Projects Under Construction

District 04

    Updated 30 Mar 2023

Districtwide Projects

Bienville Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 154: La 507 to La 793
H.012566.6 - Asphalt surface treatment
Proj. Engr: Winget, Jason Route: LA 154 map
Contractor: Madden Contracting Co., LLC Miles: 10.14
Work Order Date Contract Amount Estimated Completion Date
2022-07-16 $5,824,882 Beginning of 2023


Bossier Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

I-20 Eb: Exit Ramp Extension at La 157
H.012913.6-R2 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Evans, Demarcion Route: I-20 map
Contractor: Earnest Contracting LLC Miles: 0.25
Work Order Date Contract Amount Estimated Completion Date
2022-07-11 $881,990 Fall of 2022


LA 3: I-220 - Kingston Rd
H.014106.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Evans, Demarcion Route: LA 3 map
Contractor: Earnest Contracting LLC Miles: 5.05
Work Order Date Contract Amount Estimated Completion Date
2022-04-14 $6,635,446 Summer of 2023


Caddo Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Caddo Lake Bridge (Hbi)
H.001166.6 - New location/replacement of bridge
Proj. Engr: Rister, Michael Route: LA 1 map
Contractor: Jensen Construction Co. Miles: 0.72
Work Order Date Contract Amount Estimated Completion Date
2021-08-23 $17,284,992 Fall of 2024


Vivian Sidewalks
H.001173.6 - Sidewalks/bike paths
Proj. Engr: Zzzz Verner, Andrew Route: LA 1 map
Contractor: C W & W Contractors, Inc. Miles: 0.02
Work Order Date Contract Amount Estimated Completion Date
2012-10-29 $484,289 Spring of 2013


Black Bayou Bridge
H.001661.6 - New location/replacement of bridge
Proj. Engr: Nelson, Michael A. Route: LA 530 map
Contractor: Wl Bass Construction Inc. Miles: 0.36
Work Order Date Contract Amount Estimated Completion Date
2020-05-24 $3,722,798 Summer of 2021


I-49 Landscaping Interchanges
H.002941.6-R1 - Landscaping
Proj. Engr: Glasgow, Andy Route: I-49 map
Contractor: H & O Investments LLC Miles: 6.32
Work Order Date Contract Amount Estimated Completion Date
2017-12-18 $995,942 Summer of 2018


LA 789: Preston Road to La 169
H.010288.6 - Asphalt widening and overlay
Proj. Engr: Rister, Michael Route: LA 789 map
Contractor: Earnest Contracting LLC Miles: 4.62
Work Order Date Contract Amount Estimated Completion Date
2022-08-02 $2,782,763 End of 2022


I-20 & US 71 Overhead Sign Upgrade
H.013854.6 - Signing
Proj. Engr: Rister, Michael Route: I-20 US 71 map
Contractor: Alpha Service and Products, In Miles: 2.86
Work Order Date Contract Amount Estimated Completion Date
2021-07-19 $2,068,273 Spring of 2023


LA 1: Left Turn Lanes at Regal Drive
H.014292.6-R1 - Concrete new pavement
Proj. Engr: Rister, Michael Route: LA 1 map
Contractor: Progressive Construction Co., Miles: 0.51
Work Order Date Contract Amount Estimated Completion Date
2022-09-05 $3,205,271 Summer of 2023


Claiborne Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 520: La 2 Alt. to La 161
H.009912.6.B - Asphalt surface treatment
Proj. Engr: North, David Route: LA 520 map
Contractor: Dreher Contracting, LLC Miles: 4.11
Work Order Date Contract Amount Estimated Completion Date
2013-06-09 $130,753 Summer of 2013


LA 9: Middle Fork Bayou and Creek Bridges
H.013942.6 - New location/replacement of bridge
Proj. Engr: Winget, Jason Route: LA 9 map
Contractor: Jb James Construction LLC Miles: 0.51
Work Order Date Contract Amount Estimated Completion Date
2022-11-01 $13,771,712 Spring of 2026


LA 518, Local: Bridges Near Athens
H.013979.6 - New location/replacement of bridge
Proj. Engr: Winget, Jason Route: LA 518 map
Contractor: Wl Bass Construction Inc. Miles: 0.34
Work Order Date Contract Amount Estimated Completion Date
2022-10-17 $5,654,319 Spring of 2024


LA 534: Bridges (La 2 to Haynesville)
H.013988.6 - New location/replacement of bridge
Proj. Engr: Winget, Jason Route: LA 534 map
Contractor: Wl Bass Construction Inc. Miles: 6.49
Work Order Date Contract Amount Estimated Completion Date
2023-02-07 $18,221,992 Spring of 2027


DeSoto Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 3276: US 171 - I-49
H.013759.6 - Asph concrete ovly over in place stabilized/cement treated base course
Proj. Engr: Jones, John Paul Route: LA 3276 map
Contractor: Earnest Contracting LLC Miles: 4.68
Work Order Date Contract Amount Estimated Completion Date
2023-02-01 $14,348,351 Beginning of 2025


Red River Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 514 & La 507: US 371 to Bienville Pl
H.011600.6 - Asphalt widening and overlay
Proj. Engr: Jones, John Paul Route: LA 514 LA 507 map
Contractor: Madden Contracting Co., LLC Miles: 4.19
Work Order Date Contract Amount Estimated Completion Date
2021-11-10 $2,908,292 Fall of 2022


LA 155: Bridges Near Coushatta
H.013986.6 - New location/replacement of bridge
Proj. Engr: Jones, John Paul Route: LA 155 map
Contractor: Brown Industrial Construction, Miles: 4.50
Work Order Date Contract Amount Estimated Completion Date
2023-01-12 $13,339,761 Fall of 2026


Webster Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Dorcheat Bayou Bridge
H.001666.6 - New location/replacement of bridge
Proj. Engr: Winget, Jason Route: LA 160 map
Contractor: Wl Bass Construction Inc. Miles: 1.00
Work Order Date Contract Amount Estimated Completion Date
2022-07-16 $9,387,832 Spring of 2026


LA 531 Overpass
H.001799.6 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: Winget, Jason Route: I-20 LA 531 map
Contractor: Jb James Construction LLC Miles: 0.80
Work Order Date Contract Amount Estimated Completion Date
2023-01-01 $19,363,531 Summer of 2025


I-20: .3 Mi E. of US 79 - La 371 Pave Mkg
H.009189.6 - Striping and pavement markers
Proj. Engr: Winget, Jason Route: I-20 map
Contractor: Nation Services Company, Inc. Miles: 2.90
Work Order Date Contract Amount Estimated Completion Date
2022-07-22 $613,749 Fall of 2022


District 04

No districtwide projects.