Line Number | Item | Description | Unit | Quantity |
0001 | 201-01-00100 | Clearing and Grubbing | LUMP | 1 |
0002 | 202-02-00020 | Removal of Concrete Walks and Drives | SQYD | 5,075 |
0003 | 202-02-14500 | Removal of Guard Rail | LNFT | 299.65 |
0004 | 202-03-00010 | Relocation (Sign and Pole) | EACH | 13 |
0005 | 704-03-00100 | Blocked Out Guard rail | LNFT | 100 |
0006 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | EACH | 5 |
0007 | 706-01-00100 | Concrete Walk (4" Thick) | SQYD | 7,832.3 |
0008 | 706-02-00300 | Concrete Drive (8" Thick) | SQYD | 1,733.6 |
0009 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | SQYD | 27.9 |
0010 | 706-04-00100 | Handicapped Curb Ramps Type 1 | EACH | 8 |
0011 | 706-04-00100 | Handicapped Curb Ramps Type 10 | EACH | 4 |
0012 | 706-04-00100 | Handicapped Curb Ramps Type 2 | EACH | 9 |
0013 | 706-04-00100 | Handicapped Curb Ramps Type 5 | EACH | 10 |
0014 | 706-04-00100 | Handicapped Curb Ramps Type 6 | EACH | 1 |
0015 | 706-04-00100 | Handicapped Curb Ramps Type 7 | EACH | 46 |
0016 | 707-01-00100 | Concrete Curb | LNFT | 47.5 |
0017 | 713-01-00100 | Temporary Signs and Barricades | LUMP | 1 |
0018 | 727-01-00100 | Mobilization | LUMP | 1 |
0019 | 740-01-00100 | Construction Layout | LUMP | 1 |
0020 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | INLF | 362.4 |
0021 | TS-700-04000 | Drainage Grates (Replacement) (Furnish & Install) | EACH | 9 |
0022 | TS-800-00210 | Safety Rail (Furnished and Installed) (Over Drainage Ditch) | LNFT | 36.7 |