Projects Under Construction

District 62

    Updated 17 Nov 2025

Districtwide Projects

Livingston Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

US 190 & La 1026 (Roundabout)
H.000464.6 - Asphalt widening and overlay
Proj. Engr: Delee, Glenn Route: LA 1026 US 190 map
Contractor: Kort's Construction Services, Miles: 0.48
Work Order Date Contract Amount Estimated Completion Date
2018-04-11 $6,610,414 End of 2019


Juban Rd Widening (I-12 to US 190)
H.000464.6A - Asphalt widening and overlay
Proj. Engr: Delee, Glenn Route: LA 1026 US 190 map
Contractor: Kort's Construction Services, Miles: 0.48
Work Order Date Contract Amount Estimated Completion Date
2024-02-07 $15,811,781 Fall of 2026


Amite R. Br. Near French Settlement
H.002375.6 - New location/replacement of bridge
Proj. Engr: Watson, Christopher Route: LA 16 map
Contractor: Tl Hawk, LLC Miles: 0.87
Work Order Date Contract Amount Estimated Completion Date
2020-02-08 $20,700,451 Summer of 2023


I-12: La 63 - Tangipahoa Parish Line
H.003425.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Watson, Christopher Route: I-12 map
Contractor: Barriere Construction Co., LLC Miles: 16.46
Work Order Date Contract Amount Estimated Completion Date
2021-04-15 $22,281,022 End of 2022


Juban Rd Widening (I-12 to US 190)
H.004634.6 - Concrete new pavement
Proj. Engr: Delee, Glenn Route: LA 1026 map
Contractor: Kcr Contractors, LLC Miles: 0.86
Work Order Date Contract Amount Estimated Completion Date
2019-09-11 $15,287,043 Fall of 2025


LA 442: La 63 - W. Jct. La 441
H.010384.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Watson, Christopher Route: LA 442 LA 441 map
Contractor: Madden Gulf Coast, LLC Miles: 5.88
Work Order Date Contract Amount Estimated Completion Date
2025-10-10 $3,310,373 Spring of 2026


Cook Road Imp: La 16 to Juban Crossing
H.012308.6 - Concrete new pavement
Proj. Engr: Brown, Kresten Route: LA 16 map
Contractor: Richard Price Contracting Co, Miles: 0.91
Work Order Date Contract Amount Estimated Completion Date
2022-05-01 $16,806,158 Summer of 2025


LA 1026: Roundabout @ Eden Church Road
H.012348.6 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: Watson, Christopher Route: LA 1026 map
Contractor: Omega Foundation Services Miles: 0.24
Work Order Date Contract Amount Estimated Completion Date
2023-12-21 $3,079,662 Fall of 2024


Dist 62: Raised Rumble Strips Evaluation
H.015690.6 - Striping and pavement markers
Proj. Engr: Watson, Christopher Route: LA 16 LA 1026 map
Contractor: Highway Graphics LLC Miles: 23.25
Work Order Date Contract Amount Estimated Completion Date
2024-08-15 $1,099,605 End of 2024


Dist 62: Wet Reflective Pave Mark Eval
H.015691.6 - Striping and pavement markers
Proj. Engr: James, Clay Route: LA 16 LA 1077 map
Contractor: Highway Graphics LLC Miles: 9.75
Work Order Date Contract Amount Estimated Completion Date
2025-07-11 $249,572 Fall of 2025


District 62: Pavement Markers Repl
H.016444.6 - Striping and pavement markers
Proj. Engr: James, Clay Route: I-12 map
Contractor: Stripe-a-Zone, LLC Miles: 64.10
Work Order Date Contract Amount Estimated Completion Date
2025-11-06 $2,237,606 Spring of 2027


Port Vincent Br New Grid Floor
H.971897 - Moveable bridges reconditioned
Proj. Engr: Wascom, Kris Route: map
Contractor: Boh Bros. Construction Co., Ll Miles: 0.07
Work Order Date Contract Amount Estimated Completion Date
2012-03-23 $473,316 Spring of 2012


Walker Landscaping Project
268-01-0015 - Miscellaneous
Proj. Engr: Zzzz Hollowell, Clay Route: LA 447 I-12 map
Contractor: Twin Shores Lands. & Const Serv I Miles: 1.30
Work Order Date Contract Amount Estimated Completion Date
2009-03-23 $213,013 Summer of 2009


