Proposal:H.011655.6-R1
Parish:Iberia
Routes:LA 675
Description:LA 675: 0.53 MI SE US 90 - LA 674
Type Construction:MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, PAVEMENT WIDENING, THIN ASPHALT CONCRETE OVERLAY (COARSE MIX), AND RELATED WORK.
Estimated Construction Cost:$529,224.40
Rank | License | Bidder | Construction Bid |
1 | 34356 | Prairie Contractors LLC | $736,768.12 |
2 | 51821 | Elliott Construction, LLC | $796,845.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Prairie Contractors LLC | - 2 - Elliott Construction, LLC | Unit Price | Total Amount | Unit Price | Total Amount | 0001 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 130.1 | LNFT | 10.00 | 1,301.00 | 50.00 | 6,505.00 | 0002 | 202-02-14500 | Removal of Guard Rail | 506 | LNFT | 15.00 | 7,590.00 | 15.00 | 7,590.00 | 0003 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 17,000.00 | 17,000.00 | 15,000.00 | 15,000.00 | 0004 | 501-02-00100 | Thin Asphalt Concrete (Coarse Mix) | 2,439 | TON | 102.00 | 248,778.00 | 150.00 | 365,850.00 | 0005 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 53 | TON | 310.00 | 16,430.00 | 255.00 | 13,515.00 | 0006 | 509-01-00100 | Milling Asphalt Pavement | 688 | SQYD | 42.00 | 28,896.00 | 25.00 | 17,200.00 | 0007 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -10 | CUYD | 100.00 | -1,000.00 | 0.01 | -0.10 | 0008 | 510-01-00260 | Pavement Patching (16 inch Minimum Thickness) | 192 | SQYD | 208.00 | 39,936.00 | 225.00 | 43,200.00 | 0009 | 510-02-00100 | Pavement Widening (15" THICK) | 45 | SQYD | 300.00 | 13,500.00 | 250.00 | 11,250.00 | 0010 | 702-04-00200 | Adjusting Catch Basins Convert CB Top to CB-09 Top | 1 | EACH | 4,000.00 | 4,000.00 | 4,500.00 | 4,500.00 | 0011 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 125 | LNFT | 65.00 | 8,125.00 | 40.00 | 5,000.00 | 0012 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 262.7 | LNFT | 30.00 | 7,881.00 | 38.00 | 9,982.60 | 0013 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 90.00 | 9,000.00 | 105.00 | 10,500.00 | 0014 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 3 | EACH | 4,250.00 | 12,750.00 | 3,600.00 | 10,800.00 | 0015 | 704-10-00310 | Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) | 1 | EACH | 3,500.00 | 3,500.00 | 3,200.00 | 3,200.00 | 0016 | 707-03-00100 | Combination Concrete Curb and Gutter | 144.6 | LNFT | 35.00 | 5,061.00 | 78.00 | 11,278.80 | 0017 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 72,000.00 | 72,000.00 | 50,000.00 | 50,000.00 | 0018 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 0.232 | MILE | 5,500.00 | 1,276.00 | 4,500.00 | 1,044.00 | 0019 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 3.522 | MILE | 1.00 | 3.52 | 400.00 | 1,408.80 | 0020 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 8.773 | MILE | 1,300.00 | 11,404.90 | 800.00 | 7,018.40 | 0021 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 31 | EACH | 1.00 | 31.00 | 35.00 | 1,085.00 | 0022 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 5 | EACH | 1.00 | 5.00 | 45.00 | 225.00 | 0023 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 3.7 | MILE | 1,200.00 | 4,440.00 | 1,000.00 | 3,700.00 | 0024 | 727-01-00100 | Mobilization | 1 | LUMP | 72,250.00 | 72,250.00 | 100,000.00 | 100,000.00 | 0025 | 729-16-00200 | Object Marker Assembly (Type 2) | 4 | EACH | 75.00 | 300.00 | 50.00 | 200.00 | 0026 | 729-16-00300 | Object Marker Assembly (Type 3) | 6 | EACH | 110.00 | 660.00 | 85.00 | 510.00 | 0027 | 731-02-00100 | Reflectorized Raised Pavement Markers | 543 | EACH | 11.00 | 5,973.00 | 7.00 | 3,801.00 | 0028 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 179 | LNFT | 5.00 | 895.00 | 3.00 | 537.00 | 0029 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 58 | LNFT | 16.00 | 928.00 | 8.00 | 464.00 | 0030 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 8.773 | MILE | 4,500.00 | 39,478.50 | 3,500.00 | 30,705.50 | 0031 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 3.522 | MILE | 1,600.00 | 5,635.20 | 1,500.00 | 5,283.00 | 0032 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 31 | EACH | 550.00 | 17,050.00 | 300.00 | 9,300.00 | 0033 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 5 | EACH | 550.00 | 2,750.00 | 300.00 | 1,500.00 | 0034 | 732-05-00100 | Removal of Existing Markings | 2.202 | MILE | 13,000.00 | 28,626.00 | 10,000.00 | 22,020.00 | 0035 | 735-01-00100 | Mailboxes | 26 | EACH | 15.00 | 390.00 | 25.00 | 650.00 | 0036 | 735-02-00100 | Mailbox Supports (Single) | 26 | EACH | 180.00 | 4,680.00 | 150.00 | 3,900.00 | 0037 | 740-01-00100 | Construction Layout | 1 | LUMP | 39,000.00 | 39,000.00 | 15,000.00 | 15,000.00 | 0038 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 1,561 | INLF | 4.00 | 6,244.00 | 2.00 | 3,122.00 | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 736,768.12 | | 796,845.00 |
|