M/V St. Francisville Re-Powering and 5 Year Drydock |
650-18-0010 - Ferries/ferry landings
|
Proj. Engr: Zzzz Reed, Kevin |
Route: |
|
Contractor: Bollinger Quick Repair LLC |
Miles:
| 0.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2009-08-03 |
$1,015,538 |
End of 2009 |
Landing Barge Apron Modifications (304-003 & 304-004) |
650-99-0030 - Ferries/ferry landings
|
Proj. Engr: Zzzz Reed, Kevin |
Route: |
|
Contractor: Conrad Shipyard, LLC. |
Miles:
| 0.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2010-12-06 |
$677,380 |
Spring of 2011 |