Bid Tabulations for the Letting of 2/6/2015 in District 05 - Monroe

Proposal:H.011749.6
Parish:Madison
Routes:I-20
Description:I-20 SLIDE CHICAGO MILL BOX
Type Construction:Embankment Slope Repair
Estimated Construction Cost:$609,096.93
Rank License BidderConstruction Bid
149239WL Bass Construction Inc.$527,645.95
234567James Construction Group LLC$540,458.66
336936Dirtworks Inc Of Vicksburg$747,532.60
444640R.D. Owens Construction, Inc.$783,984.22
556298Cercontec, LLC$1,299,763.25


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
WL Bass Construction Inc.
- 2 -
James Construction Group LLC
- 3 -
Dirtworks Inc Of Vicksburg
- 4 -
R.D. Owens Construction, Inc.
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001202-02-02020Removal of Asphalt Pavement 239.8   SQYD6.001,438.804.471,071.9110.002,398.0010.002,398.00
0002202-02-14500Removal of Guard Rail 84     LNFT7.00588.0010.17854.288.00672.0050.004,200.00
0003202-02-38500Removal of Surfacing and Stabilized Base 166.7   SQYD6.001,000.206.571,095.2210.001,667.0010.001,667.00
0004203-01-00100General Excavation 7,709     CUYD11.0084,799.005.0038,545.0020.00154,180.0016.00123,344.00
0005203-03-00100Embankment 8,790     CUYD15.00131,850.0017.57154,440.3020.00175,800.0022.00193,380.00
0006203-08-00100Geotextile Fabric 23,658     SQYD1.2529,572.501.6639,272.281.5035,487.004.0094,632.00
0007204-05-00100Temporary Sediment Check Dams (Hay) 4     EACH250.001,000.00114.23456.92150.00600.0020.0080.00
0008204-06-00100Temporary Silt Fencing 500     LNFT1.00500.003.001,500.003.001,500.003.001,500.00
0009302-02-02080Class II Base Course (6" Thick) (Stone) 183.3   SQYD21.003,849.3048.008,798.4022.004,032.6018.003,299.40
0010304-05-00100Lime Treatment (Type E) 325.57  TON45.0014,650.65248.8681,021.35350.00113,949.50250.0081,392.50
0011502-01-00100Superpave Asphaltic Concrete 100.9   TON225.0022,702.50250.0025,225.00250.0025,225.00300.0030,270.00
0012502-01-00200Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 62     TON275.0017,050.00250.0015,500.00250.0015,500.00300.0018,600.00
0013704-03-00100Blocked Out Guard Rail 237.5   LNFT30.007,125.0023.005,462.5023.005,462.5035.008,312.50
0014704-11-00200Guard Rail End Treatment (Tangent) 1     EACH4,000.004,000.003,250.003,250.003,250.003,250.003,000.003,000.00
0015707-03-00100Combination Concrete Curb and Gutter 130     LNFT40.005,200.0033.144,308.2023.002,990.0030.003,900.00
0016711-01-04000Riprap (55 lb, 18" Thick) 18     SQYD100.001,800.0065.801,184.4070.001,260.0075.001,350.00
0017713-01-00100Temporary Signs and Barricades 1     LUMP35,000.0035,000.0030,500.0030,500.0015,000.0015,000.0015,000.0015,000.00
0018713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 0.5   MILE9,500.004,750.005,000.002,500.006,000.003,000.0024,000.0012,000.00
0019713-08-00100Temporary Precast Concrete Barrier (Department Furnished) 68     EACH80.005,440.00240.0616,324.08800.0054,400.00200.0013,600.00
0020713-10-00100Temporary Precast Concrete Barrier Movement 136     EACH25.003,400.0058.337,932.8850.006,800.00100.0013,600.00
0021717-01-00100Seeding 83     LB15.001,245.0010.00830.0013.001,079.0020.001,660.00
0022718-01-00100Fertilizer 1,377     LB2.002,754.000.69950.131.001,377.001.662,285.82
0023720-01-01000Erosion Control System (Slope Protection) (Type A) 3,331     SQYD1.003,331.001.354,496.853.009,993.003.009,993.00
0024720-01-01020Erosion Control System (Slope Protection) (Type B) 560     SQYD1.00560.001.35756.006.003,360.003.001,680.00
0025727-01-00100Mobilization 1     LUMP75,000.0075,000.0053,800.0053,800.0050,000.0050,000.0080,000.0080,000.00
0026729-16-00300Object Marker Assembly (Type 3) 2     EACH100.00200.0085.00170.0075.00150.00100.00200.00
0027740-01-00100Construction Layout 1     LUMP30,000.0030,000.0013,442.0013,442.0015,000.0015,000.0020,000.0020,000.00
0028NS-500-00340Saw Cutting Asphaltic Concrete Pavement 3,720     INLF2.007,440.000.552,046.005.0018,600.002.007,440.00
0029NS-700-00180Impact Attenuator (Construction Zone) 1     EACH6,800.006,800.005,100.005,100.006,000.006,000.0012,000.0012,000.00
0030NS-713-00008Portable Changeable Message Sign 2     EACH3,500.007,000.002,000.004,000.003,000.006,000.002,000.004,000.00
0031NS-805-00023Reinforced Concrete Trapezoidal Channel 32     CUYD550.0017,600.00488.2815,624.96400.0012,800.00600.0019,200.00
             
