LA 105: St. Landry Parish Line to LA 1183; Avoyelles Parish; H.012107
Thursday, March 29, 2018 at 3:24:51 PM
March 29, 2018
LA 105: St. Landry Parish Line to LA 1183 Avoyelles Parish S.P. No. H.012107 Control Section No. 144-04
The Louisiana Department of Transportation and Development (DOTD), advises the public that, weather permitting, on Thursday, April 5, 2018 road construction work will begin on LA 105 from the St. Landry Parish Line to the intersection of LA 1183.
This 5.9 miles long road base rehabilitation construction project will consist of in-place cement treated base course, superpave asphaltic concrete pavement, and related work.
This contract was awarded to the low bidder, Prairie Contractors Inc. in the amount of $2,204,507.93.
Permit/Detour Section No wide loads will be allowed beginning April 5, 2018. The roadway will be open to traffic at all times; however, there will be lane closures. Unpaved roadway conditions will exist during base course construction.
Safety Reminder DOTD appreciates your patience and reminds you to please drive with caution through the construction site and be on the lookout for work crews and their equipment.
Additional Information Call (318) 561-5100 or (800) 542-3509 or 511 or visit www.511LA.org for additional information. Motorists may also monitor the LA DOTD website @ www.dotd.la.gov, by selecting MYDOTD, the Way to Geaux Application for iPhone or Android devices, the DOTD Facebook page or the LA DOTD Twitter page, @Alex_Traffic for further information and details.
Project Contact Joseph Montalvo District 08, Project Engineer 318-346-4582 [email protected]
Media Contact Mr. Rodney Mallet, Public Information Officer Avoyelles, Rapides, and Vernon Parishes Phone # 225-379-1275 [email protected]
|