Line Number | Item | Description | Unit | Quantity |
0001 | 202-02-00030 | Removal of RAILROAD TRACKS AND PANELS | LNFT | 200 |
0002 | 202-02-00040 | Removal of Aggregate Drives | CUYD | 76.5 |
0003 | 202-02-06100 | Removal of Concrete Walks and Drives | SQYD | 52.1 |
0004 | 202-02-06120 | Removal of Curbs (Asphalt) | LNFT | 228 |
0005 | 202-02-06140 | Removal of Curbs (Concrete) | LNFT | 191 |
0006 | 202-02-14500 | Removal of Guard Rail | LNFT | 101.3 |
0007 | 202-02-38200 | Removal of Signs | EACH | 25 |
0008 | 202-02-38260 | Removal of Sign Support Footings | EACH | 1 |
0009 | 203-01-00100 | General Excavation Guard Rail Pad | CUYD | 15 |
0010 | 203-07-00100 | Borrow (Vehicular Measurement) | CUYD | 900 |
0011 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | CUYD | 837.7 |
0012 | 502-01-00100 | Asphalt Concrete | TON | 8,709 |
0013 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | TON | 585.8 |
0014 | 509-01-00100 | Milling Asphalt Pavement | SQYD | 79,402 |
0015 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | CUYD | -4,416 |
0016 | 510-01-00300 | Pavement Patching (18" Minimum Thickness) | SQYD | 14,042 |
0017 | 702-04-00150 | Adjusting Manholes w/Manhole Adjustment Rings | EACH | 11 |
0018 | 702-04-00200 | Adjusting Catch Basins | EACH | 88 |
0019 | 704-01-02000 | Guard Rail (DoubleThrie Beam) (3'-1 1/2" post spacing) | LNFT | 43.8 |
0020 | 704-01-02020 | Guard Rail (DoubleThrie Beam) (6'-3" post spacing) | LNFT | 12.5 |
0021 | 704-03-00100 | Blocked Out Guard rail | LNFT | 62.5 |
0022 | 704-05-00100 | Guard Rail Anchor Sections (Trailing End) | LNFT | 12.5 |
0023 | 706-01-00100 | Concrete Walk (4" Thick) | SQYD | 18.6 |
0024 | 706-04-00100 | Handicapped Curb Ramps TYPE 3 | EACH | 2 |
0025 | 706-04-00100 | Handicapped Curb Ramps TYPE 7 | EACH | 2 |
0026 | 707-01-00100 | Concrete Curb | LNFT | 191 |
0027 | 707-04-00100 | Asphalt Curb | LNFT | 228 |
0028 | 713-01-00100 | Temporary Signs and Barricades | LUMP | 1 |
0029 | 713-02-00300 | Temporary Pavement Markings (8" Width) | LNFT | 1,670 |
0030 | 713-02-00500 | Temporary Pavement Markings (24" Width) | LNFT | 960 |
0031 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | MILE | 9.364 |
0032 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | MILE | 9.364 |
0033 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | MILE | 21.477 |
0034 | 713-05-00200 | Temporary Pavement Legends & Symbols (Arrow - Double) | EACH | 4 |
0035 | 713-05-00220 | Temporary Pavement Legends & Symbols (Arrow - Left Turn) | EACH | 65 |
0036 | 713-05-00230 | Temporary Pavement Legends & Symbols (Arrow - Right Turn) | EACH | 3 |
0037 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | EACH | 8 |
0038 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | EACH | 4 |
0039 | 717-01-00100 | Seeding | LB | 23 |
0040 | 718-01-00100 | Fertilizer | LB | 1,150 |
0041 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | MILE | 5.36 |
0042 | 727-01-00100 | Mobilization | LUMP | 1 |
0043 | 729-01-00100 | Sign (Type A) | SQFT | 177 |
0044 | 729-02-00100 | Sign (Type B) | SQFT | 32.8 |
0045 | 729-16-00300 | Object Marker Assembly (Type 3) | EACH | 2 |
0046 | 729-19-00300 | Dead End Road Installations (Type C) | EACH | 8 |
0047 | 729-22-00100 | Square Tubing Post with 2-1/4" Anchor | EACH | 28 |
0048 | 731-02-00100 | Reflectorized Raised Pavement Markers | EACH | 882 |
0049 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | LNFT | 835 |
0050 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | LNFT | 480 |
0051 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | MILE | 10.738 |
0052 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | MILE | 4.847 |
0053 | 732-03-02010 | Plastic Pavement Striping (Dotted Line)(4" W)(2' L)(Thermo 90 mil) | MILE | 0.095 |
0054 | 732-04-01040 | Plastic Pavement Legends and Symbols (Arrow - Double) | EACH | 2 |
0055 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | EACH | 65 |
0056 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | EACH | 3 |
0057 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | EACH | 4 |
0058 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | EACH | 2 |
0059 | 736-01-00100 | Trenching and Backfilling | LNFT | 300 |
0060 | 736-09-00100 | Loop Detector | LNFT | 450 |
0061 | 736-10-00200 | Underground Junction Box (Type E) | EACH | 2 |
0062 | 736-12-00000 | Conductor (2c, Loop Lead in, imsa 50-2, #14 awg, Twisted Pair) | LNFT | 300 |
0063 | 740-01-00100 | Construction Layout | LUMP | 1 |
0064 | 741-11-00100 | Adjusting Water Valve | EACH | 32 |
0065 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | INLF | 1,200 |