UPDATE - RESCHEDULED: Jimmie Davis Bridge deck pouring operations, Caddo & Bossier Parishes
Wednesday, September 30, 2026 at 5:03:33 PM
UPDATE - RESCHEDULED: Jimmie Davis Bridge deck pouring operations, Caddo & Bossier Parishes (UPDATE 9/30/2026): DOTD advises motorists that the below referenced deck pouring operations for the new Jimmie Davis Bridge project over the Red River have been rescheduled to take place on the night of Thursday, October 9, 2026. The time frame remains the same for the Clyde Fant Parkway southbound closure: 10:00 p.m. to 10:00 a.m.
The Clyde Fant Parkway northbound closure will now take place from 4:00 a.m. to 7:00 a.m. on Friday, October 9th. Both of these closures on the parkway will take place at its interchange with the Jimmie Davis Bridge.
All other information in the notification below remains the same. ________________________________________________________________________________________________________________________________________________________________________________________
Original notification - 9/29/2026:
SHREVEPORT-BOSSIER CITY, La. – The Louisiana Department of Transportation and Development announces the next milestone for the new $361 million LA 511 (Jimmie Davis Bridge) project over the Red River. Deck pouring operations are set to begin, signaling another exciting construction activity for the new structure.
As the project continues to make significant progress, Clyde Fant Parkway southbound will be closed at the interchange with the bridge on the night of Thursday, October 1, 2026 from approximately 10:00 p.m. to 10:00 a.m.
Clyde Fant Parkway northbound will be closed for only a 3 hour time frame, from 4:00 a.m. to 7:00 a.m., on the morning of Friday, October 2nd.
These road closures are necessary to allow concrete deck pouring operations to take place safely and efficiently for both work crews and the traveling public. The deck is the driving surface of the bridge.
Advance warning signage is in place alerting motorists of the planned road closure. Traffic wishing to travel on Clyde Fant will be detoured over the existing bridge and onto Arthur Ray Teague Parkway to the Shreveport-Barksdale Bridge. (see included detour map)
Motorists are also reminded that other construction activities continue to take place throughout the project, and are urged to use extreme caution while traveling within the work zone. Ongoing intermittent lane closures remain in place as widening and reconstruction continues on the LA 511 approaches to the bridge.
The project recently hit another milestone with the completion of the girder installation, officially creating a fully connected structure across the Red River for the first time in nearly 60 years. Be sure to click here to read much more about the project.
Safety reminder:
DOTD appreciates your patience and reminds you to please drive with caution through the construction site and be on the lookout for work crews and their equipment. Remember to leave plenty of room between you and the vehicle in front of you.
Area residents should exercise caution when driving, walking, or biking near an active construction zone.
Additional information:
Call 511, visit www.511la.org, or download the Louisiana 511 mobile app for additional travel information. Out-of-state travelers may call 1-888-ROAD-511 (1-888-762-3511). Motorists may also monitor the LA DOTD website at www.dotd.la.gov, by selecting MyDOTD, or by visiting the DOTD Facebook and X (Twitter) pages.
To track updates and developments related to the T4LA initiative aimed at enhancing the manner in which DOTD serves the state’s citizens, visit www.T4la.com.
Contact Information:
Erin Buchanan DOTD Public Information Officer Shreveport-Bossier District (318) 549-8402 [email protected]
*images attached: detour map & photo of Jimmie Davis Bridge project


|