  CONTRACTOR TOTAL   527,645.95 540,458.66 747,532.60 783,984.22



Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 5 -
Cercontec, LLC
Unit PriceTotal
Amount
0001202-02-02020Removal of Asphalt Pavement 239.8   SQYD30.007,194.00
0002202-02-14500Removal of Guard Rail 84     LNFT125.0010,500.00
0003202-02-38500Removal of Surfacing and Stabilized Base 166.7   SQYD45.007,501.50
0004203-01-00100General Excavation 7,709     CUYD30.00231,270.00
0005203-03-00100Embankment 8,790     CUYD42.00369,180.00
0006203-08-00100Geotextile Fabric 23,658     SQYD2.2553,230.50
0007204-05-00100Temporary Sediment Check Dams (Hay) 4     EACH550.002,200.00
0008204-06-00100Temporary Silt Fencing 500     LNFT3.751,875.00
0009302-02-02080Class II Base Course (6" Thick) (Stone) 183.3   SQYD125.0022,912.50
0010304-05-00100Lime Treatment (Type E) 325.57  TON675.00219,759.75
0011502-01-00100Superpave Asphaltic Concrete 100.9   TON365.0036,828.50
0012502-01-00200Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 62     TON375.0023,250.00
0013704-03-00100Blocked Out Guard Rail 237.5   LNFT60.0014,250.00
0014704-11-00200Guard Rail End Treatment (Tangent) 1     EACH3,000.003,000.00
0015707-03-00100Combination Concrete Curb and Gutter 130     LNFT55.007,150.00
0016711-01-04000Riprap (55 lb, 18" Thick) 18     SQYD150.002,700.00
0017713-01-00100Temporary Signs and Barricades 1     LUMP30,000.0030,000.00
0018713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 0.5   MILE2,500.001,250.00
0019713-08-00100Temporary Precast Concrete Barrier (Department Furnished) 68     EACH800.0054,400.00
0020713-10-00100Temporary Precast Concrete Barrier Movement 136     EACH300.0040,800.00
0021717-01-00100Seeding 83     LB5.00415.00
0022718-01-00100Fertilizer 1,377     LB3.254,475.25
0023720-01-01000Erosion Control System (Slope Protection) (Type A) 3,331     SQYD3.7512,491.25
0024720-01-01020Erosion Control System (Slope Protection) (Type B) 560     SQYD3.752,100.00
0025727-01-00100Mobilization 1     LUMP60,000.0060,000.00
0026729-16-00300Object Marker Assembly (Type 3) 2     EACH350.00700.00
0027740-01-00100Construction Layout 1     LUMP10,000.0010,000.00
0028NS-500-00340Saw Cutting Asphaltic Concrete Pavement 3,720     INLF2.7510,230.00
0029NS-700-00180Impact Attenuator (Construction Zone) 1     EACH3,500.003,500.00
0030NS-713-00008Portable Changeable Message Sign 2     EACH17,500.0035,000.00
0031NS-805-00023Reinforced Concrete Trapezoidal Channel 32     CUYD675.0021,600.00
       
  CONTRACTOR TOTAL   1,299,763.25