US 51 Northbound,US 51 Southbound, St. John the Baptist Parish -- Roadwork (Traffic Signal Work) H.012639.6
Thursday, May 29, 2025 at 8:30:59 AM
- Route Name: US 51 Northbound,US 51 Southbound
Start Date: Monday, June 02, 2025 at 8:00 PM End Date: Thursday, June 05, 2025 at 6:00 AM (Weather Permitting) Closure Type: Roadwork Lanes Affected: Partial Closure/ Other (see comments) Start Cross Street: US 51 End Cross Street: US 51
Open Interactive Map
Comments There will be a nightly northbound and southbound through lane closure beginning at 8PM on Monday, June 2, 2025 through 6AM on Thursday, June 5, 2025. The purpose of this lane closure is to aid in the installation of traffic signals across US 61 in St. John Parish. Safety Reminder DOTD appreciates your patience and reminds you to please drive with caution through the work zone and be on the lookout for work crews and their equipment. Project: H.012639.6
|