SLIGO RD @ WALTER CREEK, WEST FELICIANA PARISH, SP#H.013957
Wednesday, January 8, 2025 at 12:07:28 PM
3.8 miles from Angola Road (LA 66), Sligo Road will be closed to all thru traffic beginning Monday, January 13th at 8:00AM, in order to replace an old bridge with box culvers across Walter Creek. The expected date of re-opening the road is March 28, 2025.

Traffic will be detoured using Ouida Irondale to and from LA 66.

Emergency vehicles will not have access through the work site and will have to use the detour route.

DOTD appreciates your patience and reminds you to please drive with caution through the construction site. Please look out for work crews and their equipment.

Dane LeCoq
Project Engineer
West Feliciana Parish
District 61
225-683-5548