Districtwide Projects
Bienville Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 797: La 507 to Lincoln Pl |
H.012942.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Winget, Jason |
Route: |
LA 797
map
|
Contractor: Madden Contracting Co., LLC |
Miles:
| 3.53 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2024-06-17 |
$2,374,212 |
Fall of 2024 |
US 80: Ada - La 154 |
H.015297.6 - Asphalt surface treatment
|
Proj. Engr: Winget, Jason |
Route: |
US 80
map
|
Contractor: Brudd Construction Co., LLC |
Miles:
| 4.69 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2024-07-21 |
$478,425 |
Fall of 2024 |
District 04 Chipseals: Eastern Parishes |
H.015345.6 - Asphalt surface treatment
|
Proj. Engr: Jones, John Paul |
Route: |
LA 783 LA 519
map
|
Contractor: Brudd Construction Co., LLC |
Miles:
| 46.13 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2024-04-16 |
$3,223,011 |
Beginning of 2025 |
Bossier Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
Jimmie Davis Bridge (La 511) (Hbi) |
H.001779.6 - New location/replacement of bridge
|
Proj. Engr: Easterly, Bruce |
Route: |
LA 511
map
|
Contractor: James Construction Group LLC |
Miles:
| 1.81 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-05-15 |
$361,743,367 |
Spring of 2029 |
I20 Rehab (Pines Rd to I-220) |
H.012889.6-R1 - Concrete pavement rehab-grinding/dowell retrofit/should drain install
|
Proj. Engr: Evans, Demarcion |
Route: |
I-20
map
|
Contractor: Jb James Construction LLC |
Miles:
| 10.34 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-07-31 |
$123,163,147 |
End of 2028 |
LA 3227: Intersect Realign @ La 157 Ph 1 |
H.013492.6-R1 - Asphalt new pavement-new roadway/new alignments
|
Proj. Engr: Evans, Demarcion |
Route: |
LA 3227 LA 157
map
|
Contractor: Benton & Brown, LLC. |
Miles:
| 0.42 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-11-06 |
$4,278,216 |
Spring of 2024 |
Caddo Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
Caddo Lake Bridge (Hbi) |
H.001166.6 - New location/replacement of bridge
|
Proj. Engr: Zzzz Rister, Michael |
Route: |
LA 1
map
|
Contractor: Jensen Construction Co. |
Miles:
| 0.72 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-08-23 |
$17,365,388 |
Fall of 2024 |
Vivian Sidewalks |
H.001173.6 - Sidewalks/bike paths
|
Proj. Engr: Zzzz Verner, Andrew |
Route: |
LA 1
map
|
Contractor: C W & W Contractors, Inc. |
Miles:
| 0.02 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2012-10-29 |
$484,289 |
Spring of 2013 |
I-49 Landscaping Interchanges |
H.002941.6-R1 - Landscaping
|
Proj. Engr: Zzzz Glasgow, Andy |
Route: |
I-49
map
|
Contractor: H & O Investments LLC |
Miles:
| 6.32 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2017-12-18 |
$995,942 |
Summer of 2018 |
LA 3049: Barton Drive - Whitfield Circle |
H.012937.6 - Asphalt overlay of concrete pavement
|
Proj. Engr: Nelson, Michael A. |
Route: |
LA 3049
map
|
Contractor: Benton & Brown, LLC. |
Miles:
| 4.16 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2024-09-08 |
$3,454,394 |
Beginning of 2025 |
LA 173: Left Turn Lanes at Russell Road |
H.015005.6 - Traffic flow improvements - formerly turn lanes
|
Proj. Engr: Nelson, Michael A. |
Route: |
LA 173
map
|
Contractor: T.L. Construction LLC |
Miles:
| 0.63 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2024-04-08 |
$965,709 |
Summer of 2024 |
LA 3132: I-20 - US 171 Signing |
H.015255.6 - Signing
|
Proj. Engr: Krug, Claudia |
Route: |
LA 3132
map
|
Contractor: Alpha Service and Products, In |
Miles:
| 5.18 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2024-06-17 |
$6,802,910 |
Summer of 2027 |
I-220: I-20 E to I-20 W Pavement Markings |
H.015629.6 - Striping and pavement markers
|
Proj. Engr: Nelson, Michael A. |
Route: |
I-220
map
|
Contractor: Nation Services Company, Inc. |
Miles:
| 18.11 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2024-08-07 |
$1,249,036 |
End of 2024 |
Claiborne Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 520: La 2 Alt. to La 161 |
H.009912.6.B - Asphalt surface treatment
|
Proj. Engr: North, David |
Route: |
LA 520
