Districtwide Projects
Bienville Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 516: Jct US 371 - La 792 |
H.013000.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Winget, Jason |
Route: |
LA 516
map
|
Contractor: Madden Contracting Co., LLC |
Miles:
| 3.63 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-05-15 |
$2,879,971 |
Fall of 2023 |
Bossier Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
Jimmie Davis Bridge (La 511) (Hbi) |
H.001779.6 - New location/replacement of bridge
|
Proj. Engr: Easterly, Bruce |
Route: |
LA 511
map
|
Contractor: James Construction Group LLC |
Miles:
| 1.81 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-05-15 |
$361,743,367 |
Spring of 2029 |
I20 Rehab (Pines Rd to I-220) |
H.012889.6-R1 - Concrete pavement rehab-grinding/dowell retrofit/should drain install
|
Proj. Engr: Evans, Demarcion |
Route: |
I-20
map
|
Contractor: Jb James Construction LLC |
Miles:
| 10.34 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-07-31 |
$117,978,438 |
Summer of 2028 |
I-20 Eb: Exit Ramp Extension at La 157 |
H.012913.6-R2 - Traffic flow improvements - formerly turn lanes
|
Proj. Engr: Evans, Demarcion |
Route: |
I-20
map
|
Contractor: Earnest Contracting LLC |
Miles:
| 0.25 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-07-11 |
$882,884 |
Fall of 2022 |
LA 3: I-220 - Kingston Rd |
H.014106.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Evans, Demarcion |
Route: |
LA 3
map
|
Contractor: Earnest Contracting LLC |
Miles:
| 5.05 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-04-14 |
$6,640,906 |
Summer of 2023 |
Caddo Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
Caddo Lake Bridge (Hbi) |
H.001166.6 - New location/replacement of bridge
|
Proj. Engr: Rister, Michael |
Route: |
LA 1
map
|
Contractor: Jensen Construction Co. |
Miles:
| 0.72 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-08-23 |
$17,284,992 |
Fall of 2024 |
Vivian Sidewalks |
H.001173.6 - Sidewalks/bike paths
|
Proj. Engr: Zzzz Verner, Andrew |
Route: |
LA 1
map
|
Contractor: C W & W Contractors, Inc. |
Miles:
| 0.02 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2012-10-29 |
$484,289 |
Spring of 2013 |
I-49 Landscaping Interchanges |
H.002941.6-R1 - Landscaping
|
Proj. Engr: Zzzz Glasgow, Andy |
Route: |
I-49
map
|
Contractor: H & O Investments LLC |
Miles:
| 6.32 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2017-12-18 |
$995,942 |
Summer of 2018 |
I-20 & US 71 Overhead Sign Upgrade |
H.013854.6 - Signing
|
Proj. Engr: Rister, Michael |
Route: |
I-20 US 71
map
|
Contractor: Alpha Service and Products, In |
Miles:
| 2.86 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-07-19 |
$2,078,553 |
Spring of 2023 |
US 171: Caddo P/L - La 3132 |
H.014110.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Nelson, Michael A. |
Route: |
US 171
map
|
Contractor: Earnest Contracting LLC |
Miles:
| 8.82 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-04-10 |
$10,061,517 |
Summer of 2024 |
LA 1: Left Turn Lanes at Regal Drive |
H.014292.6-R1 - Concrete new pavement
|
Proj. Engr: Rister, Michael |
Route: |
LA 1
map
|
Contractor: Progressive Construction Co., |
Miles:
| 0.51 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-09-05 |
$3,229,370 |
Summer of 2023 |
LA 523: Left Turn Lanes at Ashley Ridge |
H.014754.6 - Concrete new pavement
|
Proj. Engr: Rister, Michael |
Route: |
LA 523
map
|
Contractor: Progressive Construction Co., |
Miles:
| 0.44 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-05-15 |
$838,664 |
Fall of 2023 |
LA 3094: Hearne Ave Bridge Interim Repair |
H.014942.6 - Bridges reconditioned
|
Proj. Engr: Nelson, Michael A. |
Route: |
LA 3094
map
|
Contractor: C.E.C., Inc. |
Miles:
| 0.05 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-04-17 |
$297,000 |
Fall of 2023 |
Claiborne Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 520: La 2 Alt. to La 161 |
H.009912.6.B - Asphalt surface treatment
|
Proj. Engr: North, David |
Route: |
LA 520
map
|
Contractor: Dreher Contracting, LLC |
Miles:
| 4.11 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2013-06-09 |
$130,753 |
Summer of 2013 |
LA 9: Middle Fork Bayou and Creek Bridges |
H.013942.6 - New location/replacement of bridge
|
Proj. Engr: Winget, Jason |
Route: |
LA 9
map
|
Contractor: Jb James Construction LLC |
Miles:
| 0.51 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-11-01 |
$13,771,712 |
Spring of 2026 |
LA 518, Local: Bridges Near Athens |
H.013979.6 - New location/replacement of bridge
|
Proj. Engr: Winget, Jason |
Route: |
LA 518
map
|
Contractor: Wl Bass Construction Inc. |
Miles:
| 0.34 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-10-17 |
$5,736,057 |
Spring of 2024 |
LA 534: Bridges (La 2 to Haynesville) |
H.013988.6 - New location/replacement of bridge
|
Proj. Engr: Winget, Jason |
Route: |
LA 534
map
|
Contractor: Wl Bass Construction Inc. |
Miles:
| 6.49 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-02-07 |
$18,396,793 |
Spring of 2027 |
DeSoto Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 3276: US 171 - I-49 |
H.013759.6 - Asph concrete ovly over in place stabilized/cement treated base course
|
Proj. Engr: Jones, John Paul |
Route: |
LA 3276
map
|
Contractor: Earnest Contracting LLC |
Miles:
| 4.68 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-02-01 |
$14,472,843 |
Beginning of 2025 |
Red River Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 155: Bridges Near Coushatta |
H.013986.6 - New location/replacement of bridge
|
Proj. Engr: Jones, John Paul |
Route: |
LA 155
map
|
Contractor: Brown Industrial Construction, |
Miles:
| 4.50 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-01-12 |
$13,339,761 |
Fall of 2026 |
Webster Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
Dorcheat Bayou Bridge |
H.001666.6 - New location/replacement of bridge
|
Proj. Engr: Winget, Jason |
Route: |
LA 160
map
|
Contractor: Wl Bass Construction Inc. |
Miles:
| 1.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-07-16 |
$9,427,919 |
Spring of 2026 |
LA 531 Overpass |
H.001799.6 - Asphalt new pavement-new roadway/new alignments
|
Proj. Engr: Winget, Jason |
Route: |
I-20 LA 531
map
|
Contractor: Jb James Construction LLC |
Miles:
| 0.80 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-01-01 |
$19,513,417 |
Summer of 2025 |
I-20: .3 Mi E. of US 79 - La 371 Pave Mkg |
H.009189.6 - Striping and pavement markers
|
Proj. Engr: Winget, Jason |
Route: |
I-20
map
|
Contractor: Nation Services Company, Inc. |
Miles:
| 2.90 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-07-22 |
$613,749 |
Fall of 2022 |
District 04
No districtwide projects.