Bid Tabulations for the Letting of 11/18/2020 LA DOTD Headquarters

Proposal:H.008415.6
Parish:East Baton Rouge
Description:INFORMATION CENTER @ SOUTHERN UNIVERSITY
Type Construction:BUILDING CONSTRUCTION AND RELATED WORK.
Estimated Construction Cost:$3,675,955.00
138783Blount General Contractors LLC$3,828,000.00
243263SIENNA CONSTRUCTION, L.L.C.$4,067,000.00
318310Guy Hopkins Construction Co Inc$4,084,000.00
437753Ken Tillage Construction, Co.$4,644,938.00


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
Blount General Contractors LLC
- 2 -
SIENNA CONSTRUCTION, L.L.C.
- 3 -
Guy Hopkins Construction Co Inc
- 4 -
Ken Tillage Construction, Co.
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001TS-823-03000Building (Information Center @ Southern University)1     LUMP3,828,000.003,828,000.004,067,000.004,067,000.004,084,000.004,084,000.004,644,938.004,644,938.00
             
  CONTRACTOR TOTAL   3,828,000.00 4,067,000.00 4,084,000.00 4,644,938.00