Bid Tabulations for the Letting of 7/14/2021 LA DOTD Headquarters

Proposal:H.012338.6
Parish:Terrebonne
Description:CIVIC CENTER SIDEWALKS
Type Construction:CLEARING AND GRUBBING, GRADING, CONCRETE WALK, AND RELATED WORK.
Estimated Construction Cost:$226,012.00
140312GRAY CONSTRUCTION CORP.$168,542.07


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
GRAY CONSTRUCTION CORP.
Unit PriceTotal
Amount
0001201-01-00100Clearing and Grubbing 1     LUMP3,500.003,500.00
0002202-01-00100Removal of Structures and Obstructions 1     LUMP500.00500.00
0003202-02-06100Removal of Concrete Walks and Drives 210     SQYD31.106,531.00
0004202-02-06140Removal of Curbs (Concrete) 313     LNFT17.005,321.00
0005202-03-38000Relocation of Sign Traffic Signs4     EACH500.002,000.00
0006203-05-00100Excavation and Embankment 1     LUMP12,800.0012,800.00
0007204-06-00100Temporary Silt Fencing 3,020     LNFT1.504,530.00
0008706-01-00100Concrete Walk (4" Thick) 1,636.9   SQYD49.5081,026.55
0009706-02-00200Concrete Drive (6" Thick) 210.2   SQYD68.1014,314.62
0010706-04-00100Handicapped Curb Ramps 14     EACH568.007,952.00
0011713-01-00100Temporary Signs and Barricades 1     LUMP6,300.006,300.00
0012727-01-00100Mobilization 1     LUMP14,000.0014,000.00
0013732-01-02080Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) 77     LNFT21.001,617.00
0014732-05-00100Removal of Existing Markings 0.015 MILE64,000.00960.00
0015739-01-00100Hydro-Seeding 1.15  ACRE3,250.003,737.50
0016740-01-00100Construction Layout 1     LUMP1,800.001,800.00
0017NS-600-00220Saw Cutting Portland Cement Concrete Pavement 1,944     INLF0.851,652.40
       
  CONTRACTOR TOTAL   168,542.07