Proposal:H.012579.6
Parish:Franklin
Routes:LA 17, LA 4, LA 577, LA 865
Description:DISTRICT 58 AST: FRANKLIN PARISH
Type Construction:PAVEMENT PATCHING, MILLING ASPHALT PAVEMENT, ASPHALT SURFACE TREATMENT AND RELATED WORK.
Estimated Construction Cost:$993,981.68
| Rank | License | Bidder | Construction Bid |
| 1 | 46716 | BRUDD CONSTRUCTION CO., LLC | $896,515.18 |
| 2 | 05635 | Dreher Contracting, LLC | $958,329.86 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - BRUDD CONSTRUCTION CO., LLC | - 2 - Dreher Contracting, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 507-01-00100 | Asphalt Material (CRS-2P Emulsion) | 115,393 | GAL | 2.15 | 248,094.95 | 2.00 | 230,786.00 | | 0002 | 507-02-00200 | Aggregate (S2) | 66,389 | SQYD | 0.91 | 60,413.99 | 0.90 | 59,750.10 | | 0003 | 507-02-00300 | Aggregate (S3) | 293,004 | SQYD | 0.84 | 246,123.36 | 0.89 | 260,773.56 | | 0004 | 509-01-00100 | Milling Asphalt Pavement | 66,389 | SQYD | 1.00 | 66,389.00 | 1.00 | 66,389.00 | | 0005 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -692 | CUYD | 1.00 | -692.00 | 1.00 | -692.00 | | 0006 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 195 | SQYD | 125.00 | 24,375.00 | 125.00 | 24,375.00 | | 0007 | 510-01-00260 | Pavement Patching (16 inch Minimum Thickness) | 80 | SQYD | 172.00 | 13,760.00 | 180.00 | 14,400.00 | | 0008 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 23,350.00 | 23,350.00 | 23,000.00 | 23,000.00 | | 0009 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 48 | LNFT | 1.00 | 48.00 | 2.00 | 96.00 | | 0010 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 101 | LNFT | 8.00 | 808.00 | 2.00 | 202.00 | | 0011 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 4.527 | MILE | 1.00 | 4.53 | 600.00 | 2,716.20 | | 0012 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 13.954 | MILE | 550.00 | 7,674.70 | 650.00 | 9,070.10 | | 0013 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 63.148 | MILE | 800.00 | 50,518.40 | 850.00 | 53,675.80 | | 0014 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | 5,611 | EACH | 1.65 | 9,258.15 | 2.00 | 11,222.00 | | 0015 | 727-01-00100 | Mobilization | 1 | LUMP | 54,000.00 | 54,000.00 | 90,000.00 | 90,000.00 | | 0016 | 731-02-00100 | Reflectorized Raised Pavement Markers | 3,768 | EACH | 5.00 | 18,840.00 | 6.00 | 22,608.00 | | 0017 | 737-01-00100 | Painted Traffic Striping (Solid Line) (4" Width) | 63.148 | MILE | 800.00 | 50,518.40 | 1,000.00 | 63,148.00 | | 0018 | 737-01-00300 | Painted Traffic Striping (Solid Line) (8" Width) | 48 | MILE | 1.00 | 48.00 | 15.00 | 720.00 | | 0019 | 737-02-00100 | Painted Traffic Striping (Broken Line) (4" Width) | 13.954 | MILE | 550.00 | 7,674.70 | 650.00 | 9,070.10 | | 0020 | 737-03-00500 | Painted Traffic Striping (Solid Line) (24" Width) | 101 | LNFT | 8.00 | 808.00 | 20.00 | 2,020.00 | | 0021 | 740-01-00100 | Construction Layout | 1 | LUMP | 14,500.00 | 14,500.00 | 15,000.00 | 15,000.00 | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 896,515.18 | | 958,329.86 |
|