Proposal:H.007534.6
Parish:Pointe Coupee
Routes:LA 411, LA 77, LA 78, LA 81, US 190
Description:LIVONIA SIGNAGE ENHANCEMENT PROJECT
Type Construction:SIGNAGE (WITH OR WITHOUT INTERNAL LIGHTING), LANDSCAPING, IRRIGATION INSTALLATION AND RELATED WORK.
Estimated Construction Cost:$130,111.51
| Rank | License | Bidder | Construction Bid |
| 1 | 36764 | Lamay Group, LLC | $156,099.25 |
| 2 | 32044 | Quality Design & Construction, LLC | $189,337.80 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Lamay Group, LLC | - 2 - Quality Design & Construction, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 204-06-00100 | Temporary Silt Fencing | 182 | LNFT | 3.00 | 546.00 | 19.40 | 3,530.80 | | 0002 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 5,125.00 | 5,125.00 | 10,130.00 | 10,130.00 | | 0003 | 717-01-00100 | Seeding | 8 | LB | 50.00 | 400.00 | 85.00 | 680.00 | | 0004 | 719-01-06000 | Plants (Plant) (Container) (4 inch) Liriope | 1,120 | EACH | 4.50 | 5,040.00 | 2.80 | 3,136.00 | | 0005 | 719-01-06020 | Plants (Plant) (Container) (1 gallon) Agapanthus | 118 | EACH | 28.00 | 3,304.00 | 13.80 | 1,628.40 | | 0006 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) Indian Hawthorn | 40 | EACH | 35.00 | 1,400.00 | 25.00 | 1,000.00 | | 0007 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) Maiden Grass | 18 | EACH | 35.00 | 630.00 | 25.00 | 450.00 | | 0008 | 719-02-00100 | Top Dressing Mulch (3 inch Depth) Hardwood | 94 | SQYD | 10.00 | 940.00 | 10.40 | 977.60 | | 0009 | 719-03-00300 | Bed Preparation (10 inch Depth) | 94 | SQYD | 20.00 | 1,880.00 | 32.50 | 3,055.00 | | 0010 | 727-01-00100 | Mobilization | 1 | LUMP | 15,000.00 | 15,000.00 | 16,100.00 | 16,100.00 | | 0011 | 730-07-10000 | Luminaire (LED)(Flag Pole Up Lighting) | 3 | EACH | 1,700.00 | 5,100.00 | 1,080.00 | 3,240.00 | | 0012 | 740-01-00100 | Construction Layout | 1 | LUMP | 4,000.00 | 4,000.00 | 6,760.00 | 6,760.00 | | 0013 | NS-ENH-06020 | Flag Pole Complete and Installed | 1 | EACH | 7,500.00 | 7,500.00 | 7,500.00 | 7,500.00 | | 0014 | NS-ENH-09000 | Irrigation System Complete and Installed | 1 | LUMP | 6,000.00 | 6,000.00 | 7,700.00 | 7,700.00 | | 0015 | NS-ENH-19100 | Sign (Gateway) Directional, Complete and Installed | 1 | EACH | 22,221.00 | 22,221.00 | 33,600.00 | 33,600.00 | | 0016 | NS-ENH-19100 | Sign (Gateway) Main, Complete and Installed | 2 | EACH | 29,000.00 | 58,000.00 | 39,100.00 | 78,200.00 | | 0017 | NS-ENH-19100 | Sign (Gateway) Town Limits, Complete and Installed | 5 | EACH | 3,802.65 | 19,013.25 | 2,330.00 | 11,650.00 | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 156,099.25 | | 189,337.80 |
|