Line Number | Item | Description | Unit | Quantity |
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | LUMP | 1 |
| 0002 | 202-02-02020 | Removal of Asphalt Pavement | SQYD | 828.5 |
| 0003 | 202-02-03010 | Removal of Base – Recycled PCC or Stone | SQYD | 285.9 |
| 0004 | 202-02-03010 | Removal of Base – Recycled PCC or Stone (8") | SQYD | 542.6 |
| 0005 | 202-02-04501 | Removal of Bridge (Sta. 105+55, 47.7' X 57.2' Timber Bridge) | LUMP | 1 |
| 0006 | 202-02-04501 | Removal of Bridge (Sta. 205+91, 36.9' x 95' Timber Bridge) | LUMP | 1 |
| 0007 | 202-02-06000 | Removal of Concrete Approach Slabs | SQYD | 167.9 |
| 0008 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | LNFT | 604.5 |
| 0009 | 202-02-06100 | Removal of Concrete Walks and Drives | SQYD | 451 |
| 0010 | 203-02-00100 | Drainage Excavation | CUYD | 356 |
| 0011 | 203-05-00100 | Excavation and Embankment | LUMP | 1 |
| 0012 | 204-02-00100 | Temporary Hay Bales | EACH | 30 |
| 0013 | 204-06-00100 | Temporary Silt Fencing | LNFT | 1,000 |
| 0014 | 302-02-08070 | Class II Base Course (8" Thick) (Crushed Stone or Recycled Portland Cement Concrete) | SQYD | 647.1 |
| 0015 | 502-01-00100 | Asphalt Concrete | TON | 148.1 |
| 0016 | 701-03-01002 | Storm Drain Pipe (15" RCP/RPVCP) | LNFT | 30 |
| 0017 | 702-03-00500 | Catch Basins (CB-06) | EACH | 1 |
| 0018 | 702-04-00200 | Adjusting Catch Basins | EACH | 1 |
| 0019 | 706-01-00100 | Concrete Walk (4" Thick) | SQYD | 318.7 |
| 0020 | 706-02-00200 | Concrete Drive (6" Thick) | SQYD | 162.4 |
| 0021 | 706-04-00100 | Handicapped Curb Ramps | EACH | 3 |
| 0022 | 707-03-00100 | Combination Concrete Curb and Gutter | LNFT | 470 |
| 0023 | 711-01-03020 | Riprap (30 lb, 18" Thick) | SQYD | 798 |
| 0024 | 711-04-00100 | Geotextile Fabric | SQYD | 798 |
| 0025 | 713-01-00100 | Temporary Signs and Barricades | LUMP | 1 |
| 0026 | 714-01-00700 | Slab Sodding (Centipede) | SQYD | 547 |
| 0027 | 717-01-00100 | Seeding | LB | 16 |
| 0028 | 718-01-00100 | Fertilizer | LB | 400 |
| 0029 | 726-01-00100 | Bedding Material | CUYD | 6.7 |
| 0030 | 727-01-00100 | Mobilization | LUMP | 1 |
| 0031 | 729-16-00300 | Object Marker Assembly (Type 3) | EACH | 8 |
| 0032 | 731-02-00100 | Reflectorized Raised Pavement Markers | EACH | 15 |
| 0033 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | MILE | 0.108 |
| 0034 | 740-01-00100 | Construction Layout | LUMP | 1 |
| 0035 | 802-01-00100 | Structural Excavation (Bents) | CUYD | 236 |
| 0036 | 804-01-00400 | Precast Concrete Piles (18") | LNFT | 1,350 |
| 0037 | 804-01-00600 | Precast Concrete Piles (24") | LNFT | 1,500 |
| 0038 | 804-14-00100 | Dynamic Monitoring Assistance | EACH | 4 |
| 0039 | 804-15-00100 | Dynamic Monitoring Instrumentation | LUMP | 1 |
| 0040 | 804-17-00100 | Construction Site Survey | LUMP | 1 |
| 0041 | 804-18-00100 | Vibration Monitoring | DAY | 12 |
| 0042 | 805-01-00100 | Class A1 Concrete (Slab Span) | CUYD | 462.98 |
| 0043 | 805-01-00300 | Class A1 Concrete (Bent Cap) | CUYD | 163.09 |
| 0044 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | SQFT | 1,785 |
| 0045 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | SQFT | 8,739 |
| 0046 | 806-01-00100 | Deformed Reinforcing Steel (XX) | LB | 131,277 |
| 0047 | 810-03-00100 | Concrete and Metal Bridge Railing | LNFT | 370 |
| 0048 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | SQFT | 3,396 |
| 0049 | 814-01-00100 | Elastomeric Bearing Pads (Non-Reinforced) | SFIN | 380 |
| 0050 | 815-03-00300 | Joint Seal (Poured) | LNFT | 519 |
| 0051 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | INLF | 408 |