Line Number | Item | Description | Unit | Quantity |
| 0001 | 201-01-00200 | Clearing and Grubbing (Selective) | LUMP | 1 |
| 0002 | 202-02-00010 | Removal of Existing Drainage Safety End Treatment | EACH | 1 |
| 0003 | 202-02-03030 | Removal of Pavement Structure | SQYD | 8,213 |
| 0004 | 202-02-06100 | Removal of Concrete Walks and Drives | SQYD | 256.5 |
| 0005 | 202-02-06140 | Removal of Curbs (Concrete) | LNFT | 992 |
| 0006 | 202-02-14500 | Removal of Guard Rail | LNFT | 665 |
| 0007 | 202-02-32100 | Removal of Pipe (Cross Drain) 18" CMP | LNFT | 3 |
| 0008 | 202-02-32100 | Removal of Pipe (Cross Drain) 18" Plastic | LNFT | 1 |
| 0009 | 202-02-32100 | Removal of Pipe (Cross Drain) 18" RCP | LNFT | 66 |
| 0010 | 202-02-32100 | Removal of Pipe (Cross Drain) 24" RCP | LNFT | 64 |
| 0011 | 202-02-32120 | Removal of Pipe (Side Drain) 12" RCP | LNFT | 118 |
| 0012 | 202-02-32120 | Removal of Pipe (Side Drain) 15" CMP | LNFT | 30 |
| 0013 | 202-02-32120 | Removal of Pipe (Side Drain) 15" Plastic | LNFT | 20 |
| 0014 | 202-02-32120 | Removal of Pipe (Side Drain) 18" CMP | LNFT | 31 |
| 0015 | 202-02-32120 | Removal of Pipe (Side Drain) 18" Plastic | LNFT | 74 |
| 0016 | 202-02-38300 | Removal of Sign and U-Channel Post | EACH | 55 |
| 0017 | 203-01-00100 | General Excavation | CUYD | 3,886.5 |
| 0018 | 203-07-00100 | Borrow (Vehicular Measurement) | CUYD | 566 |
| 0019 | 204-06-00100 | Temporary Silt Fencing | LNFT | 300 |
| 0020 | 302-02-08080 | Class II Base Course (8" Thick) (Asphalt Concrete Base) | SQYD | 16,756.8 |
| 0021 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | CUYD | 400 |
| 0022 | 502-01-00100 | Asphalt Concrete | TON | 23,836.2 |
| 0023 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | TON | 2,065.3 |
| 0024 | 509-01-00100 | Milling Asphalt Pavement | SQYD | 140,534 |
| 0025 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | CUYD | -4,870 |
| 0026 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | SQYD | 6,575 |
| 0027 | 701-01-00900 | Cross Drain Pipe (18" RCP) | LNFT | 252 |
| 0028 | 701-01-01001 | Cross Drain Pipe (24" RCP) | LNFT | 228 |
| 0029 | 701-03-01002 | Storm Drain Pipe (15" RCP/RPVCP) | LNFT | 4 |
| 0030 | 701-04-01020 | Storm Drain Pipe Arch (18" Equiv. RCPA) | LNFT | 823 |
| 0031 | 701-07-00300 | Yard Drain Pipe (8") | LNFT | 16 |
| 0032 | 701-15-00100 | Concrete Collar | EACH | 21 |
| 0033 | 702-01-00100 | Junction Boxes 2' x 2' | EACH | 2 |
| 0034 | 702-03-00100 | Catch Basins (CB-01) | EACH | 15 |
| 0035 | 702-03-00400 | Catch Basins (CB-05) | EACH | 2 |
| 0036 | 702-04-00100 | Adjusting Manholes | EACH | 1 |
| 0037 | 702-04-00150 | Adjusting Manholes w/Manhole Adjustment Rings | EACH | 1 |
| 0038 | 702-04-00200 | Adjusting Catch Basins | EACH | 5 |
| 0039 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | LNFT | 57 |
| 0040 | 704-01-02005 | Guard Rail (DoubleThrie Beam) (18.75" Post Spacing) | LNFT | 42.2 |
| 0041 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | LNFT | 218.9 |
| 0042 | 704-06-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | LNFT | 10 |
| 0043 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | LNFT | 75 |
