
| 713-04-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
12.252 |
MILE |
160.00 |
1,960.32 |
210.00 |
2,572.92 |
325.00 |
3,981.90 |
|
|
| 713-04-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
10.338 |
MILE |
1.00 |
10.33 |
210.00 |
2,170.98 |
215.00 |
2,222.67 |
|
|
| 713-05-A |
temporary pavement markings (solid line)(4" width)
|
30.374 |
MILE |
1.00 |
30.37 |
420.00 |
12,757.08 |
430.00 |
13,060.82 |
|
|
| 713-07 |
temporary reflectorized raised pavement markers
|
1,080   |
EACH |
1.00 |
1,080.00 |
1.31 |
1,414.80 |
0.40 |
432.00 |
|
|
| 714-02 |
water
|
7.5 |
MGAL |
1.00 |
7.50 |
1.00 |
7.50 |
10.00 |
75.00 |
|
|
| 724-01-B |
pavement patching (12" minimum thickness)
|
500   |
SQYD |
85.00 |
42,500.00 |
42.00 |
21,000.00 |
75.00 |
37,500.00 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
50,000.00 |
50,000.00 |
20,000.00 |
20,000.00 |
80,000.00 |
80,000.00 |
|
|
| 729-16-C |
object marker assembly (type 3)
|
4   |
EACH |
65.00 |
260.00 |
68.00 |
272.00 |
70.00 |
280.00 |
|
|
| 731-02 |
reflectorized raised pavement markers
|
540   |
EACH |
5.00 |
2,700.00 |
5.00 |
2,700.00 |
5.00 |
2,700.00 |
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
33   |
LNFT |
16.00 |
528.00 |
3.15 |
103.95 |
3.25 |
107.25 |
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
10.125 |
MILE |
1,950.00 |
19,743.75 |
1,760.00 |
17,820.00 |
1,800.00 |
18,225.00 |
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
3.446 |
MILE |
700.00 |
2,412.20 |
630.00 |
2,170.98 |
650.00 |
2,239.90 |
|
|
| 735-01 |
mailboxes
|
109   |
EACH |
1.00 |
109.00 |
13.00 |
1,417.00 |
20.00 |
2,180.00 |
|
|
| 735-02 |
mailbox supports (single)
|
89   |
EACH |
85.00 |
7,565.00 |
130.00 |
11,570.00 |
105.00 |
9,345.00 |
|
|
| 735-03 |
mailbox supports (double)
|
6   |
EACH |
120.00 |
720.00 |
200.00 |
1,200.00 |
150.00 |
900.00 |
|
|
| 735-04 |
mailbox supports (multiple)
|
2   |
EACH |
250.00 |
500.00 |
350.00 |
700.00 |
275.00 |
550.00 |
|
|
| 739-01 |
hydro-seeding
|
0.25 |
ACRE |
5,000.00 |
1,250.00 |
2,100.00 |
525.00 |
2,200.00 |
550.00 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
6,000.00 |
6,000.00 |
7,192.50 |
7,192.50 |
7,500.00 |
7,500.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
982,214.78 |
|
986,066.85 |
|
1,071,617.54 |
|
|
|