Line Number | Item | Description | Unit | Quantity |
0001 | 202-02-02020 | Removal of Asphalt Pavement | SQYD | 166.2 |
0002 | 202-02-06100 | Removal of Concrete Walks and Drives | SQYD | 2,901 |
0003 | 202-02-14500 | Removal of Guard Rail | LNFT | 1,134.2 |
0004 | 502-01-00100 | Asphalt Concrete | TON | 16,290.5 |
0005 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | TON | 2,892.1 |
0006 | 502-04-00100 | Asphalt Concrete (SMA) Wearing Course | TON | 7,374.7 |
0007 | 509-01-00100 | Milling Asphalt Pavement | SQYD | 162,423 |
0008 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | CUYD | -3,379 |
0009 | 510-01-00104 | Pavement Patching (10" Minimum Thickness) | SQYD | 594 |
0010 | 510-01-00400 | Pavement Patching (24" Minimum Thickness) | SQYD | 3,609 |
0011 | 602-05-01120 | Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (8" Thick) | SQYD | 12 |
0012 | 602-05-02120 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (8" Thick) | SQYD | 253 |
0013 | 602-05-03120 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (8" Thick) | SQYD | 172 |
0014 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | LNFT | 972.4 |
0015 | 704-05-00300 | Guard Rail Anchor Sections - 31", (Trailing End) | LNFT | 12.6 |
0016 | 704-10-00204 | Guard Rail End Treatment, MASH, (TL-2 Tangent) | EACH | 2 |
0017 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | EACH | 12 |
0018 | 713-01-00100 | Temporary Signs and Barricades | LUMP | 1 |
0019 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | MILE | 26.041 |
0020 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | MILE | 12.083 |
0021 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | MILE | 78.95 |
0022 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | MILE | 8.441 |
0023 | 727-01-00100 | Mobilization | LUMP | 1 |
0024 | 729-16-00300 | Object Marker Assembly (Type 3) | EACH | 16 |
0025 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | EACH | 1,279 |
0026 | 731-02-00100 | Reflectorized Raised Pavement Markers | EACH | 2,394 |
0027 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | LNFT | 4,072 |
0028 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | LNFT | 1,922 |
0029 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | MILE | 26.317 |
0030 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | MILE | 4.027 |
0031 | 732-03-02030 | Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | MILE | 0.455 |
0032 | 732-04-01020 | Plastic Pavement Legends and Symbols (Arrow - Straight) | EACH | 4 |
0033 | 732-04-01040 | Plastic Pavement Legends and Symbols (Arrow - Double) | EACH | 11 |
0034 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | EACH | 31 |
0035 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | EACH | 14 |
0036 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | EACH | 38 |
0037 | 732-05-00100 | Removal of Existing Markings | MILE | 0.351 |
0038 | 736-09-00100 | Loop Detector | LNFT | 1,800 |
0039 | 736-10-00200 | Underground Junction Box (Type E) | EACH | 4 |
0040 | 736-11-00050 | Conduit (1/2" HDPE, Schedule 80) | LNFT | 178 |
0041 | 740-01-00100 | Construction Layout | LUMP | 1 |
0042 | NS-500-00260 | Sawcuts in Asphalt Concrete Lifts | LNFT | 410 |