Bid Tabulations for the Letting of 6/12/2019 LA DOTD Headquarters
Proposal:H.011278.6
Parish:Livingston
Routes:I-12
Description:I-12: MEDIAN CABLE BARRIER
Type Construction:CABLE BARRIER SYSTEM AND RELATED WORK.
Estimated Construction Cost:$4,385,395.50
Rank | License | Bidder | Construction Bid |
1 | 54896 | Magee Excavation & Development LLC | $4,297,473.40 |
2 | 57931 | KCR CONTRACTORS, LLC | $4,317,987.13 |
3 | 39462 | JB JAMES CONSTRUCTION LLC | $4,438,976.00 |
4 | 48896 | Command Construction Industries LLC | $4,542,546.79 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Magee Excavation & Development LLC | - 2 - KCR CONTRACTORS, LLC | - 3 - JB JAMES CONSTRUCTION LLC | - 4 - Command Construction Industries LLC |
Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount |
0001 | 203-07-00100 | Borrow (Vehicular Measurement) | 9,777 | CUYD | 15.00 | 146,655.00 | 21.61 | 211,280.97 | 5.00 | 48,885.00 | 0.01 | 97.77 |
0002 | 204-02-00100 | Temporary Hay Bales | 562 | EACH | 12.00 | 6,744.00 | 22.41 | 12,594.42 | 25.00 | 14,050.00 | 10.00 | 5,620.00 |
0003 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 169,000.00 | 169,000.00 | 40,250.00 | 40,250.00 | 275,000.00 | 275,000.00 | 150,000.00 | 150,000.00 |
0004 | 713-11-00100 | Portable Changeable Message Signs | 6 | EACH | 11,000.00 | 66,000.00 | 5,750.00 | 34,500.00 | 7,500.00 | 45,000.00 | 2,500.00 | 15,000.00 |
0005 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 66,352 | SQYD | 0.50 | 33,176.00 | 1.20 | 79,622.40 | 0.75 | 49,764.00 | 0.01 | 663.52 |
0006 | 721-01-00100 | Mowing | 4 | CYCL | 14,000.00 | 56,000.00 | 5,750.00 | 23,000.00 | 24,000.00 | 96,000.00 | 10,000.00 | 40,000.00 |
0007 | 727-01-00100 | Mobilization | 1 | LUMP | 175,000.00 | 175,000.00 | 108,003.41 | 108,003.41 | 440,000.00 | 440,000.00 | 450,000.00 | 450,000.00 |
0008 | 739-01-00100 | Hydro-Seeding | 27.4 | ACRE | 2,000.00 | 54,800.00 | 1,485.68 | 40,707.63 | 1,000.00 | 27,400.00 | 1,500.00 | 41,100.00 |
0009 | 740-01-00100 | Construction Layout | 1 | LUMP | 23,000.00 | 23,000.00 | 5,000.00 | 5,000.00 | 70,000.00 | 70,000.00 | 150,000.00 | 150,000.00 |
0010 | NS-704-00001 | High Tension Cable Barrier | 58,093 | LNFT | 7.30 | 424,078.90 | 7.69 | 446,735.17 | 9.00 | 522,837.00 | 8.00 | 464,744.00 |
0011 | NS-704-00002 | Cable Barrier Gated End Terminal | 56 | EACH | 3,400.00 | 190,400.00 | 1,790.36 | 100,260.16 | 3,500.00 | 196,000.00 | 2,500.00 | 140,000.00 |
0012 | NS-704-00003 | Concrete Strip | 66,351 | SQYD | 44.50 | 2,952,619.50 | 48.47 | 3,216,032.97 | 40.00 | 2,654,040.00 | 46.50 | 3,085,321.50 |
| | | | | | | | | | | | |
| | CONTRACTOR TOTAL | | | | 4,297,473.40 | | 4,317,987.13 | | 4,438,976.00 | | 4,542,546.79 |