Line Number | Item | Description | Unit | Quantity |
0001 | 202-02-04540 | Removal of Bridge Component RAILING | EACH | 1 |
0002 | 202-02-04540 | Removal of Bridge Component WINGWALL | EACH | 1 |
0003 | 202-02-06000 | Removal of Concrete Approach Slabs | SQYD | 6.7 |
0004 | 202-02-14500 | Removal of Guard Rail | LNFT | 29.5 |
0005 | 203-03-00100 | Embankment | CUYD | 8 |
0006 | 204-06-00100 | Temporary Silt Fencing | LNFT | 755 |
0007 | 713-01-00100 | Temporary Signs and Barricades | LUMP | 1 |
0008 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | MILE | 2.426 |
0009 | 713-07-00100 | Temporary Precast Concrete Barrier (Contractor Furnished) | EACH | 2,200 |
0010 | 713-11-00100 | Portable Changeable Message Signs | EACH | 1 |
0011 | 727-01-00100 | Mobilization | LUMP | 1 |
0012 | 729-16-00300 | Object Marker Assembly (Type 3) | EACH | 1 |
0013 | 731-02-00100 | Reflectorized Raised Pavement Markers | EACH | 216 |
0014 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | MILE | 0.808 |
0015 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | MILE | 0.405 |
0016 | 732-05-00100 | Removal of Existing Markings | MILE | 0.405 |
0017 | 740-01-00100 | Construction Layout | LUMP | 1 |
0018 | 804-03-00800 | Steel Piles (HP 14x73) | LNFT | 70 |
0019 | 805-01-00900 | Class A1 Concrete (WINGWALL, APPROACH SLAB, & PARAPET) | CUYD | 7.26 |
0020 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | SQFT | 182 |
0021 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | SQFT | 306 |
0022 | 806-01-00100 | Deformed Reinforcing Steel | LB | 773 |
0023 | 810-01-00400 | Concrete Bridge Railing POST AND RAIL | LNFT | 28 |
0024 | 815-03-00200 | Joint Seal (Preformed Silicone) | LNFT | 3 |
0025 | 830-07-00100 | Structural Concrete Patching | SQFT | 43 |
0026 | NS-700-00810 | Impact Attenuator (Construction Zone)(Test Level 3) | EACH | 1 |