Line Number | Item | Description | Unit | Quantity |
0001 | 202-01-00100 | Removal of Structures and Obstructions | LUMP | 1 |
0002 | 202-02-02020 | Removal of Asphalt Pavement | SQYD | 409 |
0003 | 202-02-06102 | Removal of Incidental Concrete Paving | SQYD | 27 |
0004 | 202-02-14500 | Removal of Guard Rail | LNFT | 914 |
0005 | 203-07-00100 | Borrow (Vehicular Measurement) | CUYD | 625 |
0006 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | EACH | 4 |
0007 | 204-06-00100 | Temporary Silt Fencing | LNFT | 50 |
0008 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | CUYD | 1,273 |
0009 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | CUYD | 30 |
0010 | 502-01-00100 | Asphalt Concrete | TON | 14,722.4 |
0011 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | TON | 861.9 |
0012 | 507-01-00100 | Asphalt Material (CRS-2P Emulsion) | GAL | 46,270 |
0013 | 507-02-00200 | Aggregate (S2) | SQYD | 68,044 |
0014 | 507-02-00300 | Aggregate (S3) | SQYD | 68,044 |
0015 | 509-01-00100 | Milling Asphalt Pavement | SQYD | 65,815 |
0016 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | CUYD | -3,400 |
0017 | 510-01-00300 | Pavement Patching (18" Minimum Thickness) | SQYD | 4,108 |
0018 | 510-02-00100 | Pavement Widening (24" Thickness) | SQYD | 222.2 |
0019 | 701-02-01040 | Cross Drain Pipe Arch (36" Equiv. RCPA) | LNFT | 80 |
0020 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | LNFT | 37 |
0021 | 704-01-01000 | Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) | LNFT | 225 |
0022 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | LNFT | 180 |
0023 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | LNFT | 281.25 |
0024 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | EACH | 8 |
0025 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | SQYD | 26.7 |
0026 | 713-01-00100 | Temporary Signs and Barricades | LUMP | 1 |
0027 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | MILE | 13.898 |
0028 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | MILE | 14.056 |
0029 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | MILE | 39.26 |
0030 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | EACH | 2,438 |
0031 | 713-11-00100 | Portable Changeable Message Signs | EACH | 4 |
0032 | 724-01-00100 | Rumble Strips (Centerline) | MILE | 3.967 |
0033 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | MILE | 9.233 |
0034 | 726-01-00100 | Bedding Material | CUYD | 20.9 |
0035 | 727-01-00100 | Mobilization | LUMP | 1 |
0036 | 729-16-00200 | Object Marker Assembly (Type 2) | EACH | 2 |
0037 | 729-16-00300 | Object Marker Assembly (Type 3) | EACH | 8 |
0038 | 731-02-00100 | Reflectorized Raised Pavement Markers | EACH | 825 |
0039 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | LNFT | 132 |
0040 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | LNFT | 460 |
0041 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | MILE | 12.244 |
0042 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | MILE | 3.514 |
0043 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | EACH | 14 |
0044 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | EACH | 2 |
0045 | 735-01-00100 | Mailboxes | EACH | 86 |
0046 | 735-02-00100 | Mailbox Supports (Single) | EACH | 82 |
0047 | 735-03-00100 | Mailbox Supports (Double) | EACH | 2 |
0048 | 736-01-00100 | Trenching and Backfilling | LNFT | 37 |
0049 | 736-09-00100 | Loop Detector | LNFT | 140 |
0050 | 736-11-00100 | Conduit (1" HDPE, Schedule 80) | LNFT | 37 |
0051 | 739-01-00100 | Hydro-Seeding | ACRE | 3.375 |
0052 | 740-01-00100 | Construction Layout | LUMP | 1 |
0053 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | INLF | 21,006 |