0001201-01-00100Clearing and Grubbing LUMP1
0002202-01-00100Removal of Structures and Obstructions LUMP1
0003202-02-02020Removal of Asphalt Pavement SQYD1,849.3
0004202-02-04501Removal of Bridge (STA 200+00; 19' x 31' TIMBER - PILES, BENTS, & GUARD RAIL, TIMBER DECK W/ ASPHALT)LUMP1
0005202-02-12000Removal of Fence LNFT340
0006202-02-32100Removal of Pipe (Cross Drain) ((2) 84'' x 60' CMP pipe)LNFT120
0007203-05-00100Excavation and Embankment LUMP1
0008204-03-00100Temporary Slope Drains LNFT250
0009204-06-00100Temporary Silt Fencing LNFT1,770
0010302-02-08520Class II Base Course (8-1/2" Thick) (Crushed Stone) SQYD1,966
0011401-02-00100Aggregate Surface Course (Adjusted Vehicular Measurement) CUYD27
0012502-01-00100Asphalt Concrete TON369
0013704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) LNFT100
0014704-07-00200Guard Rail Transitions (Double Thrie Beam) LNFT200
0015704-10-00205Guard Rail End Treatment, MASH, (TL-3 Tangent) EACH8
0016711-01-04000Riprap (55 lb, 18" Thick) SQYD1,500
0017711-04-00100Geotextile Fabric SQYD1,500
0018713-01-00100Temporary Signs and Barricades LUMP1
0019716-01-00100Mulch (Vegetative) TON1.4
0020717-01-00100Seeding LB22
0021718-01-00100Fertilizer LB707
0022727-01-00100Mobilization LUMP1
0023729-16-00300Object Marker Assembly (Type 3) EACH8
0024731-02-00100Reflectorized Raised Pavement Markers EACH23
0025737-03-00100Painted Traffic Striping (Solid Line) (4" Width) LNFT1,744
0026740-01-00100Construction Layout LUMP1
0027804-01-00300Precast Concrete Piles (16") LNFT1,920
0029805-12-00100Bridge Superstructure and Substructure (24' Roadway, 90 Degree Crossing) SQFT1,920
0030805-12-00300Bridge Superstructure and Substructure (24' Roadway, 60 Degree Crossing) SQFT1,440
0031813-01-00100Concrete Approach Slabs (Cast-in-Place) (24' Clear Roadway, 90 Degree skew, 10' Long)SQFT500
0032813-01-00100Concrete Approach Slabs (Cast-in-Place) 24' Clear Rodway, 90 Degree skew, 10' long)SQFT500
0033NS-500-00340Saw Cutting Asphalt Concrete Pavement INLF240