| 0044 | 704-07-00250 | MASH Guard Rail Transitions (Nested Thrie Beam) | LNFT | 65.7 |
| 0045 | 704-10-00310 | Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) | EACH | 6 |
| 0046 | 706-01-00100 | Concrete Walk (4" Thick) | SQYD | 124.9 |
| 0047 | 706-02-00200 | Concrete Drive (6" Thick) | SQYD | 142.3 |
| 0048 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | SQYD | 47.3 |
| 0049 | 706-04-00110 | Curb Ramps Type 4 | SQYD | 17.9 |
| 0050 | 706-04-00110 | Curb Ramps Type 6 | SQYD | 13.7 |
| 0051 | 706-04-00110 | Curb Ramps Type 7 | SQYD | 26.6 |
| 0052 | 707-01-00100 | Concrete Curb | LNFT | 125 |
| 0053 | 707-01-00100 | Concrete Curb Barrier | LNFT | 278 |
| 0054 | 707-01-00100 | Concrete Curb Mountable | LNFT | 589 |
| 0055 | 711-01-03000 | Riprap (30 lb, 14" Thick) | SQYD | 253.5 |
| 0056 | 711-04-00100 | Geotextile Fabric | SQYD | 253.5 |
| 0057 | 713-01-00100 | Temporary Signs and Barricades | LUMP | 1 |
| 0058 | 713-02-00300 | Temporary Pavement Markings (8" Width) | LNFT | 1,488 |
| 0059 | 713-02-00500 | Temporary Pavement Markings (24" Width) | LNFT | 2,178 |
| 0060 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | MILE | 16.558 |
| 0061 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | MILE | 10.847 |
| 0062 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | MILE | 51.778 |
| 0063 | 716-01-00100 | Mulch (Vegetative) | TON | 7.7 |
| 0064 | 717-01-00100 | Seeding | LB | 152 |
| 0065 | 718-01-00100 | Fertilizer | LB | 5,075 |
| 0066 | 726-01-00100 | Bedding Material | CUYD | 891.3 |
| 0067 | 727-01-00100 | Mobilization | LUMP | 1 |
| 0068 | 729-16-00300 | Object Marker Assembly (Type 3) | EACH | 71 |
| 0069 | 729-19-00300 | Dead End Road Installations (Type C) | EACH | 60 |
| 0070 | 731-02-00100 | Reflectorized Raised Pavement Markers | EACH | 2,215 |
| 0071 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | LNFT | 744 |
| 0072 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | LNFT | 969 |
| 0073 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | LNFT | 120 |
| 0074 | 732-01-05200 | Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 125 mil) | LNFT | 866 |
| 0075 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | MILE | 25.007 |
| 0076 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | MILE | 5.064 |
| 0077 | 732-05-00100 | Removal of Existing Markings | MILE | 0.081 |
| 0078 | 735-01-00100 | Mailboxes | EACH | 369 |
| 0079 | 735-02-00100 | Mailbox Supports (Single) | EACH | 283 |
| 0080 | 735-03-00100 | Mailbox Supports (Double) | EACH | 43 |
| 0081 | 736-01-00100 | Trenching and Backfilling | LNFT | 10 |
| 0082 | 736-09-00100 | Loop Detector | LNFT | 224 |
| 0083 | 736-11-00050 | Conduit (1/2" HDPE, Schedule 80) | LNFT | 10 |
| 0084 | 740-01-00100 | Construction Layout | LUMP | 1 |
| 0085 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | INLF | 123,598 |
| 0086 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | INLF | 7,803 |
| 0087 | NS-602-00001 | Milling Concrete Pavement | SQYD | 1,182 |
| 0088 | NS-700-00840 | Impact Attenuator (Reusable, Test Level 3) | EACH | 2 |
| 0089 | NS-719-00002 | Tree Trimming | LUMP | 1 |
| 0090 | NS-DEV-50241 | Flexible Pavement High Friction Surface Treatment | SQYD | 5,360 |