Bid Tabulations for the Letting of 8/13/2014 LA DOTD Headquarters
Proposal:H.009325.6-R1
Parish:St. Tammany
Description:South Channel Fender Repair and Structural Improvements
Type Construction:BRIDGE REPAIRS AND RELATED WORK.
Estimated Construction Cost:$1,563,259.72
Rank | License | Bidder | Construction Bid |
1 | 26435 | C.E.C., Inc. | $2,031,865.00 |
2 | 37302 | Double Aught Construction LLC | $2,419,952.60 |
3 | 08768 | PROFESSIONAL CONST. SERVICES, INC. | $2,471,757.88 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - C.E.C., Inc. | - 2 - Double Aught Construction LLC | - 3 - PROFESSIONAL CONST. SERVICES, INC. |
Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount |
0001 | 202-02-00010 | Removal of Handrail (Pipe) | 1 | EACH | 4,200.00 | 4,200.00 | 31,200.00 | 31,200.00 | 6,500.00 | 6,500.00 |
0002 | 202-02-00010 | Removal of Handrail (Timber) | 2 | EACH | 6,000.00 | 12,000.00 | 21,450.00 | 42,900.00 | 9,600.00 | 19,200.00 |
0003 | 202-02-00010 | Removal of Bridge Components (Existing Steel Spiral Staircase) | 2 | EACH | 21,000.00 | 42,000.00 | 21,640.00 | 43,280.00 | 16,350.00 | 32,700.00 |
0004 | 202-02-00010 | Removal of Walers (Timber) | 1 | EACH | 24,000.00 | 24,000.00 | 41,100.00 | 41,100.00 | 26,000.00 | 26,000.00 |
0005 | 202-02-38240 | Removal of Signs and Supports | 4 | EACH | 1,000.00 | 4,000.00 | 5,200.00 | 20,800.00 | 3,500.00 | 14,000.00 |
0006 | 202-03-00010 | Relocation of Cameras | 1 | EACH | 3,000.00 | 3,000.00 | 15,000.00 | 15,000.00 | 20,000.00 | 20,000.00 |
0007 | 712-02-00300 | Sacked Concrete Revetment (Dry batched) | 329.16 | SQYD | 250.00 | 82,290.00 | 820.00 | 269,911.20 | 300.00 | 98,748.00 |
0008 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 1,000.00 | 1,000.00 | 20,000.00 | 20,000.00 | 2,500.00 | 2,500.00 |
0009 | 727-01-00100 | Mobilization | 1 | LUMP | 180,000.00 | 180,000.00 | 150,000.00 | 150,000.00 | 350,000.00 | 350,000.00 |
0010 | 740-01-00100 | Construction Layout | 1 | LUMP | 5,000.00 | 5,000.00 | 20,000.00 | 20,000.00 | 15,000.00 | 15,000.00 |
0011 | 807-08-00100 | Structural Metalwork | 33,961 | LUMP | 490,000.00 | 490,000.00 | 508,990.00 | 508,990.00 | 548,000.00 | 548,000.00 |
0012 | 812-01-00200 | Treated Timber (Coastal Treatment) Handrail for Fender System, Furnish & Install | 3.84 | MFBM | 25,000.00 | 96,000.00 | 14,400.00 | 55,296.00 | 36,850.00 | 141,504.00 |
0013 | 812-01-00200 | Treated Timber (Coastal Treatment) Wire Rope for Fender Pile Cluster, Remove & Replace | 7.565 | MFBM | 13,000.00 | 98,345.00 | 26,060.00 | 197,143.90 | 23,325.00 | 176,453.63 |
0014 | 812-01-00200 | Treated Timber (Coastal Treatment) 3"x8" Decking Boards | 0.72 | MFBM | 55,000.00 | 39,600.00 | 56,660.00 | 40,795.20 | 89,200.00 | 64,224.00 |
0015 | 812-01-00200 | Treated Timber (Coastal Treatment) Pier Protection, Refurbish (Dolphin Rub Rails) | 1.15 | MFBM | 48,000.00 | 55,200.00 | 66,240.00 | 76,176.00 | 76,225.00 | 87,658.75 |
0016 | 812-01-00200 | Treated Timber (Coastal Treatment) Batter Blocking for Fender Piles, Remove & Replace | 2.33 | MFBM | 46,000.00 | 107,180.00 | 100,000.00 | 233,000.00 | 35,400.00 | 82,482.00 |
0017 | 812-01-00200 | Treated Timber (Coastal Treatment) Pier Protection, Refurbish (Fender System Walers and Headers), Furnish and Install | 2.93 | MFBM | 38,000.00 | 111,340.00 | 28,310.00 | 82,948.30 | 25,750.00 | 75,447.50 |
0018 | NS-729-00001 | Navigational Clearance Gauge (Mounted) | 2 | EACH | 15,000.00 | 30,000.00 | 10,000.00 | 20,000.00 | 9,000.00 | 18,000.00 |
0019 | NS-730-00002 | Bridge Navigational Lighting System | 1 | LUMP | 110,000.00 | 110,000.00 | 120,000.00 | 120,000.00 | 200,000.00 | 200,000.00 |
0020 | NS-800-00600 | Aggregate Fill for Dolphin & Sheet Pile Cells Limestone Only | 257 | TON | 800.00 | 205,600.00 | 240.00 | 61,680.00 | 780.00 | 200,460.00 |
0021 | NS-800-00640 | Unreinforced Plastic Composite Marine Timbers (12 x 12) | 789 | LNFT | 270.00 | 213,030.00 | 308.00 | 243,012.00 | 220.00 | 173,580.00 |
0022 | NS-800-00643 | Unreinforced Plastic Composite Marine Timbers (6 x 12) Remove and Replace | 96 | LNFT | 480.00 | 46,080.00 | 820.00 | 78,720.00 | 250.00 | 24,000.00 |
0023 | NS-805-00020 | Bridge Substructure Repair Grout Removal and Replacement | 2 | EACH | 3,500.00 | 7,000.00 | 6,000.00 | 12,000.00 | 7,400.00 | 14,800.00 |
0024 | NS-P52-00104 | Fender Guard Rail System Repair | 1 | LUMP | 65,000.00 | 65,000.00 | 36,000.00 | 36,000.00 | 80,500.00 | 80,500.00 |
| | | | | | | | | | |
| | CONTRACTOR TOTAL | | | | 2,031,865.00 | | 2,419,952.60 | | 2,471,757.88 |