Bid Tabulations for the Letting of 11/14/2018 LA DOTD Headquarters
Proposal:H.013432.6
Parish:St. Charles
Routes:I-310
Description:I-310: CONCRETE PATCH AT SB MM 9
Type Construction:MILLING ASPHALT PAVEMENT, HIGH EARLY STRENGTH CONCRETE
PAVEMENT, ASPHALT CONCRETE SHOULDER, AND RELATED WORK.
Estimated Construction Cost:$239,221.50
Rank | License | Bidder | Construction Bid |
1 | 21982 | Forby Contracting, Inc. | $129,452.40 |
2 | 24901 | Hard Rock Construction LLC | $157,911.65 |
3 | 38610 | Three C's Properties Inc., The | $178,408.00 |
4 | 02179 | Boh Bros. Construction Co., LLC. | $186,615.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Forby Contracting, Inc. | - 2 - Hard Rock Construction LLC | - 3 - Three C's Properties Inc., The | - 4 - Boh Bros. Construction Co., LLC. |
Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount |
0001 | 502-01-00100 | Asphalt Concrete | 5.2 | TON | 1,550.00 | 8,060.00 | 900.00 | 4,680.00 | 300.00 | 1,560.00 | 1,500.00 | 7,800.00 |
0002 | 509-01-00100 | Milling Asphalt Pavement | 62.2 | SQYD | 88.00 | 5,473.60 | 148.00 | 9,205.60 | 25.00 | 1,555.00 | 100.00 | 6,220.00 |
0003 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -3 | CUYD | 0.10 | -0.30 | 1.00 | -3.00 | 1.00 | -3.00 | 1.00 | -3.00 |
0004 | 602-16-00100 | High Early Strength (HES) Concrete Pavement Full and Partial Depth Patching (12" Thick) | 240 | SQYD | 275.00 | 66,000.00 | 230.00 | 55,200.00 | 350.00 | 84,000.00 | 372.00 | 89,280.00 |
0005 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 10,000.00 | 10,000.00 | 18,000.00 | 18,000.00 | 18,000.00 | 18,000.00 | 14,000.00 | 14,000.00 |
0006 | 713-02-00100 | Temporary Pavement Markings (4" Width) | 4,210 | LNFT | 0.20 | 842.00 | 1.00 | 4,210.00 | 0.50 | 2,105.00 | 0.20 | 842.00 |
0007 | 713-07-00100 | Temporary Precast Concrete Barrier (Contractor Furnished) | 28 | EACH | 150.00 | 4,200.00 | 880.00 | 24,640.00 | 350.00 | 9,800.00 | 700.00 | 19,600.00 |
0008 | 713-10-00100 | Temporary Precast Concrete Barrier Movement | 28 | EACH | 50.00 | 1,400.00 | 450.00 | 12,600.00 | 700.00 | 19,600.00 | 200.00 | 5,600.00 |
0009 | 713-11-00100 | Portable Changeable Message Signs | 1 | EACH | 1,000.00 | 1,000.00 | 1,500.00 | 1,500.00 | 1,600.00 | 1,600.00 | 2,000.00 | 2,000.00 |
0010 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 0.174 | MILE | 400.00 | 69.60 | 425.00 | 73.95 | 30,000.00 | 5,220.00 | 11,000.00 | 1,914.00 |
0011 | 727-01-00100 | Mobilization | 1 | LUMP | 25,000.00 | 25,000.00 | 15,000.00 | 15,000.00 | 23,500.00 | 23,500.00 | 30,000.00 | 30,000.00 |
0012 | 731-02-00100 | Reflectorized Raised Pavement Markers | 2 | EACH | 25.00 | 50.00 | 22.00 | 44.00 | 25.00 | 50.00 | 29.00 | 58.00 |
0013 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 1,750 | LNFT | 0.75 | 1,312.50 | 2.00 | 3,500.00 | 1.00 | 1,750.00 | 1.00 | 1,750.00 |
0014 | 732-03-02101 | Plastic Pavement Striping (Broken Line) (4" W) (Preformed Tape Retroreflectivity I or Thermo 90 mil)(Black Contrast) | 0.015 | MILE | 20,000.00 | 300.00 | 41,000.00 | 615.00 | 42,000.00 | 630.00 | 24,000.00 | 360.00 |
0015 | 732-05-00100 | Removal of Existing Markings | 0.949 | MILE | 5,000.00 | 4,745.00 | 8,900.00 | 8,446.10 | 9,000.00 | 8,541.00 | 6,000.00 | 5,694.00 |
0016 | 740-01-00100 | Construction Layout | 1 | LUMP | 1,000.00 | 1,000.00 | 200.00 | 200.00 | 500.00 | 500.00 | 1,500.00 | 1,500.00 |
| | | | | | | | | | | | |
| | CONTRACTOR TOTAL | | | | 129,452.40 | | 157,911.65 | | 178,408.00 | | 186,615.00 |