Bid Tabulations for the Letting of 5/20/2021 in District 02 - New Orleans

Proposal:H.972417.6
Parish:St. Charles
Description:LULING PE OFFICE FLOOD DAMAGE REPAIRS
Type Construction:BUILDING REPAIRS
Estimated Construction Cost:$82,579.05
135819Frickey Brothers Construction, Inc.$97,035.00
247282Taylor Enterprises of Louisiana, LLC$168,500.00
334263La Contracting Enterprise LLC$205,800.00


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
Frickey Brothers Construction, Inc.
- 2 -
Taylor Enterprises of Louisiana, LLC
- 3 -
La Contracting Enterprise LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001TS-821-02140Building (Renovation and Addition) Base Repairs1     LUMP75,436.0075,436.00128,000.00128,000.00123,000.00123,000.00
0002TS-821-02140Building (Renovation and Addition) Exterior Awning Replacement1     LUMP6,088.006,088.0013,500.0013,500.0042,200.0042,200.00
0003TS-821-02140Building (Renovation and Addition) LED Lighting Fixtures, Ceiling tiles, and the additional cost for drywall & paint in lieu of paneling1     LUMP15,511.0015,511.0027,000.0027,000.0040,600.0040,600.00
           
  CONTRACTOR TOTAL   97,035.00 168,500.00 205,800.00