Proposal:H.012109.6
Parish:Catahoula
Routes:US 425
Description:US 425: CLAYTON - SICILY ISLAND
Type Construction:MILLING ASPHALT PAVEMENT, PAVEMENT PATCHING, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$2,176,883.07
| Rank | License | Bidder | Construction Bid |
| 1 | 12312 | GILCHRIST CONSTRUCTION CO. LLC | $1,901,200.20 |
| 2 | 12487 | Diamond B Construction Co., L.L.C. | $1,914,803.42 |
| 3 | 05789 | D & J CONSTRUCTION CO., LLC | $1,965,097.30 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - GILCHRIST CONSTRUCTION CO. LLC | - 2 - Diamond B Construction Co., L.L.C. | - 3 - D & J CONSTRUCTION CO., LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 502-01-00100 | Asphalt Concrete | 13,865.8 | TON | 82.00 | 1,136,995.60 | 90.00 | 1,247,922.00 | 86.00 | 1,192,458.80 | | 0002 | 509-01-00100 | Milling Asphalt Pavement | 124,260 | SQYD | 1.20 | 149,112.00 | 0.75 | 93,195.00 | 1.15 | 142,899.00 | | 0003 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -5,178 | CUYD | 1.00 | -5,178.00 | 1.00 | -5,178.00 | 1.00 | -5,178.00 | | 0004 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 75 | SQYD | 100.00 | 7,500.00 | 158.00 | 11,850.00 | 125.00 | 9,375.00 | | 0005 | 510-01-00300 | Pavement Patching (18" Minimum Thickness) | 2,000 | SQYD | 110.00 | 220,000.00 | 110.00 | 220,000.00 | 150.00 | 300,000.00 | | 0006 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 68,000.00 | 68,000.00 | 58,500.00 | 58,500.00 | 63,000.00 | 63,000.00 | | 0007 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 1,980 | LNFT | 0.26 | 514.80 | 0.25 | 495.00 | 0.30 | 594.00 | | 0008 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 17.73 | MILE | 200.00 | 3,546.00 | 154.00 | 2,730.42 | 200.00 | 3,546.00 | | 0009 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 11.14 | MILE | 500.00 | 5,570.00 | 500.00 | 5,570.00 | 500.00 | 5,570.00 | | 0010 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 11.14 | MILE | 700.00 | 7,798.00 | 700.00 | 7,798.00 | 700.00 | 7,798.00 | | 0011 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 9 | EACH | 16.00 | 144.00 | 16.00 | 144.00 | 15.00 | 135.00 | | 0012 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 9 | EACH | 16.00 | 144.00 | 16.00 | 144.00 | 15.00 | 135.00 | | 0013 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 11.4 | MILE | 300.00 | 3,420.00 | 550.00 | 6,270.00 | 300.00 | 3,420.00 | | 0014 | 727-01-00100 | Mobilization | 1 | LUMP | 158,000.00 | 158,000.00 | 88,000.00 | 88,000.00 | 50,000.00 | 50,000.00 | | 0015 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,738 | EACH | 7.00 | 12,166.00 | 7.00 | 12,166.00 | 6.50 | 11,297.00 | | 0016 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 1,320 | LNFT | 3.25 | 4,290.00 | 3.25 | 4,290.00 | 3.00 | 3,960.00 | | 0017 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 24.32 | MILE | 4,000.00 | 97,280.00 | 3,850.00 | 93,632.00 | 3,850.00 | 93,632.00 | | 0018 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 12.16 | MILE | 1,000.00 | 12,160.00 | 1,000.00 | 12,160.00 | 1,000.00 | 12,160.00 | | 0019 | 732-03-02030 | Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.061 | MILE | 11,000.00 | 671.00 | 10,500.00 | 640.50 | 11,000.00 | 671.00 | | 0020 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 5 | EACH | 420.00 | 2,100.00 | 425.00 | 2,125.00 | 450.00 | 2,250.00 | | 0021 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 1 | EACH | 420.00 | 420.00 | 425.00 | 425.00 | 450.00 | 450.00 | | 0022 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 6 | EACH | 520.00 | 3,120.00 | 550.00 | 3,300.00 | 550.00 | 3,300.00 | | 0023 | 732-05-00100 | Removal of Existing Markings | 6.59 | MILE | 520.00 | 3,426.80 | 550.00 | 3,624.50 | 550.00 | 3,624.50 | | 0024 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 | 45,000.00 | 45,000.00 | 60,000.00 | 60,000.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,901,200.20 | | 1,914,803.42 | | 1,965,097.30 |
|