Bid Tabulations for the Letting of 2/8/2017 LA DOTD Headquarters

Proposal:H.012216.6
Parish:Orleans
Description:US 90: RIGOLETS PIER AND FENDER REMOVAL
Type Construction:REMOVAL OF UNDERWATER DEBRIS (OLD PIER AND FENDER), AND RELATED WORK.
Estimated Construction Cost:$855,000.00
Rank License BidderConstruction Bid
153308COASTAL MARINE CONTRACTORS, LLC$674,500.00
225747Kostmayer Construction, LLC$980,000.00
308768Cycle Marine Group, Inc.$2,279,000.00
439613BAKER PILE DRIVING AND SITE WORK LLC$9,948,260.00


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
COASTAL MARINE CONTRACTORS, LLC
- 2 -
Kostmayer Construction, LLC
- 3 -
Cycle Marine Group, Inc.
- 4 -
BAKER PILE DRIVING AND SITE WORK LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001202-02-04300Removal of Bridge Substructure (Concrete Caisson Pier) 1     EACH310,000.00310,000.00280,000.00280,000.001,955,000.001,955,000.008,420,143.008,420,143.00
0002202-02-12300Removal of Fender System 1     EACH247,500.00247,500.00300,000.00300,000.00208,000.00208,000.001,026,845.001,026,845.00
0003727-01-00100Mobilization 1     LUMP67,000.0067,000.00300,000.00300,000.0071,000.0071,000.00408,632.00408,632.00
0004740-01-00100Construction Layout 1     LUMP50,000.0050,000.00100,000.00100,000.0045,000.0045,000.0092,640.0092,640.00
             
  CONTRACTOR TOTAL   674,500.00 980,000.00 2,279,000.00 9,948,260.00