map
|
Contractor: Dreher Contracting, LLC |
Miles:
| 4.11 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2013-06-09 |
$130,753 |
Summer of 2013 |
LA 9: Middle Fork Bayou and Creek Bridges |
H.013942.6 - New location/replacement of bridge
|
Proj. Engr: Winget, Jason |
Route: |
LA 9
map
|
Contractor: Jb James Construction LLC |
Miles:
| 0.51 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-11-01 |
$14,046,958 |
Spring of 2026 |
LA 518, Local: Bridges Near Athens |
H.013979.6 - New location/replacement of bridge
|
Proj. Engr: Winget, Jason |
Route: |
LA 518
map
|
Contractor: Wl Bass Construction Inc. |
Miles:
| 0.34 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-10-17 |
$5,725,257 |
Spring of 2024 |
LA 521: Bridges Near Dykesville |
H.013987.6 - New location/replacement of bridge
|
Proj. Engr: Winget, Jason |
Route: |
LA 521
map
|
Contractor: Specialty Trackhoe & Dozer Ser |
Miles:
| 0.46 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2024-02-22 |
$6,088,427 |
Fall of 2025 |
LA 534: Bridges (La 2 to Haynesville) |
H.013988.6 - New location/replacement of bridge
|
Proj. Engr: Winget, Jason |
Route: |
LA 534
map
|
Contractor: Wl Bass Construction Inc. |
Miles:
| 6.49 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-02-07 |
$18,395,165 |
Spring of 2027 |
DeSoto Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 5: Thomas Road to La 172 |
H.012227.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Jones, John Paul |
Route: |
LA 5
map
|
Contractor: Earnest Contracting LLC |
Miles:
| 11.04 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-09-30 |
$15,389,994 |
Summer of 2025 |
LA 3248: Naborton Loop |
H.012982.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Jones, John Paul |
Route: |
LA 3248
map
|
Contractor: Madden Contracting Co., LLC |
Miles:
| 3.66 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2024-05-05 |
$2,448,405 |
Fall of 2024 |
LA 3276: US 171 - I-49 |
H.013759.6 - Asph concrete ovly over in place stabilized/cement treated base course
|
Proj. Engr: Jones, John Paul |
Route: |
LA 3276
map
|
Contractor: Earnest Contracting LLC |
Miles:
| 4.68 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-02-01 |
$15,422,093 |
Beginning of 2025 |
Red River Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 155: Bridges Near Coushatta |
H.013986.6 - New location/replacement of bridge
|
Proj. Engr: Jones, John Paul |
Route: |
LA 155
map
|
Contractor: Brown Industrial Construction, |
Miles:
| 4.50 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-01-12 |
$13,835,916 |
Beginning of 2027 |
LA 507, La 514, Local: Bayou and Cr Brs |
H.013995.6-R1 - New location/replacement of bridge
|
Proj. Engr: Murphy, Michael |
Route: |
LA 507 LA 514
map
|
Contractor: Apeck Construction, LLC |
Miles:
| 0.89 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2024-04-14 |
$12,059,356 |
Spring of 2028 |
US 71: US 371 - La 515 |
H.015274.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Jones, John Paul |
Route: |
US 71
map
|
Contractor: Benton & Brown, LLC. |
Miles:
| 5.09 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2024-07-07 |
$2,948,139 |
Beginning of 2025 |
Webster Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
Dorcheat Bayou Bridge |
H.001666.6 - New location/replacement of bridge
|
Proj. Engr: Winget, Jason |
Route: |
LA 160
map
|
Contractor: Wl Bass Construction Inc. |
Miles:
| 1.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-07-16 |
$9,400,591 |
Spring of 2026 |
LA 531 Overpass |
H.001799.6 - Asphalt new pavement-new roadway/new alignments
|
Proj. Engr: Winget, Jason |
Route: |
I-20 LA 531
map
|
Contractor: Jb James Construction LLC |
Miles:
| 0.80 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-01-01 |
$20,570,982 |
Summer of 2025 |
I-20: .3 Mi E. of US 79 - La 371 Pave Mkg |
H.009189.6 - Striping and pavement markers
|
Proj. Engr: Winget, Jason |
Route: |
I-20
map
|
Contractor: Nation Services Company, Inc. |
Miles:
| 2.90 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-07-22 |
$613,749 |
Fall of 2022 |
District 04
No districtwide projects.