Line Number | Item | Description | Unit | Quantity |
| 0001 | 201-01-00200 | Clearing and Grubbing (Selective) 0.24 ACRES | LUMP | 1 |
| 0002 | 202-02-02000 | Removal of Asphalt Drives | SQYD | 255 |
| 0003 | 202-02-02020 | Removal of Asphalt Pavement | SQYD | 1,627.4 |
| 0004 | 202-02-04560 | Removal of Bridge Joint Removal of Bridge Joint | LNFT | 1,055 |
| 0005 | 202-02-06100 | Removal of Concrete Walks and Drives | SQYD | 276 |
| 0006 | 202-02-14500 | Removal of Guard Rail | LNFT | 3,001 |
| 0007 | 202-02-32100 | Removal of Pipe (Cross Drain) 24" RCP | LNFT | 8 |
| 0008 | 203-07-00100 | Borrow (Vehicular Measurement) | CUYD | 3,300 |
| 0009 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | EACH | 58 |
| 0010 | 204-06-00100 | Temporary Silt Fencing | LNFT | 1,948 |
| 0011 | 303-02-00100 | Removal of Existing Patches | SQYD | 270 |
| 0012 | 303-03-00400 | In-Place Cement Treated Base Course (12" Thick) | SQYD | 74,807 |
| 0013 | 304-01-00100 | Lime | TON | 321.58 |
| 0014 | 304-03-00400 | Lime Treatment (Type C) (12" Thick) | SQYD | 22,686 |
| 0015 | 309-01-12000 | In-Place Cement Treated Subgrade (12" Thick) | SQYD | 73,498 |
| 0016 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | CUYD | 1,571 |
| 0017 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | CUYD | 200 |
| 0018 | 502-01-00100 | Asphalt Concrete | TON | 19,559.2 |
| 0019 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | TON | 1,738.5 |
| 0020 | 509-01-00100 | Milling Asphalt Pavement | SQYD | 61,923 |
| 0021 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | CUYD | -6,200 |
| 0022 | 510-01-00250 | Pavement Patching (14 inch Minimum Thickness) | SQYD | 603 |
| 0023 | 701-01-01001 | Cross Drain Pipe (24" RCP) | LNFT | 16 |
| 0024 | 701-05-01086 | Side Drain Pipe (30" RCP/RPVCP/CPEPDW/CPPPDW/CPPPTW) | LNFT | 64 |
| 0025 | 701-15-00100 | Concrete Collar | EACH | 2 |
| 0026 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | LNFT | 250 |
| 0027 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | LNFT | 556.3 |
| 0028 | 704-06-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | LNFT | 50 |
| 0029 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | LNFT | 300 |
| 0030 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | EACH | 7 |
| 0031 | 704-10-00310 | Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) | EACH | 5 |
| 0032 | 706-02-00200 | Concrete Drive (6" Thick) | SQYD | 259.9 |
| 0033 | 707-04-00100 | Asphalt Curb | LNFT | 108 |
| 0034 | 711-01-03000 | Riprap (30 lb, 14" Thick) | SQYD | 150 |
| 0035 | 711-04-00100 | Geotextile Fabric | SQYD | 150 |
| 0036 | 712-02-00100 | Sacked Concrete Revetment | SQYD | 4 |
| 0037 | 712-04-00100 | Flexible Revetment | SQYD | 6 |
| 0038 | 713-01-00100 | Temporary Signs and Barricades | LUMP | 1 |
| 0039 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | MILE | 11.826 |
| 0040 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | MILE | 11.826 |
| 0041 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | MILE | 45.53 |
| 0042 | 722-02-00100 | Project Site Laboratory (Equipped) | EACH | 1 |
| 0043 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | MILE | 10.174 |
| 0044 | 726-01-00100 | Bedding Material | CUYD | 17.6 |
| 0045 | 727-01-00100 | Mobilization | LUMP | 1 |
| 0046 | 729-16-00200 | Object Marker Assembly (Type 2) | EACH | 11 |
| 0047 | 729-16-00300 | Object Marker Assembly (Type 3) | EACH | 12 |
| 0048 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | EACH | 2,140 |
| 0049 | 731-02-00100 | Reflectorized Raised Pavement Markers | EACH | 1,003 |
| 0050 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | MILE | 15.177 |
| 0051 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | MILE | 3.942 |
| 0052 | 732-05-00100 | Removal of Existing Markings | MILE | 0.198 |
| 0053 | 735-01-00100 | Mailboxes | EACH | 55 |
| 0054 | 735-02-00100 | Mailbox Supports (Single) | EACH | 55 |
| 0055 | 739-01-00100 | Hydro-Seeding | ACRE | 5.14 |
| 0056 | 740-01-00100 | Construction Layout | LUMP | 1 |
| 0057 | 815-03-00200 | Joint Seal (Preformed Silicone) | LNFT | 775 |
| 0058 | 815-03-00300 | Joint Seal (Poured) | LNFT | 280 |