US 171, Vernon Parish, US 171 @LA 1213, Sp No. H.010264
Tuesday, June 9, 2015 at 4:29:28 PM
US 171, Vernon Parish US 171 @ LA 1213 SP No. H.010264
The Louisiana Department of Transportation and Development (DOTD) announces that, weather permitting, construction work will begin on the US 171 North Bound lane at LA 1213 cross drain replacement project, Thursday, June 18, 2015 and will continue for approximately (2) two months. This 0.015 mile long project will receive drainage structures, pavement patching, and related work.
The project was awarded to the low bidder, Apeck Constuction, Inc. in the amount of $489,209.10.
Permit/Detour section The US 171 North will be open to traffic at all times. There will be no restrictions for regular traffic and a 12’ wide lane width restriction for all oversize vehicles. LA 1213 at the intersection of US 171 North will be closed for the first phase of the project. The US 171 North Bound Lane will be reduced to one lane for the duration of the project. A subsequent press release will be issued to notify the public when the intersection of LA 1213 at US 171 North will re-open to traffic.
Safety reminder DOTD appreciates your patience and reminds you to please drive with caution and be on the lookout for work crews and their equipment.
Additional Information Call (318) 561-5100 or (800) 542-3509 or 511 or visit www.511LA.org for additional information. Motorists may also monitor the LA DOTD website, www.dotd.la.gov, selecting MYDOTD, the LA DOTD Facebook page, or the LA DOTD Twitter page, @Alex_Traffic for further information.
Project Contact Marcus Connella, P.E. LADOTD Project Engineer Vernon Parish 337-238-6406 [email protected]
|