Line Number | Item | Description | Unit | Quantity |
| 0001 | 201-01-00100 | Clearing and Grubbing | LUMP | 1 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | LUMP | 1 |
| 0003 | 202-02-02000 | Removal of Asphalt Drives | SQYD | 40 |
| 0004 | 204-02-00100 | Temporary Hay Bales | EACH | 17 |
| 0005 | 204-06-00100 | Temporary Silt Fencing | LNFT | 412 |
| 0006 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | CUYD | 5 |
| 0007 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | TON | 6.7 |
| 0008 | 705-04-00100 | Single Swinging Driveway Gates | EACH | 1 |
| 0009 | 705-06-00400 | Chain Link Fence (7 Foot Height) | LNFT | 278 |
| 0010 | 713-01-00100 | Temporary Signs and Barricades | LUMP | 1 |
| 0011 | 727-01-00100 | Mobilization | LUMP | 1 |
| 0012 | 739-01-00100 | Hydro-Seeding | ACRE | 0.55 |
| 0013 | 740-01-00100 | Construction Layout | LUMP | 1 |
| 0014 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | INLF | 306 |