Proposal:H.011716.6
Parish:Plaquemines
Description:Belle Chasse/Scarsdale Mooring Dolphins
Type Construction:TOWING, INSPECTION, REMOVAL, INSTALLATION, AND RELATED WORK
Estimated Construction Cost:$636,250.00
Rank | License | Bidder | Construction Bid |
1 | 00481 | COASTAL BRIDGE CO., L.L.C. | $689,650.00 |
2 | 00271 | Massman Construction Co. | $702,560.00 |
3 | 53308 | COASTAL MARINE CONTRACTORS, LLC | $865,790.00 |
4 | 08768 | Cycle Marine Group, Inc. | $899,870.00 |
5 | 46933 | Cajun Maritime, LLC | $1,055,352.00 |
6 | 02179 | Boh Bros. Construction Co., LLC. | $1,099,850.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - COASTAL BRIDGE CO., L.L.C. | - 2 - Massman Construction Co. | - 3 - COASTAL MARINE CONTRACTORS, LLC | - 4 - Cycle Marine Group, Inc. | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 78,000.00 | 78,000.00 | 10,000.00 | 10,000.00 | 97,450.00 | 97,450.00 | 17,000.00 | 17,000.00 | 0002 | 202-02-00010 | Removal of Removal of Existing Timber Protective Dolphins | 2 | EACH | 15,000.00 | 30,000.00 | 8,000.00 | 16,000.00 | 20,000.00 | 40,000.00 | 15,000.00 | 30,000.00 | 0003 | 711-02-00400 | Riprap (55 lb) | 250 | CUYD | 165.00 | 41,250.00 | 100.00 | 25,000.00 | 200.00 | 50,000.00 | 225.00 | 56,250.00 | 0004 | 727-01-00100 | Mobilization To Include Towing | 1 | LUMP | 65,000.00 | 65,000.00 | 70,000.00 | 70,000.00 | 80,000.00 | 80,000.00 | 200,000.00 | 200,000.00 | 0005 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 | 12,000.00 | 12,000.00 | 30,000.00 | 30,000.00 | 7,500.00 | 7,500.00 | 0006 | 804-02-00100 | Treated Timber Piles (Noncoastal Treatment) | 840 | LNFT | 75.00 | 63,000.00 | 87.00 | 73,080.00 | 70.00 | 58,800.00 | 80.00 | 67,200.00 | 0007 | 804-03-02120 | Steel Piles (24" Pipe) | 796 | LNFT | 150.00 | 119,400.00 | 280.00 | 222,880.00 | 215.00 | 171,140.00 | 145.00 | 115,420.00 | 0008 | 804-03-02160 | Steel Piles (36" Pipe) | 360 | LNFT | 300.00 | 108,000.00 | 260.00 | 93,600.00 | 310.00 | 111,600.00 | 300.00 | 108,000.00 | 0009 | 807-08-00100 | Structural Metalwork | 17,400 | LUMP | 75,000.00 | 75,000.00 | 80,000.00 | 80,000.00 | 126,800.00 | 126,800.00 | 114,500.00 | 114,500.00 | 0010 | NS-805-00028 | Rubber Fender Elements | 2 | EACH | 50,000.00 | 100,000.00 | 50,000.00 | 100,000.00 | 50,000.00 | 100,000.00 | 92,000.00 | 184,000.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 689,650.00 | | 702,560.00 | | 865,790.00 | | 899,870.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - Cajun Maritime, LLC | - 6 - Boh Bros. Construction Co., LLC. | Unit Price | Total Amount | Unit Price | Total Amount | 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 54,064.00 | 54,064.00 | 14,000.00 | 14,000.00 | 0002 | 202-02-00010 | Removal of Removal of Existing Timber Protective Dolphins | 2 | EACH | 17,885.00 | 35,770.00 | 5,000.00 | 10,000.00 | 0003 | 711-02-00400 | Riprap (55 lb) | 250 | CUYD | 418.00 | 104,500.00 | 125.00 | 31,250.00 | 0004 | 727-01-00100 | Mobilization To Include Towing | 1 | LUMP | 189,667.00 | 189,667.00 | 150,250.00 | 150,250.00 | 0005 | 740-01-00100 | Construction Layout | 1 | LUMP | 44,500.00 | 44,500.00 | 10,000.00 | 10,000.00 | 0006 | 804-02-00100 | Treated Timber Piles (Noncoastal Treatment) | 840 | LNFT | 169.00 | 141,960.00 | 120.00 | 100,800.00 | 0007 | 804-03-02120 | Steel Piles (24" Pipe) | 796 | LNFT | 151.00 | 120,196.00 | 450.00 | 358,200.00 | 0008 | 804-03-02160 | Steel Piles (36" Pipe) | 360 | LNFT | 320.00 | 115,200.00 | 550.00 | 198,000.00 | 0009 | 807-08-00100 | Structural Metalwork | 17,400 | LUMP | 116,295.00 | 116,295.00 | 159,350.00 | 159,350.00 | 0010 | NS-805-00028 | Rubber Fender Elements | 2 | EACH | 66,600.00 | 133,200.00 | 34,000.00 | 68,000.00 | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,055,352.00 | | 1,099,850.00 |
|