Line Number | Item | Description | Unit | Quantity |
| 0001 | 202-02-00010 | Removal of Power Pole | EACH | 1 |
| 0002 | 202-02-00040 | Removal of Sludge | CUYD | 15 |
| 0003 | 202-02-00050 | Removal of Sewer Treatment Plant | LUMP | 1 |
| 0004 | 203-01-00100 | General Excavation | CUYD | 12 |
| 0005 | 203-03-00100 | Embankment | CUYD | 112 |
| 0006 | 204-06-00100 | Temporary Silt Fencing | LNFT | 500 |
| 0007 | 204-07-00100 | Temporary Stone Construction Entrance | EACH | 1 |
| 0008 | 302-02-12070 | Class II Base Course (12" Thick) (Crushed Stone or Recycled Portland Cement Concrete) | SQYD | 50.2 |
| 0009 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | CUYD | 34.6 |
| 0010 | 705-06-00300 | Chain Link Fence (6-Foot Height) | LNFT | 109 |
| 0011 | 705-08-02040 | 6-Foot Double Gates for Chain Link Fence (6-Foot Height) | DBGT | 1 |
| 0012 | 711-04-00100 | Geotextile Fabric | SQYD | 50 |
| 0013 | 714-01-00600 | Slab Sodding (St. Augustine) | SQYD | 1,000 |
| 0014 | 727-01-00100 | Mobilization | LUMP | 1 |
| 0015 | 740-01-00100 | Construction Layout | LUMP | 1 |
| 0016 | 805-01-00900 | Class A1 Concrete (Wash Rack) | CUYD | 40.08 |
| 0017 | 806-01-00100 | Deformed Reinforcing Steel | LB | 3,049 |
| 0018 | TS-821-00101 | Building Plumbing | LUMP | 1 |
| 0019 | TS-821-00102 | HDPE Pipe (2") | LNFT | 80 |
| 0020 | TS-821-00102 | HDPE Pipe (3/4") | LNFT | 37.5 |
| 0021 | TS-821-00103 | PVC Pipe (4") | LNFT | 350.25 |
| 0022 | TS-821-00304 | Sewage Treatment Plant | LUMP | 1 |
| 0023 | TS-822-00001 | Site Electrical | LUMP | 1 |