EB & WB US 90 (Jefferson Hwy) between LA 3152 (Clearview Pkwy) & Dakin St,, Jefferson Parish -- Roadwork (Paving Operations) H.013757
Thursday, July 7, 2022 at 3:02:28 PM
  • Route Name: US 90 Eastbound,US 90 Westbound
    Start Date: Saturday, July 09, 2022 at 7:00 AM
    End Date: Sunday, July 10, 2022 at 9:00 PM
    (Weather Permitting)
    Closure Type: Roadwork
    Lanes Affected: Partial Closure/ All Lanes
    Special Notes: This is an Alternating lane closure.
    Start Cross Street: LA 3152, S. Clearview Parkway
    End Cross Street: Dakin St
    Recurrence: Alternating lane closures from 7 AM Saturday, June 9th - 9 PM Sunday night, July 10th for asphalt and concrete work


Open Interactive Map
Image
    Comments
    Expect minor delays
    Safety Reminder
    DOTD appreciates your patience and reminds you to please drive with caution through the work zone and be on the lookout for work crews and their equipment.
    Project: H.013757