Search


DOTD Announcements
UPDATED: LA 1026 Eastbound and Westbound & Eden Church Road Northbound and Southbound, Livingston Parish -- Roadwork (Road Construction) H.012348
Monday, June 9, 2025 at 9:22:18 AM
  • Route Name: LA 1026 Eastbound,LA 1026 Westbound
    Start Date: Wednesday, July 16, 2025 at 4:00 AM
    End Date: Wednesday, July 16, 2025 at 6:00 AM
    (Weather Permitting)
    Closure Type: Roadwork
    Lanes Affected: Partial Closure/ All Lanes
    Special Notes: This is an Alternating lane closure.
    Start Cross Street: COUNTRY CLUB DR
    End Cross Street: POWER SUBSTATION
    Detour/Alternate Route: Westbound motorists can take LA 1026 East to LA 1027 South to US 190 West to LA 16 North back on to LA 1026. Eastbound motorists can take LA 1026 West to LA 16 South to US 190 East to LA 1027 North back to LA 1026.

  • Route Name: Northbound and Southbound Eden Church Road
    Start Date: Wednesday, July 16, 2025 at 4:00 AM
    End Date: Wednesday, July 16, 2025 at 6:00 AM
    (Weather Permitting)
    Closure Type: Roadwork
    Lanes Affected: Partial Closure/ All Lanes
    Special Notes: This is an Alternating lane closure.
    Start Cross Street: FAIRWAY DRIVE
    End Cross Street: LA 1026
    Detour/Alternate Route: Westbound motorists can take LA 1026 East to LA 1027 South to US 190 West to LA 16 North back on to LA 1026. Eastbound motorists can take LA 1026 West to LA 16 South to US 190 East to LA 1027 North back to LA 1026.


Open Interactive Map
Image
    Comments
    These lane closures are to allow crews to pour concrete on the project. Flagman will be in place at all times. All message boards have been updated to show this closure.
    Safety Reminder
    DOTD appreciates your patience and reminds you to please drive with caution through the work zone and be on the lookout for work crews and their equipment.
    Project: H.012348