St. Helena Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 448: La 37 - La 10
H.014115.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Watson, Christopher Route: LA 448 map
Contractor: Madden Gulf Coast, LLC Miles: 8.60
Work Order Date Contract Amount Estimated Completion Date
2025-06-15 $3,448,948 Beginning of 2026


LA 43: Drainage Improvements
H.014141.6 - Drainage
Proj. Engr: Golz, Sarah Route: LA 43 map
Contractor: 21 Construction, L.L.C. Miles: 0.36
Work Order Date Contract Amount Estimated Completion Date
2025-10-24 $190,827 Beginning of 2026


St. John Baptist Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 3127: St. James P/L - St. Charles P/L
H.010385.6 - Asphalt overlay of asphalt pavement
Proj. Engr: James, Clay Route: LA 3127 map
Contractor: Barriere Construction Co., LLC Miles: 8.87
Work Order Date Contract Amount Estimated Completion Date
2025-10-01 $13,240,935 Fall of 2027


St. John Eb Miss River Trail, Phase 4
H.011845.6 - Sidewalks/bike paths
Proj. Engr: Zzzz Oustalet, Randy Route: LA 44 map
Contractor: Magee Excavation & Development Miles: 1.14
Work Order Date Contract Amount Estimated Completion Date
2019-04-16 $2,587,920 End of 2022


Highway 61 Streetscape Improvements
H.013239.6-R2 - Sidewalks/bike paths
Proj. Engr: Liang, Frank Route: US 61 map
Contractor: Kort's Construction Services, Miles: 0.78
Work Order Date Contract Amount Estimated Completion Date
2025-05-22 $3,760,919 Beginning of 2026


US 61: Wildcat Dr - Airport Rd
H.014109.6 - Asphalt overlay of asphalt pavement
Proj. Engr: James, Clay Route: US 61 map
Contractor: Barber Bros. Contracting Co., Miles: 2.94
Work Order Date Contract Amount Estimated Completion Date
2025-07-17 $5,173,242 Summer of 2026


US 61: Airport Rd - St James P/L
H.014111.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Zzzz Boutte, Christian Route: US 61 map
Contractor: Madden Gulf Coast, LLC Miles: 5.20
Work Order Date Contract Amount Estimated Completion Date
2024-10-01 $11,515,553 Spring of 2026


LA 628: Lm 0.522 - St Charles P/L
H.015362.6 - Asphalt overlay of asphalt pavement
Proj. Engr: James, Clay Route: LA 628 map
Contractor: R.J. Daigle & Sons Contractors Miles: 2.13
Work Order Date Contract Amount Estimated Completion Date
2025-05-02 $1,410,177 Fall of 2025


I-10: St John Pl to US 51 Pave Mkgs
H.016028.6 - Striping and pavement markers
Proj. Engr: James, Clay Route: I-10 map
Contractor: Southern Synergy LLC Miles: 12.50
Work Order Date Contract Amount Estimated Completion Date
2025-07-14 $498,537 Fall of 2025


St. Tammany Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Boston Street Beautification
H.000486.6 - Sidewalks/bike paths
Proj. Engr: Zzzz Harper, Daniel Route: US 190-X map
Contractor: Kass Bros. Inc. Miles: 0.47
Work Order Date Contract Amount Estimated Completion Date
2012-09-17 $550,353 Fall of 2013


US 190: La 437 - US 190 Bus (Ph1)
H.001344.6 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: Adams, Kevin Route: US 190 LA 437 map
Contractor: Boh Bros. Construction Co., Ll Miles: 1.18
Work Order Date Contract Amount Estimated Completion Date
2022-06-01 $30,671,433 Beginning of 2024


Abita Springs Town Ctr Sidewalk Lighting
H.009934.6 - Sidewalks/bike paths
Proj. Engr: Martin, David Route:
Contractor: Ernest P. Breaux Electrical, L Miles: 0.69
Work Order Date Contract Amount Estimated Completion Date
2023-12-11 $660,581 Beginning of 2025


I-12: La 1077 to La 21
H.011137.6 - Asphalt widening and overlay
Proj. Engr: Faucheux, Cody Route: I-12 LA 21 map
Contractor: James Construction Group LLC Miles: 3.65
Work Order Date Contract Amount Estimated Completion Date
2023-07-01 $57,284,940 Summer of 2026


US 11 & US 190 Bicycle & Ped Crossings
H.011775.6 - Striping and pavement markers
Proj. Engr: Pechon, Brady Route: US 11 US 190-Y map
Contractor: Kort's Construction Services, Miles: 0.23
Work Order Date Contract Amount Estimated Completion Date
2024-07-29 $1,271,963 Spring of 2025


