Proposal:4400019384
Parish:Bienville, Bossier, Caddo, Lincoln, Madison, Ouachita, Richland, Webster
Routes:VARIOUS
Description:HIGH-TENSION CABLE BARRIER REPAIRS IN DISTS. 04, 05 AND 58
Type Construction:REPAIR AND MAINTENANCE OF HIGH TENSION CABLE BARRIER AND RELATED WORK.
Estimated Construction Cost:$370,372.75
| Rank | License | Bidder | Construction Bid |
| 1 | 64826 | Highway Safety Systems LLC | $177,250.30 |
| 2 | 58815 | Simmons Erosion Control, Inc. | $234,195.00 |
| 3 | 05635 | Dreher Contracting, LLC | $434,925.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Highway Safety Systems LLC | - 2 - Simmons Erosion Control, Inc. | - 3 - Dreher Contracting, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | NS-MNT-00001 | Wire Rope for High-Tension Median Cable Barrier | 20 | LNFT | 100.00 | 2,000.00 | 3.50 | 70.00 | 10.00 | 200.00 | | 0002 | NS-MNT-00002 | Threaded Terminals for High-Tension Median Cable Barrier | 5 | EACH | 0.01 | 0.05 | 100.00 | 500.00 | 460.00 | 2,300.00 | | 0003 | NS-MNT-00003 | Turnbuckles for High-Tension Median Cable Barrier | 5 | EACH | 500.00 | 2,500.00 | 200.00 | 1,000.00 | 440.00 | 2,200.00 | | 0004 | NS-MNT-00004 | End Terminal Fittings for High-Tension Median Cable Barrier | 20 | EACH | 250.00 | 5,000.00 | 25.00 | 500.00 | 935.00 | 18,700.00 | | 0005 | NS-MNT-00005 | Line Posts and Post Accessories for High-Tension Median Cable Barrier | 525 | EACH | 250.00 | 131,250.00 | 265.00 | 139,125.00 | 280.00 | 147,000.00 | | 0006 | NS-MNT-00006 | Gating End Terminals for High-Tension Median Cable Barrier | 15 | EACH | 0.01 | 0.15 | 100.00 | 1,500.00 | 500.00 | 7,500.00 | | 0007 | NS-MNT-00007 | Guardrail Attachment End Terminals for High-Tension Median Cable Barrier | 5 | EACH | 0.01 | 0.05 | 100.00 | 500.00 | 100.00 | 500.00 | | 0008 | NS-MNT-00008 | Line Post and End Post Anchor Foundation Concrete and Reinforcing Steel for High-Tension Median Cable Barrier | 5 | CUYD | 0.01 | 0.05 | 500.00 | 2,500.00 | 880.00 | 4,400.00 | | 0009 | NS-MNT-00009 | Tensioning and Re-Tensioning of Cable for High-Tension Median Cable Barrier | 55 | EACH | 400.00 | 22,000.00 | 250.00 | 13,750.00 | 1,250.00 | 68,750.00 | | 0010 | NS-MNT-00010 | Concrete Mow Pad for High-Tension Median Cable Barrier | 5 | LNFT | 100.00 | 500.00 | 250.00 | 1,250.00 | 275.00 | 1,375.00 | | 0011 | NS-MNT-00013 | MOBILIZATION AND MAINTENANCE OF TRAFFIC FOR CABLE BARRIER (EACH SITE) | 70 | EACH | 200.00 | 14,000.00 | 1,050.00 | 73,500.00 | 2,600.00 | 182,000.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 177,250.30 | | 234,195.00 | | 434,925.00 |
|