Districtwide Projects
Bienville Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 4: Bee Branch Bridge |
H.001537.6 - New location/replacement of bridge
|
Proj. Engr: Winget, Jason |
Route: |
LA 4
map
|
Contractor: Specialty Trackhoe & Dozer Ser |
Miles:
| 0.46 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-02-27 |
$2,270,280 |
Spring of 2021 |
LA 154: Bossier Pl to La 4 |
H.012961.6 - Asphalt surface treatment
|
Proj. Engr: Sincavage, Bernie |
Route: |
LA 154
map
|
Contractor: Dreher Contracting, LLC |
Miles:
| 8.51 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-10-02 |
$591,818 |
Beginning of 2021 |
Bossier Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
Bayou Fifi Bridge (Hbi) |
H.000118.6 - New location/replacement of bridge
|
Proj. Engr: Evans, Demarcion |
Route: |
US 80
map
|
Contractor: Specialty Trackhoe & Dozer Ser |
Miles:
| 0.37 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2019-10-05 |
$4,228,534 |
Beginning of 2022 |
I-220\i-20 Interchange Imp & Bafb Access |
H.003370.6 - New location/replacement of bridge
|
Proj. Engr: Easterly, Bruce |
Route: |
I-20 I-220
map
|
Contractor: James Construction Group LLC |
Miles:
| 3.48 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2019-04-24 |
$72,174,491 |
Summer of 2025 |
LA 529: La 160 to La 2 |
H.011599.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Evans, Demarcion |
Route: |
LA 529
map
|
Contractor: Benton & Brown, LLC. |
Miles:
| 6.74 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-10-19 |
$2,939,605 |
Summer of 2021 |
Caddo Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
Vivian Sidewalks |
H.001173.6 - Sidewalks/bike paths
|
Proj. Engr: Verner, Andrew |
Route: |
LA 1
map
|
Contractor: C W & W Contractors, Inc. |
Miles:
| 0.02 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2012-10-29 |
$484,289 |
Spring of 2013 |
Black Bayou Bridge |
H.001661.6 - New location/replacement of bridge
|
Proj. Engr: Nelson, Michael |
Route: |
LA 530
map
|
Contractor: Wl Bass Construction Inc. |
Miles:
| 0.36 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-05-24 |
$3,512,622 |
Summer of 2021 |
I-49 Landscaping Interchanges |
H.002941.6-R1 - Landscaping
|
Proj. Engr: Glasgow, Andy |
Route: |
I-49
map
|
Contractor: H & O Investments LLC |
Miles:
| 6.32 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2017-12-18 |
$995,942 |
Summer of 2018 |
Claiborne Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 520: La 2 Alt. to La 161 |
H.009912.6.B - Asphalt surface treatment
|
Proj. Engr: Zzzz North, David |
Route: |
LA 520
map
|
Contractor: Dreher Contracting, LLC |
Miles:
| 4.11 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2013-06-09 |
$130,753 |
Summer of 2013 |
DeSoto Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 5 Realignment and Cross Slope Improve |
H.001749.6 - Miscellaneous
|
Proj. Engr: Jones, John Paul |
Route: |
LA 5
map
|
Contractor: Specialty Trackhoe & Dozer Ser |
Miles:
| 3.83 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-09-21 |
$1,840,681 |
Summer of 2021 |
LA 512 & La 483: US 171 to La 175 |
H.010285.6-R1 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Jones, John Paul |
Route: |
LA 512 LA 483
map
|
Contractor: Madden Contracting Co., LLC |
Miles:
| 7.64 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-06-24 |
$5,641,461 |
Summer of 2021 |
I-49 Cb: Natchitoches P/L to La 3132 |
H.011914.6 - Miscellaneous
|
Proj. Engr: Jones, John Paul |
Route: |
I-49
map
|
Contractor: Progressive Construction Co., |
Miles:
| 41.29 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2017-07-12 |
$5,379,563 |
Beginning of 2019 |
Red River Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 507 Creek Bridge |
H.001761.6 - New location/replacement of bridge
|
Proj. Engr: Jones, John Paul |
Route: |
LA 507
map
|
Contractor: Specialty Trackhoe & Dozer Ser |
Miles:
| 0.27 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-02-26 |
$2,220,115 |
Fall of 2021 |
Webster Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 532 Over I-20 Bridge Replacement |
H.010008.6 - New location/replacement of bridge
|
Proj. Engr: Winget, Jason |
Route: |
LA 532 I-20
map
|
Contractor: Jb James Construction LLC |
Miles:
| 0.80 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-02-03 |
$8,187,326 |
Beginning of 2022 |