Lindberg Drive @ US 190 (Gause Blvd)
H.013381.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Zzzz Clancy, Blaine Route:
Contractor: Barriere Construction Co., LLC Miles: 0.15
Work Order Date Contract Amount Estimated Completion Date
2022-04-01 $475,672 Summer of 2022


La433 & Us90:bonfouca & E. Pearl Mb Rprs
H.015090.6 - Moveable bridges reconditioned
Proj. Engr: Faucheux, Cody Route: LA 433 US 90 map
Contractor: Coastal Contractors, LLC Miles: 0.24
Work Order Date Contract Amount Estimated Completion Date
2024-03-01 $337,432 Spring of 2024


Access Mgmt Impr Tangipahoa/St Tammany
H.015109.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Adams, Kevin Route: LA 1090 US 190 map
Contractor: Gulf States Services, LLC Miles: 1.10
Work Order Date Contract Amount Estimated Completion Date
2025-08-01 $723,562 Fall of 2025


LA 3241: I-12/La 434 to La 36 Clear/Grub
H.016022.6 - Clearing and grubbing
Proj. Engr: Faucheux, Cody Route: LA 434 map
Contractor: James Construction Group LLC Miles: 6.39
Work Order Date Contract Amount Estimated Completion Date
2024-10-10 $1,797,929 Summer of 2025


I-10/I-12/I-59: Signs & Pvmt Markings
H.016042.6 - Signing
Proj. Engr: Adams, Kevin Route: I-10 map
Contractor: Traffic Control Prod. Co of La Miles: 13.13
Work Order Date Contract Amount Estimated Completion Date
2025-08-01 $3,532,058 Summer of 2027


Tangipahoa Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 3234 University Ave Sidewalks
H.013938.6-R2 - Sidewalks/bike paths
Proj. Engr: Zzzz Boutte, Christian Route: LA 3234 map
Contractor: Gulf States Services, LLC Miles: 1.09
Work Order Date Contract Amount Estimated Completion Date
2024-05-30 $3,522,609 Beginning of 2026


I-12: US 51b (Hammond) Intchg Lighting
H.014271.6 - Roadway lighting
Proj. Engr: Zzzz Boutte, Christian Route: I-12 map
Contractor: Diamond Electrical Co., Inc. Miles: 0.82
Work Order Date Contract Amount Estimated Completion Date
2023-07-14 $973,582 Beginning of 2025


US 51: 2nd St - La 16
H.015309.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Woods, Derek Route: US 51 map
Contractor: Madden Gulf Coast, LLC Miles: 6.12
Work Order Date Contract Amount Estimated Completion Date
2025-03-01 $2,842,415 Beginning of 2026


LA 22: 100' E Olde Mill Ln - Howes Ln
H.016010.6 - Asphalt overlay of asphalt pavement
Proj. Engr: James, Clay Route: LA 22 map
Contractor: Barriere Construction Co., LLC Miles: 1.98
Work Order Date Contract Amount Estimated Completion Date
2025-06-02 $1,994,891 Fall of 2025


I-12: I-55 to La 21 Pavement Markers
H.016034.6 - Striping and pavement markers
Proj. Engr: James, Clay Route: I-12 map
Contractor: Southern Synergy LLC Miles: 20.97
Work Order Date Contract Amount Estimated Completion Date
2025-11-07 $96,446 Beginning of 2026


I-55: La 1050 Opass - St Line
H.016149.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Woods, Derek Route: I-55 map
Contractor: Barriere Construction Co., LLC Miles: 7.90
Work Order Date Contract Amount Estimated Completion Date
2025-08-19 $15,428,777 Spring of 2026


Washington Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 21: Cslm 0.413 - Bogalusa Cl
H.014852.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Hickman, Tommy Jr. Route: LA 21 map
Contractor: Barriere Construction Co., LLC Miles: 6.65
Work Order Date Contract Amount Estimated Completion Date
2025-04-14 $10,316,770 Fall of 2026


LA 25: Washington Parish Sw, Segment a
H.014913.6 - Sidewalks/bike paths
Proj. Engr: Dunn, Nicole Route: LA 25 map
Contractor: Kort's Construction Services, Miles: 0.73
Work Order Date Contract Amount Estimated Completion Date
2024-11-01 $815,571 Spring of 2025


District 62

No districtwide projects.